Outer dome installed at Changjiang unit 4

The dome – measuring 52 metres in diameter, 12 metres in height and weighing about 415 tonnes – was hoisted into place on top of the containment building using a 4,000-tonne crawler crane on 13 April. The process of raising the outer dome into position took two hours.

China National Nuclear Corporation (CNNC) said the installation of the outer dome of unit 4 “marks the entry of the second phase of the Changjiang Nuclear Power Plant civil construction project into the final stage”.


(Image: CNNC)

The Hualong One reactor design features a double-layered containment building, the main function of which is to ensure the integrity and leak tightness of the reactor building, and it plays a key role in the containment of radioactive substances.

Construction of the unit is being undertaken by CNNC subsidiary CNNC 22nd Engineering Co Ltd. “This installation was the result of a series of systematic innovations and collaborative efforts in the fields of technology and management,” CNNC said. “The CNNC 22nd Engineering Co Ltd project team adopted several groundbreaking measures to build a comprehensive support system for the installation task.”


(Image: CNNC)

The entire hoisting process utilised 3D modeling technology, CNNC noted. A full-size digital model of the outer dome was constructed in advance, allowing for precise simulation and collision detection of the hoisting path and key connection points, thus mitigating potential risks from the outset. Based on the 3D model, multi-level technical briefings and construction simulations were conducted, providing solid technical support for the successful one-time hoisting of the outer dome.

Two Hualong One reactors are being constructed in the second phase of the Changjiang plant. First concrete was poured for the base slab of unit 3’s nuclear island in March 2021, with that of unit 4 being poured in the December of that year. Changjiang Phase II – units 3 and 4 – represents a total estimated investment of CNY40 billion (USD5.9 billion), according to China Huaneng, which holds a 51% share in the project. The construction period is expected to be 60 months. Both units are scheduled to be fully operational in early 2027.


(Image: CNNC)

“After completion, the annual power generation [by Changjiang units 3 and 4] will reach 18 billion kilowatt-hours, which is equivalent to saving 6.326 million tonnes of coal and reducing carbon dioxide emissions by 11.68 million tonnes per year,” China Huaneng said.

The Changjiang nuclear site is already home to two operating CNP-600 pressurised water reactors (PWRs) – Changjiang 1 and 2 – which entered commercial operation in 2015 and 2016, respectively. In 2021, CNNC also began construction of a demonstration ACP100 small modular reactor at the site. The multi-purpose 125 MWe PWR – also referred to as the Linglong One – is designed for electricity production, heating, steam production or seawater desalination. It is currently undergoing pre-commissioning tests.

The island province of Hainan is China’s southernmost point. Energy policies published in 2019 by Hainan Province Development and Reform Commission specify that nuclear power will become the primary source of electricity for the island, which has a population of close to 10 million.

   

  • Related Posts

    Major component milestone for Indian reactor

    Manufactured by L&T Heavy Engineering, the manufacturing arm of Larsen & Toubro, at its Hazira facility, the component weighs 107 tonnes and is about 9.3 metres across with a thickness…

    Fusion supply chain spend up, but challenges remain

    The figure, in the report, is based on interviews with 25 fusion companies and 67 fusion suppliers. It suggests that progress is being made to overcome the “chicken-and-egg” problem of fusion…

    Have You Seen?

    Trump Insists Iran Has Agreed to Nuclear Inspections

    • June 23, 2026
    Trump Insists Iran Has Agreed to Nuclear Inspections

    Will US and International Sanctions on Iran be Lifted?

    • June 23, 2026
    Will US and International Sanctions on Iran be Lifted?

    US Supreme Court Boosts Exxon’s Bid to Get Compensation from Cuba

    • June 23, 2026
    US Supreme Court Boosts Exxon’s Bid to Get Compensation from Cuba

    US Natural Gas Drops on Cooler Outlooks, New Pipeline Capacity

    • June 23, 2026
    US Natural Gas Drops on Cooler Outlooks, New Pipeline Capacity

    Trump Administration to Slash Oil-Drilling Bond Amount by 95%

    • June 23, 2026
    Trump Administration to Slash Oil-Drilling Bond Amount by 95%

    India Boosts U.S. LPG Imports to Record High

    • June 23, 2026
    India Boosts U.S. LPG Imports to Record High

    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions

    • June 23, 2026
    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions

    Iran Says U.S. Agreed to Unblock $12 Billion in Frozen Funds

    • June 23, 2026
    Iran Says U.S. Agreed to Unblock $12 Billion in Frozen Funds

    IOC’s Tanker Tender Comes Up Empty as Hormuz Risk Lingers

    • June 23, 2026
    IOC’s Tanker Tender Comes Up Empty as Hormuz Risk Lingers

    Europe’s Battery Storage Installations Set to Quadruple by 2030

    • June 23, 2026
    Europe’s Battery Storage Installations Set to Quadruple by 2030