Tepco to remove fuel from Kashiwazaki-Kariwa 7

Tepco applied for Nuclear Regulation Authority (NRA) approval of its design and construction plan for Kashiwazaki-Kariwa units 6 and 7 in September 2013. It submitted information on safety upgrades across the site and at those two units. These 1356 MWe Advanced Boiling Water Reactors began commercial operation in 1996 and 1997, respectively, and were the first Japanese boiling water reactors to be put forward for restart.

In 2017, Tepco received permission from the NRA to restart units 6 and 7. However, in early 2021, Tepco notified the NRA of malfunctions in intruder detection equipment on the Kashiwazaki-Kariwa site. In addition, it reported the unauthorised use of an ID card. In April 2021, the NRA issued an administrative order to Tepco prohibiting it from moving nuclear fuel at the plant until improvements in security measures there have been confirmed by additional inspections. This order was lifted in December last year after inspections confirmed that measures had been enhanced at the site.

Tepco announced in April 2024 that it had completed loading fuel into unit 7, which it aimed to restart as early as this summer. The unit, however, would have to be taken offline again in October to implement anti-terrorism safety measures. The company has determined that unit 7 cannot be restarted before the completion of the antiterrorism facility scheduled for August 2029.

“As the installation deadline for the Specially Designated Severe Accident Response Facilities approaches on 13 October 2025, we have decided to suspend the test operation of the reactor itself, as we will be removing the loaded fuel without conducting inspections involving critical reaction operations,” the company has now announced.

According to Tepco, the fuel removal work will begin on 14 October, Jiji Press reported. A total of 872 nuclear fuel assemblies will then be transferred to a used fuel storage pool over about two weeks from 21 October.

Tepco is now prioritising restarting Kashiwazaki-Kariwa unit 6, where fuel loading was completed in June. The company has until September 2029 to implement anti-terrorism safety measures at unit 6, and it could operate until that time, pending local approval.

   

  • Related Posts

    Polish companies team up for regional SMR deployment

    The memorandum of understanding (MoU) aims to facilitate collaboration between the companies and establish working groups to jointly explore potential projects in Central and Eastern Europe. These activities will include…

    Reactor vessel installed at Lianjiang unit 2

    State Power Investment Corp (SPIC) said the reactor pressure vessel of unit 2 was successfully hoisted into place on Wednesday, “marking the start of the equipment installation phase for both…

    Have You Seen?

    Nikkiso CE&IG wins cryogenic pump contract for major German LNG site

    • April 7, 2026
    Nikkiso CE&IG wins cryogenic pump contract for major German LNG site

    Airgas provides high-pressure nitrogen for Artemis II

    • April 7, 2026
    Airgas provides high-pressure nitrogen for Artemis II

    INOXAP commissions first ultra-high purity liquid oxygen facility in India

    • April 7, 2026
    INOXAP commissions first ultra-high purity liquid oxygen facility in India

    LNG ships halted at strait deadline nears

    • April 7, 2026
    LNG ships halted at strait deadline nears

    U.S. Oil Premiums Hit Record High as World Scrambles for Crude

    • April 7, 2026
    U.S. Oil Premiums Hit Record High as World Scrambles for Crude

    Qatar’s LNG Exports Still Frozen as Two Tankers U-Turn at Hormuz

    • April 7, 2026
    Qatar’s LNG Exports Still Frozen as Two Tankers U-Turn at Hormuz

    India Back to Buying Venezuelan Crude

    • April 7, 2026
    India Back to Buying Venezuelan Crude

    Carbon Capture Edges Forward Despite Cost Challenge

    • April 7, 2026
    Carbon Capture Edges Forward Despite Cost Challenge

    Investors Press Amazon, Microsoft and Google on Water, Power Use in US Data Centers

    • April 7, 2026
    Investors Press Amazon, Microsoft and Google on Water, Power Use in US Data Centers

    US Crude Exports Test Limits as Shipping Constraints Mount

    • April 7, 2026
    US Crude Exports Test Limits as Shipping Constraints Mount