Rooppur 1 hot testing under way

Thursday, 17 July 2025

The first nuclear power unit at the Rooppur nuclear power plant in Bangladesh is undergoing hot tests as the next stage of the commissioning process.

Rooppur 1 hot testing under way
(Image: ASE-Rosatom)

According to AtomStroyExport (ASE), part of Rosatom, “during the tests, the reactor unit is heated up, and our specialists check step-by-step how key elements operate under these conditions: pumps, pipelines, heat exchange equipment. It is important to record how the equipment behaves under load – after all, it will be the one that will ensure reliable operation of the plant later”.

The hot testing is designed as a general check of the reliability of the reactor unit “before moving on to the next, more important stages … and shows where the system is ready to function under conditions close to real operation”.

Leak tests on the containment building for Rooppur 1 were successfully completed last month.

Step-up transformers and auxiliary transformers were also commissioned for the unit at the end of June – the step-up transformers convert the voltage generated by the turbogenerator, 24 kV,  into 400 kV to supply electricity to the national grid. They are capable of transmitting a total of up to 1599 MW of power, which is more than the 1200 MW capacity of the unit.

The Rooppur project

In February 2011 Russia’s Rosatom signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first unit began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 – the moment that the site got its status as a nuclear facility. In March Rooppur unit 1’s turbine installation was completed, as were hydraulic tests to check the primary circuit systems and equipment, paving the way for hot functional tests to begin. Rosatom has included grid connection for Rooppur unit 1 as one of its key targets for the current year.

   

  • Related Posts

    Dismantling of reactor channels to begin at second Ignalina unit

    In accordance with the approved technical design, the steam-water discharge piping at the top of the reactor and the water supply piping at the bottom of the reactor, as well…

    ČEZ eyeing 80-year operation of Dukovany units

    ČEZ currently operates four VVER-440 units at Dukovany, which began operating between 1985 and 1987. Their output has gradually been increased from the original 440 MWe to 512 MWe through…

    Have You Seen?

    Recalibration and resilience to go the distance

    • April 11, 2026
    Recalibration and resilience to go the distance

    Vance Warns Iran Not to “Play Us” as He Prepares for Talks

    • April 11, 2026
    Vance Warns Iran Not to “Play Us” as He Prepares for Talks

    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    • April 11, 2026
    Northern Vietnam Power Utility Accelerates Grid Upgrades And Rooftop Solar Push To Meet Rising Demand

    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    • April 11, 2026
    GSECL Seeks GERC Approval For Tariff Of 25 MW Palitana Solar Project In Gujarat

    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    • April 11, 2026
    SECI Invites Bids For 4.45 MW Rooftop Solar Projects Across India Under RESCO Model

    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    • April 11, 2026
    SECI Seeks ₹660 Crore Loan For 200 MW Solar Project In Madhya Pradesh

    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    • April 11, 2026
    India’s Power Sector Roadmap 2026–2036 Balancing Renewable Growth With Grid Reliability – CEA

    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    • April 11, 2026
    Global Renewable Energy Hits 49% Capacity In 2025 As Solar Leads Record Growth – RE Statistics 2026

    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    • April 11, 2026
    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    • April 10, 2026
    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022