Hot testing of first San’ao unit completed

Tuesday, 17 June 2025

Hot testing of first San'ao unit completed
(Image: CGN)

Hot functional tests involve increasing the temperature of the reactor coolant system and carrying out comprehensive tests to ensure that coolant circuits and safety systems are operating as they should. Carried out before the loading of nuclear fuel, such testing simulates the thermal working conditions of the power plant and verifies that nuclear island and conventional equipment and systems meet design requirements.

China General Nuclear (CGN) said the completion of hot test at San’ao unit 1 on 10 June “lays the foundation for subsequent reactor loading, grid-connected power generation and commercial operation”.

Cold functional tests – which are carried out to confirm whether components and systems important to safety are properly installed and ready to operate in a cold condition – were completed at San’ao 1 in November last year. The main purpose of those tests – which marked the first time the reactor systems were operated together with the auxiliary systems – was to verify the leak-tightness of the primary circuit.


The San’ao plant site (Image: CGN)

In May 2015, the National Energy Administration approved the project to carry out site protection and related demonstration work at San’ao. On 2 September 2020, the executive meeting of the State Council approved the construction of units 1 and 2 as the first phase of the plant. China’s National Nuclear Safety Administration issued a construction permit for the two units on 30 December that year and first concrete for unit 1 was poured the following day. The first concrete for San’ao 2 was poured on 30 December 2021.

San’ao 1 and 2 are scheduled to begin supplying electricity in 2026 and 2027, respectively.

The San’ao plant is the first nuclear power project in China’s Yangtze River Delta region to adopt the Hualong One reactor design. A total of six Hualong One units are planned for the San’ao site. In August 2024, the State Council approved the construction of San’ao Phase II (units 3 and 4).

The San’ao project marks the first Chinese nuclear power project involving private capital, with Geely Technology Group taking a 2% stake in the plant. CGN holds 46% of the shares of the project company Cangnan Nuclear Power, with other state-owned enterprises holding the remainder.

   

  • Related Posts

    Viewpoint: IAEA’s non-proliferation safeguards and industry’s role

    What are nuclear safeguards? Nuclear safeguards are technical measures applied to verify that nuclear material in peaceful activities is not diverted to nuclear weapons. Implemented in 192 States, International Atomic Energy…

    Approval for VVER fuel production in Germany

    Framatome subsidiary Advanced Nuclear Fuels (ANF) applied in March 2022 under the Atomic Energy Act for permission to begin producing hexagonal pressurised water fuel elements under licence with TVEL, the…

    Have You Seen?

    Most Gulf Coast Refineries Unaffected by Tropical Storm Bertha

    • July 25, 2026
    Most Gulf Coast Refineries Unaffected by Tropical Storm Bertha

    CG Power Reports Record Q1 FY27 Revenue and Profit as Order Book Surges 45% to INR 17,333 Crore

    • July 25, 2026
    CG Power Reports Record Q1 FY27 Revenue and Profit as Order Book Surges 45% to INR 17,333 Crore

    US Energy Firms Cut Rigs for First Time in Six Weeks, Says Baker Hughes

    • July 25, 2026
    US Energy Firms Cut Rigs for First Time in Six Weeks, Says Baker Hughes

    Oil Falls on Report China Pushing for End US-Iran War

    • July 25, 2026
    Oil Falls on Report China Pushing for End US-Iran War

    PERSPECTIVE: Wind and Solar Have an Important Role – But They Are Energy “Diversification”, Not Energy “Transition”

    • July 25, 2026
    PERSPECTIVE: Wind and Solar Have an Important Role – But They Are Energy “Diversification”, Not Energy “Transition”

    Devon Energy Mulls $4 Billion Sale of Eagle Ford, Powder River Assets, Bloomberg News Reports

    • July 25, 2026
    Devon Energy Mulls $4 Billion Sale of Eagle Ford, Powder River Assets, Bloomberg News Reports

    LONGi Partners with Innoptus and Delft Solar Teams for 2026 American Solar Challenge

    • July 25, 2026
    LONGi Partners with Innoptus and Delft Solar Teams for 2026 American Solar Challenge

    Adani Power Reports Record Q1 FY27 EBITDA as Revenue Rises 28%, Advances 45 GW Capacity Expansion

    • July 25, 2026
    Adani Power Reports Record Q1 FY27 EBITDA as Revenue Rises 28%, Advances 45 GW Capacity Expansion

    Actis Secures IFC, Proparco Investment for Ulug Enerji Grid Upgrades

    • July 25, 2026
    Actis Secures IFC, Proparco Investment for Ulug Enerji Grid Upgrades

    Global LNG Giants Target Cambodia as New Energy Market

    • July 24, 2026
    Global LNG Giants Target Cambodia as New Energy Market