Rooppur 1 boron flushes completed, ahead of fuel loading

The work, described as one of the key stages of preparation for the first criticality test at Rooppur Nuclear Power Plant’s unit 1, was completed in what its operators described as a record-breaking 81 hours.

According to the plant’s social media channels: “This result was achieved thanks to the highly organised production processes and the coordinated and professional work of the specialists involved in the project. Boron flushes are a crucial technological step preceding the loading of nuclear fuel into the reactor core and the subsequent physical startup of the power unit.

“The results of the work confirm the readiness of the power unit for the next stage – physical start-up.”

According to a report earlier this month in Bangladesh’s The Daily Star newspaper, it was told by senior Ministry of Science and Technology officials that fuel loading is scheduled to take place during April.

There are a number of stages of checks and tests in the commissioning process for a nuclear power reactor – all taking place under strict regulatory oversight. And these continue after first criticality, with new units having their power increased in stages, with safety tests and checks at each level before the power output is increased.

The Rooppur project

In February 2011 Russia’s Rosatom signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first unit began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 – the moment that the site got its status as a nuclear facility. In March last year, Rooppur unit 1’s turbine installation was completed, as were hydraulic tests to check the primary circuit systems and equipment, followed by hot functional tests. Rosatom has included grid connection for Rooppur unit 1 as one of its key targets for the current year.

   

  • Related Posts

    Holtec SMR design clears key UK regulatory stage

    Generic Design Assessment (GDA) is a process carried out by the Office for Nuclear Regulation (ONR), the Environment Agency and Natural Resources Wales to assess the safety, security, and environmental…

    Application lodged for Poland’s first nuclear power plant

    One of the key elements of the documentation submitted with the licence application is the Preliminary Safety Analysis Report (PSAR). This report is one of the most important attachments, detailing…

    Have You Seen?

    Trump Urges Countries to Go to Strait of Hormuz and ‘Just Take It’

    • March 31, 2026
    Trump Urges Countries to Go to Strait of Hormuz and ‘Just Take It’

    US Exempts Gulf of Mexico Drillers From Protecting Endangered Species

    • March 31, 2026
    US Exempts Gulf of Mexico Drillers From Protecting Endangered Species

    Constellation Plans $3.9 Billion Capex, Lifts Buyback Amid Clean Power Demand

    • March 31, 2026
    Constellation Plans $3.9 Billion Capex, Lifts Buyback Amid Clean Power Demand

    Half the World’s Oil Comes From Just Five Countries – Visual Capitalist

    • March 31, 2026
    Half the World’s Oil Comes From Just Five Countries – Visual Capitalist

    UAE Investment Firm Buys U.S. Midstream Gas Assets for $2.25 Billion

    • March 31, 2026
    UAE Investment Firm Buys U.S. Midstream Gas Assets for $2.25 Billion

    Asia Burns More Coal as Middle East War Sends LNG Prices to 3-Year Highs

    • March 31, 2026
    Asia Burns More Coal as Middle East War Sends LNG Prices to 3-Year Highs

    Air Products readies for NASA’s largest-ever hydrogen supply ahead of Artemis II

    • March 31, 2026
    Air Products readies for NASA’s largest-ever hydrogen supply ahead of Artemis II

    Video | “We need to work on resilience” – Nippon Gases

    • March 31, 2026
    Video | “We need to work on resilience” – Nippon Gases

    CarbiCrete secures C$700,000 to scale CO2-based concrete

    • March 31, 2026
    CarbiCrete secures C$700,000 to scale CO2-based concrete

    Global helium shortage sends ‘silent bottleneck’ signal to AI

    • March 31, 2026
    Global helium shortage sends ‘silent bottleneck’ signal to AI