Work starts on Pele microreactor core

Friday, 25 July 2025

Fabrication of the reactor core for the Project Pele prototype mobile microreactor – the first microreactor to be built and operated in the USA – has begun at  BWX Technologies’ Innovation Campus in Lynchburg, Virginia.

Work starts on Pele microreactor core
Pele prototype core reactor assembly (Image: BWXT)

Project Pele was launched in 2019 with the objective of designing, building, and demonstrating a prototype mobile nuclear reactor within five years. The initiative is led by the Department of Defense’s Strategic Capabilities Office, which is working in collaboration with the US Department of Energy (DOE), the Nuclear Regulatory Commission and the US Army Corps of Engineers, as well as with industry partners.

BWXT Advanced Technologies and X-energy LLC were subsequently selected to develop a final design for a prototype mobile high-temperature gas reactor using high-assay low-enriched uranium (HALEU) tristructural isotropic (TRISO) fuel under the Project Pele initiative. BWXT was contracted in June 2022 to build a prototype 1.5 MWe microreactor. The contractor team also includes critical roles played by Northrop Grumman, Rolls Royce Liberty Works, and Torch Technologies. The fuel for the reactor will be produced at BWXT’s facilities using material from the DOE’s highly-enriched uranium inventory.

BWXT has now announced the start of work on the reactor core.


A rendering of the Pele microreactor (Image: BWXT)

“We are proud to develop and deliver the Pele microreactor for the benefit of our armed forces,” said BWXT Advanced Technologies President Kate Kelly. “This is a tremendous achievement for the BWXT team and for the advancement of groundbreaking nuclear energy technology as a reliable, resilient source of electricity and heat for multiple applications.”

The prototype reactor facility is designed to be transported within four 20-foot shipping containers, and tested at Idaho National Laboratory’s (INL’s) Critical Infrastructure Test Range Complex. The technology is expected to begin producing electricity in 2028.

BWXT said it has completed fabricating the TRISO nuclear fuel for the reactor and will ship it to INL in the months ahead.

Northrop Grumman is providing the control module for the reactor, while Rolls-Royce is developing the power conversion module at its Liberty Works facility in Indianapolis, Indiana.

   

  • Related Posts

    Westinghouse teams up with Hyundai E&C for Dutch FEED studies

    In August, EDF and Westinghouse were awarded contracts by the Nuclear Energy Organisation of the Netherlands (NEO NL) – the state-owned company established for the construction and operation of the…

    China’s Tianwan 7 connected to the grid

    The delivery of the first electricity to the grid from the VVER-1200 reactor on 8 October took place just over a week after it achieved a self-sustaining controlled nuclear chain reaction…

    Have You Seen?

    Gevo delivers 10,000 CDR credits from North Dakota BECCS facility

    • October 8, 2026
    Gevo delivers 10,000 CDR credits from North Dakota BECCS facility

    GCE opens India medical gas centre amid healthcare infrastructure expansion

    • October 8, 2026
    GCE opens India medical gas centre amid healthcare infrastructure expansion

    First Deep-Gulf Tanker Attack in Nearly a Month Hits Vessel off Qatar

    • October 8, 2026
    First Deep-Gulf Tanker Attack in Nearly a Month Hits Vessel off Qatar

    India’s Inflation Likely Hit 5.4% in September as Oil Costs Bite

    • October 8, 2026
    India’s Inflation Likely Hit 5.4% in September as Oil Costs Bite

    Equinor Finds New Gas at Norway’s 40-Year-Old Gullfaks Field

    • October 8, 2026
    Equinor Finds New Gas at Norway’s 40-Year-Old Gullfaks Field

    EIA Boosts Oil Price Forecast by $5 in 2026, $10 in 2027

    • October 8, 2026
    EIA Boosts Oil Price Forecast by $5 in 2026, $10 in 2027

    Video | What space needs from the gases industry

    • October 8, 2026
    Video | What space needs from the gases industry

    Hormuz Tanker Traffic Hits Two-Month Low as Attacks Surge

    • October 8, 2026
    Hormuz Tanker Traffic Hits Two-Month Low as Attacks Surge

    Big Oil Begins Shutting In Gulf of Mexico Production

    • October 8, 2026
    Big Oil Begins Shutting In Gulf of Mexico Production

    Air Liquide targets 2028 start-up of Sydney ASU

    • October 8, 2026
    Air Liquide targets 2028 start-up of Sydney ASU