Steam generator marks milestone for Indian fleet construction

The completion of this major component was hailed by Nuclear Power Corporation of India Ltd (NPCIL) as a “significant step” for India’s nuclear expansion.

“Manufactured and dispatched seven months ahead of schedule, this Steam Generator underscores the capability of India’s industry to deliver critical nuclear components with speed and quality,” the company said.

“As NPCIL spearheads the fleet of 10 indigenously designed 700 MWe PHWRs, this achievement strengthens the foundation of our proactive expansion strategy and reinforces our commitment to India’s vision of 100 GWe nuclear power capacity by 2047, ensuring reliable, clean and sustainable energy for a Viksit Bharat.” (Viksit Bharat is the government’s strategy to make India into a completely developed nation by 2047)


The flagging off ceremony (Image: NPCIL)

Steam generators are heat exchangers which convert heat generated by the reactor core from the reactor coolant into steam to power the turbogenerator. The reactor coolant system is known as the primary circuit; the system in which the steam is produced is the secondary circuit.

The Gorakhpur plant – its full name is Gorakhpur Haryana Anu Vidyut Pariyojana, sometimes abbreviated to GHAVP – will be home to four 700 MWe Indian-designed pressurised heavy water reactors, or PHWRs. These are to be built in two phases. India’s Atomic Energy Regulatory Board (AERB) granted a siting licence in 2015, and the government accorded administrative approval and financial sanction for the first two units in 2014. Gorakhpur units 3 and 4 are among ten 700 MWe PHWRs accorded administrative approval and financial sanction by the government in 2018, for construction in “fleet” mode.

Excavation work for Gorakhpur units 1 and 2 began at the site in 2018, and construction of peripheral buildings and structures is under way, although work on the main nuclear island has been delayed because of the need for extra ground stabilisation. According to recent written answers to the Indian parliament, the first two units are now pencilled in for completion by 2031-32.

   

  • Related Posts

    NPCIL signs MoU for Gujarat nuclear power projects

    In what it called “a significant step towards exploring new horizons for nuclear power development in Gujarat”, Nuclear Power Corporation of India Limited (NPCIL) said the MoU would “facilitate collaboration between…

    Hinkley Point B becomes second AGR plant transferred for decommissioning

    Hinkley Point B – comprising two Advanced Gas-cooled Reactors (AGRs) – was first synchronised to the electricity grid in February 1976. The plant generated more than 311 terawatt-hours of electricity…

    Have You Seen?

    OPEC+ holds November oil production targets steady as supply remains constrained

    • October 4, 2026
    OPEC+ holds November oil production targets steady as supply remains constrained

    Japan’s JERA Creates Oil Storage Firm to Manage National Reserve Sites

    • October 2, 2026
    Japan’s JERA Creates Oil Storage Firm to Manage National Reserve Sites

    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    • October 2, 2026
    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    • October 2, 2026
    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    Latest Dallas Fed Survey Reveals Theme Among Respondents

    • October 2, 2026
    Latest Dallas Fed Survey Reveals Theme Among Respondents

    What is the near-term feasibility of helium-3 fuel for fusion power?

    • October 2, 2026
    What is the near-term feasibility of helium-3 fuel  for fusion power?

    UN Says Global Fuel Subsidies Could Top $1 Trillion

    • October 2, 2026
    UN Says Global Fuel Subsidies Could Top $1 Trillion

    JERA CEO Warns LNG Prices Have Further to Climb

    • October 2, 2026
    JERA CEO Warns LNG Prices Have Further to Climb

    Scaling up: Blue Star’s next phase in Colorado

    • October 2, 2026
    Scaling up: Blue Star’s next phase in Colorado

    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    • October 2, 2026
    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant