Rooppur 1 boron flushes completed, ahead of fuel loading

The work, described as one of the key stages of preparation for the first criticality test at Rooppur Nuclear Power Plant’s unit 1, was completed in what its operators described as a record-breaking 81 hours.

According to the plant’s social media channels: “This result was achieved thanks to the highly organised production processes and the coordinated and professional work of the specialists involved in the project. Boron flushes are a crucial technological step preceding the loading of nuclear fuel into the reactor core and the subsequent physical startup of the power unit.

“The results of the work confirm the readiness of the power unit for the next stage – physical start-up.”

According to a report earlier this month in Bangladesh’s The Daily Star newspaper, it was told by senior Ministry of Science and Technology officials that fuel loading is scheduled to take place during April.

There are a number of stages of checks and tests in the commissioning process for a nuclear power reactor – all taking place under strict regulatory oversight. And these continue after first criticality, with new units having their power increased in stages, with safety tests and checks at each level before the power output is increased.

The Rooppur project

In February 2011 Russia’s Rosatom signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first unit began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 – the moment that the site got its status as a nuclear facility. In March last year, Rooppur unit 1’s turbine installation was completed, as were hydraulic tests to check the primary circuit systems and equipment, followed by hot functional tests. Rosatom has included grid connection for Rooppur unit 1 as one of its key targets for the current year.

   

  • Related Posts

    Podcast: Sustainability and the UK’s Low Level Waste Repository

    Nuclear Waste Services’ Director of Sites and Operations, Mike Pigott, and Head of Waste Services Howard Falconer, explain the history of the site, how its operations have changed and its…

    Kazakhstan outlines localisation plans

    The Comprehensive Plan for Developing Localisation in the Nuclear Industry for 2026–2030 was developed by Kazakhstan’s Atomic Energy Agency, jointly with Kazakhstan Nuclear Power Plants LLP, interested central government agencies,…

    Have You Seen?

    Analysts Explain Oil Price Drop

    • May 25, 2026
    Analysts Explain Oil Price Drop

    Oil Prices Plunge Below $100 on Iran Deal Optimism

    • May 25, 2026
    Oil Prices Plunge Below $100 on Iran Deal Optimism

    More Tankers Make It Through the Strait of Hormuz

    • May 25, 2026
    More Tankers Make It Through the Strait of Hormuz

    China Coking Coal Prices Surge After Deadly Shanxi Mine Blast

    • May 25, 2026
    China Coking Coal Prices Surge After Deadly Shanxi Mine Blast

    Video | What emerging technologies mean for specialty gases

    • May 25, 2026
    Video | What emerging technologies mean for specialty gases

    Kawasaki, EcoLog partner on midstream liquid hydrogen transport

    • May 25, 2026
    Kawasaki, EcoLog partner on midstream liquid hydrogen transport

    Eni expands Asian LNG supply and CCS financing

    • May 25, 2026
    Eni expands Asian LNG supply and CCS financing

    EU Warns Energy Prices Will Stay Elevated Through 2027

    • May 25, 2026
    EU Warns Energy Prices Will Stay Elevated Through 2027

    U.S.-Iran Deal Delayed as Trump Refuses to “Rush” Agreement

    • May 25, 2026
    U.S.-Iran Deal Delayed as Trump Refuses to “Rush” Agreement

    Analysis: Security returns to the centre of the hydrogen debate

    • May 25, 2026
    Analysis: Security returns to the centre of the hydrogen debate