Cavendish, Amentum awarded follow-on Monju contract

Alkali Metal Processing Limited – a joint venture between Cavendish Nuclear and Amentum – will construct, commission, and secure regulatory permissions for a new facility in the UK which will treat the sodium coolant removed from the Japanese reactor. The material, which presents no radiological hazards, will be safely converted into sodium hydroxide for general industrial reuse.

This award builds on a previous contract, awarded by the Japan Atomic Energy Agency (JAEA) in May 2023, which focused on the design and engineering phase of the UK-based project.

Cavendish Nuclear, a wholly-owned subsidiary of Babcock International Group, said the joint venture will now move forward with construction, installation of process equipment and preparations for operation, working closely with locally based supply chain partners.

“The approach draws on both companies’ experience gained from the decommissioning of the UK’s Dounreay Prototype Fast Reactor, which shares design similarities with the Monju reactor,” the company noted. 

“It is my great pleasure to have successfully concluded the contract for the next phase of this important project,” said JAEA President Masanori Koguchi. “I sincerely hope that, through the implementation of this project, the collaborative partnership between JAEA and Cavendish Nuclear/Amentum will continue to grow and further deepen.”

Cavendish Nuclear Managing Director Mick Gornall added: “This award is a testament to the trust and confidence JAEA has placed in us. It reflects our deep nuclear expertise and highlights our continued commitment to delivering complex decommissioning solutions both in the UK and internationally, and I am delighted to continue to build our strong relations with JAEA.”

Loren Jones, Senior Vice President, Amentum, said: “This contract is another great example of Amentum using our global decommissioning knowledge and experience to provide real benefit to our customers internationally. We are pleased to be working with JAEA on a project which will deliver considerable social value.”

A key part of Japan’s nuclear energy programme, the 280 MWe Monju FBR in Tsuruga City initially started in 1994. However, it was shut down after just four months when about 700 kilograms of liquid sodium leaked from the secondary cooling loop. Although there were no injuries and no radioactivity escaped plant buildings, the operator tried to conceal the scale of the damage. It eventually restarted in May 2010 but has not operated since refuelling equipment fell into the reactor vessel during a refuelling outage later that year. The equipment was subsequently retrieved and replaced but the Nuclear Regulatory Authority (NRA) did not permit the reactor to restart.

In November 2015, following concerns over equipment inspections, the NRA determined JAEA was not competent to operate the idled reactor and, in December 2016, the government formally announced its decision to decommission it.

The decommissioning of Monju will take 30 years and cost more than JPY375 billion (USD2.5 billion), the government estimates. This includes JPY225 billion for maintenance, JPY135 billion for dismantling the plant and JPY15 billion for defuelling and preparations for decommissioning.

   

  • Related Posts

    Urenco breaks ground for new enrichment capacity

    The company announced its plans to expand its US capacity by nearly 50% in June, making a strategic, multi-billion-dollar investment to fund the construction of a new enrichment plant at…

    Passive safety module installed at Zhangzhou 4

    The passive reactor cavity water injection tank is an important component of the reactor cavity cooling system. It has a total height of 22 metres and has a fully enclosed…

    Have You Seen?

    Risks and opportunities in the CO2 market

    • August 19, 2026
    Risks and opportunities in the CO2 market

    3 Chinese Supertankers Abort Hormuz Attempt

    • August 19, 2026
    3 Chinese Supertankers Abort Hormuz Attempt

    Dover targets Indian cryogenics growth with Leistung acquisition

    • August 19, 2026
    Dover targets Indian cryogenics growth with Leistung acquisition

    Company profile: LanzaTech

    • August 19, 2026
    Company profile: LanzaTech

    India Daily: GMIDC Plans 14.3 MW Solar-BESS, India Solar Crosses 165 GW, APERC Eases Rooftop Solar Rules, JVVNL Tenders 2 MW/4 MWh BESS, UERC Proposes 2026 DSM Rules and More…

    • August 19, 2026
    India Daily: GMIDC Plans 14.3 MW Solar-BESS, India Solar Crosses 165 GW, APERC Eases Rooftop Solar Rules, JVVNL Tenders 2 MW/4 MWh BESS, UERC Proposes 2026 DSM Rules and More…

    Suntech Powers Commercial Rooftop Solar Project In Malaysia’s Shah Alam

    • August 19, 2026
    Suntech Powers Commercial Rooftop Solar Project In Malaysia’s Shah Alam

    Podcast | Industrial gases financials: headwinds, growth and what comes next?

    • August 19, 2026
    Podcast | Industrial gases financials: headwinds, growth and what comes next?

    Indian Renewable Energy Stocks End Lower Amid Broad Market Sell-Off (19 August 2026)

    • August 19, 2026
    Indian Renewable Energy Stocks End Lower Amid Broad Market Sell-Off (19 August 2026)

    Gaza’s medical oxygen system could be close to collapse

    • August 19, 2026
    Gaza’s medical oxygen system could be close to collapse

    Sri Lanka Clean Energy Week 2026 Set to Unite the Industry in Just 2 Days  

    • August 19, 2026
    Sri Lanka Clean Energy Week 2026 Set to Unite the Industry in Just 2 Days