CERC Forms Committee To Evaluate SCOD Extensions For Renewable And Storage Projects

Representational image. Credit: Canva

The Central Electricity Regulatory Commission (CERC) issued an office order on July 30, 2025, to constitute a committee for recommending extensions in the Scheduled Commercial Operation Date (SCOD) of certain renewable energy and energy storage projects. This is in reference to Regulation 13(2)(h) of the amended CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2020, which were published on July 4, 2025.

According to the revised regulation, renewable energy generating stations (REGS) based on wind, solar, or hybrid sources, and Battery Energy Storage Systems (ESS), which are eligible for inter-state transmission charge waivers and have their SCOD on or before June 30, 2025, can seek an extension if they fail to meet the timeline due to Force Majeure events or reasons beyond their control. If the project achieves COD within the extended time, it will still qualify for the waiver as if it had been commissioned by June 30, 2025.

Such extensions can be granted up to a maximum of two times, each not exceeding six months. In cases where there is no Power Purchase Agreement under Section 63 of the Electricity Act, the CERC will decide on the extension based on the recommendation of a designated committee.

The committee includes Sh. Indu Shekhar Jha (Ex-Member, CERC) as Chairman, Ms. Anjuli Chandra (Ex-Member, PSERC), Sh. A.K. Rajput (Ex-Member, CEA), and the COO of CTUIL, as the Convenor. They may also co-opt other experts if needed, and secretarial support will be provided by CTUIL.

The extension process involves three steps. First, the REGS or ESS must apply to the Committee with all relevant documents and send a copy to the buyer, if applicable. The application should be sent to CTUIL at its Gurugram office. Second, the Committee will analyze and conduct prudence checks before submitting its recommendation to the Commission within three months. Third, the Commission will issue an order accepting or rejecting the extension.

The Committee’s term is 18 months from the date of the order or until a further order is issued, whichever is earlier. Retired members of the committee will receive per-sitting remuneration following Regulation 60A of the Conduct of Business Regulations.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Vietnam Faces Rooftop Solar Curtailment Amid Grid Constraints

    Representational image. Credit: Canva Vietnam is facing a new challenge in managing its rapidly growing rooftop solar power sector. The Vietnam Electricity Group (EVN) and the National Load Dispatch Center…

    Genex Technocrats LLP Recognised with Technology of the Year – AI-Based Solar Monitoring Award at India Solar Week 2026

    At India Solar Week 2026, held on 18–19 February 2026, Genex Technocrats LLP was recognised with the Technology of the Year – AI-Based Solar Monitoring Award, celebrating its advancements in…

    Have You Seen?

    Surveys begin on Australian natural hydrogen and helium project

    • April 13, 2026
    Surveys begin on Australian natural hydrogen and helium project

    US firm claims DAC cost breakthrough, but questions remain over scale

    • April 13, 2026
    US firm claims DAC cost breakthrough, but questions remain over scale

    Vietnam Faces Rooftop Solar Curtailment Amid Grid Constraints

    • April 13, 2026
    Vietnam Faces Rooftop Solar Curtailment Amid Grid Constraints

    Genex Technocrats LLP Recognised with Technology of the Year – AI-Based Solar Monitoring Award at India Solar Week 2026

    • April 13, 2026
    Genex Technocrats LLP Recognised with Technology of the Year – AI-Based Solar Monitoring Award at India Solar Week 2026

    Citicore Launches Pangasinan Solar Plant, Boosts Philippines Clean Energy Capacity

    • April 13, 2026
    Citicore Launches Pangasinan Solar Plant, Boosts Philippines Clean Energy Capacity

    Trump Vows Hormuz Blockade after Failed Talks

    • April 13, 2026
    Trump Vows Hormuz Blockade after Failed Talks

    Australian 1.5GW green hydrogen project joins federal fast-track programme

    • April 13, 2026
    Australian 1.5GW green hydrogen project joins federal fast-track programme

    New International Renewable Energy Agency Report Highlights How Clean Energy Is Reducing Fossil Fuel Dependence Worldwide

    • April 13, 2026
    New International Renewable Energy Agency Report Highlights How Clean Energy Is Reducing Fossil Fuel Dependence Worldwide

    Cement plants emerge as strategic CO2 source for e-fuels

    • April 13, 2026
    Cement plants emerge as strategic CO2 source for e-fuels

    Kusile Power Station Reaches Full Capacity, Boosting South Africa’s Energy Security

    • April 13, 2026
    Kusile Power Station Reaches Full Capacity, Boosting South Africa’s Energy Security