Akkuyu 2’s turbine generator stator installed

The 12-metre-long, 4.2-metre-diameter generator stator is one of the heaviest components in a nuclear power plant, with preparations including reinforcement of the turbine hall floor, Rosatom said.


Being transported to the turbine hall ​(Image: Akkuyu NPP)

It was lifted into the pre-design position, 18.5 metres above ground level, using a hydraulic rigging system.


(Image: Akkuyu NPP)

Akkuyu Nuclear JSC CEO Sergei Butskikh said: “Commissioning works continue at Unit 1, while construction and installation operations are simultaneously performed consistently at other units. With assistance of an experienced Turkish company, which specialises in transportation and rigging operations, we completed transportation and lifting of the turbine generator stator to the design elevation, as well as its installation into the pre-design position at unit 2. Thus, in the turbine hall we are gradually switching from construction works to installation of turbine plant components, while ensuring the required margin for subsequent installation and commissioning works.”


(Image: Rosatom)

Background

Akkuyu, in the southern Mersin province, is Turkey’s first nuclear power plant. Rosatom is building four VVER-1200 reactors, under a so-called BOO (build-own-operate) model. According to the terms of the 2010 Intergovernmental Agreement between the Russian Federation and the Republic of Turkey, the commissioning of the first power unit of the nuclear power plant must take place within seven years from receipt of all permits for the construction of the unit.

The licence for the construction of the first unit was issued in 2018, with construction work beginning that year. Nuclear fuel was delivered to the site in April 2023. Turkey’s Nuclear Regulatory Agency issued permission for the first unit to be commissioned in December 2023, and in February 2024 it was announced that the reactor compartment had been prepared for controlled assembly of the reactor – and the generator stator had also been installed in its pre-design position.

The aim is for unit 1 to begin supplying Turkey’s energy system during 2026. When the 4800 MWe plant is completed, it is expected to meet about 10% of Turkey’s electricity needs. All four units are under construction – first concrete for the fourth unit was poured in July 2022.

   

  • Related Posts

    X-energy, Talen to assess deployment of multiple SMR plants

    The companies will explore opportunities to deploy three or more four-unit XE-100 plants “to add clean baseload capacity to help support reliability and meet growing energy demand from onshoring of…

    Framatome to supply low-enriched fuel for Belgium’s BR2 research reactor

    The French-based fuel specialist will supply high-density silicide low-enriched uranium (HD LEU) fuel elements for the 100 MWt reactor, which is a key global producer of medical radioisotopes. Framatome delivered three Lead…

    Have You Seen?

    European Commission Launches Consultation for Post-2030 Renewable Energy Framework

    • March 21, 2026
    European Commission Launches Consultation for Post-2030 Renewable Energy Framework

    Energy Storage Growth: India’s BESS Pipeline Hits 92 GWh, Capacity Set to Surge to 346 GWh by 2033

    • March 21, 2026
    Energy Storage Growth: India’s BESS Pipeline Hits 92 GWh, Capacity Set to Surge to 346 GWh by 2033

    Fox ESS Unveils Power Q Series Energy Storage System at Solar Solutions Amsterdam

    • March 21, 2026
    Fox ESS Unveils Power Q Series Energy Storage System at Solar Solutions Amsterdam

    NTPC Explores Power & Mining Collaboration with Malawi at BES 2026

    • March 21, 2026
    NTPC Explores Power & Mining Collaboration with Malawi at BES 2026

    CERAWeek Energy Conference Returns to Houston as Iran Conflict Rocks Global Energy Markets

    • March 21, 2026
    CERAWeek Energy Conference Returns to Houston as Iran Conflict Rocks Global Energy Markets

    Oil Jumps to Highest Settlement Since July 2022 as More Mideast Supply Disrupted

    • March 21, 2026
    Oil Jumps to Highest Settlement Since July 2022 as More Mideast Supply Disrupted

    US Drillers Cut Oil and Gas Rigs for First Time in Three Weeks, Says Baker Hughes

    • March 20, 2026
    US Drillers Cut Oil and Gas Rigs for First Time in Three Weeks, Says Baker Hughes

    Locked Out BP Workers Picket Outside Indiana Refinery Amid Labor Contract Dispute

    • March 20, 2026
    Locked Out BP Workers Picket Outside Indiana Refinery Amid Labor Contract Dispute

    North Dakota Operators Likely to Increase Crude Output in March, Regulator Says

    • March 20, 2026
    North Dakota Operators Likely to Increase Crude Output in March, Regulator Says

    US Crude Heads to Asia via Panama Canal as Iran Crisis Redraws Trade Flows

    • March 20, 2026
    US Crude Heads to Asia via Panama Canal as Iran Crisis Redraws Trade Flows