Inner containment construction set to begin for Leningrad’s seventh unit

Pre-assembly and welding of the first tier of the inner containment has been taking place over the past few weeks next to the reactor building site and Rosenergoatom – part of Rosatom – said it will soon be ready for installation.

It is planned to begin the work on installing the first tier – to be followed by concreting and subsequent tiers of the inner containment building – during September, with the entire process expected to last for two and a half years with the entire structure due to be completed, with dome, in 2028.

Evgeny Milushkin from Leningrad NPP-2 said the inner containment would comprise a “concrete structure more than a metre thick, reinforced for strength with steel … the inner protective shell will prevent radioactive substances and ionising radiation from leaving the reactor building. This means that the personnel of the nuclear power plant, the population living next to it and the environment will be safe”.

There will also be a second, external containment building, which will “protect the reactor, steam generators and other important equipment from extreme external natural and man-made influences” including hurricanes, plane crashes or earthquakes.

Background

The Leningrad nuclear power plant is one of the largest in Russia, with an installed capacity of 4400 MWe, and provides more than 55% of the electricity demand of St Petersburg and the Leningrad region, or 30% of all the electricity in northwest Russia.

Leningrad 1 shut down in 2018 after 45 years of operation. Leningrad 2, also a 1000 MWe RBMK unit, started up in 1975 and was permanently shut down in November 2020. As the first two of the plant’s four RBMK-1000 units shut down, new VVER-1200 units started at the neighbouring Leningrad II plant. The 60-year service life of these fifth and sixth units (also known as Leningrad II-1 and Leningrad II-2) secures power supply until the 2080s. Units 7 and 8 (also known as Leningrad II-3 and Leningrad II-4) will replace units 3 and 4 as they are shut in the coming years.

The pouring of the first concrete for unit 7 in March 2024 marked the start of the main phase of construction of the new power unit, which is expected to generate power for 60 years, with the possibility of a 20-year extension.

   

  • Related Posts

    Polish companies team up for regional SMR deployment

    The memorandum of understanding (MoU) aims to facilitate collaboration between the companies and establish working groups to jointly explore potential projects in Central and Eastern Europe. These activities will include…

    Reactor vessel installed at Lianjiang unit 2

    State Power Investment Corp (SPIC) said the reactor pressure vessel of unit 2 was successfully hoisted into place on Wednesday, “marking the start of the equipment installation phase for both…

    Have You Seen?

    US Intelligence Warns Iran Unlikely to Ease Hormuz Strait Chokehold Soon

    • April 4, 2026
    US Intelligence Warns Iran Unlikely to Ease Hormuz Strait Chokehold Soon

    MnSEIA, SEIA, And CCSA Criticize Minnesota’s Approval Of Xcel’s 200 MW Battery Program, Warning Of Risks To Ratepayers

    • April 4, 2026
    MnSEIA, SEIA, And CCSA Criticize Minnesota’s Approval Of Xcel’s 200 MW Battery Program, Warning Of Risks To Ratepayers

    Victron Energy Demonstrates Integrated Energy Solutions at Solar & Storage Live Africa 2026 in Johannesburg

    • April 4, 2026
    Victron Energy Demonstrates Integrated Energy Solutions at Solar & Storage Live Africa 2026 in Johannesburg

    Brazil Advances Tangará Project: New Transformers And 500 kV Line Upgrade Boost Reliability In Maranhão And Pará

    • April 4, 2026
    Brazil Advances Tangará Project: New Transformers And 500 kV Line Upgrade Boost Reliability In Maranhão And Pará

    Smarter Power, Brighter Africa: Pylontech Deepens Presence in South Africa with All-Scenario Solutions and Local Service Center

    • April 4, 2026
    Smarter Power, Brighter Africa: Pylontech Deepens Presence in South Africa with All-Scenario Solutions and Local Service Center

    HD Hyundai Energy Solutions Secures $85 Million Module Supply Deal for U.S. Solar Project

    • April 4, 2026
    HD Hyundai Energy Solutions Secures $85 Million Module Supply Deal for U.S. Solar Project

    Trump Says US Can Take Strait of Hormuz With More Time, Take the Oil and Make a Fortune

    • April 3, 2026
    Trump Says US Can Take Strait of Hormuz With More Time, Take the Oil and Make a Fortune

    China Sets 2029 Deadline to Shut Down Outdated Petrochemical Plants

    • April 3, 2026
    China Sets 2029 Deadline to Shut Down Outdated Petrochemical Plants

    India Passes on Iranian Oil as Sanctioned Tanker Redirects to China

    • April 3, 2026
    India Passes on Iranian Oil as Sanctioned Tanker Redirects to China

    India’s Russian Crude Imports Jump 90% in March After U.S. Waiver

    • April 3, 2026
    India’s Russian Crude Imports Jump 90% in March After U.S. Waiver