CERC Reinstates Connectivity For 196.8 MW Hybrid Renewable Energy Project In Madhya Pradesh

Representational image. Credit: Canva

The Central Electricity Regulatory Commission has ruled in favor of VEH Jayin Renewables Private Limited, allowing the company to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The decision, issued on May 7, 2026, resolves a dispute related to the delayed submission of mandatory financial guarantees and enables the project to move ahead toward commissioning.

The matter arose after regulatory amendments introduced in September 2025 imposed additional compliance requirements on existing renewable energy projects. VJRPL was already developing a 151.8 MW wind power project connected to the Rajgarh substation in Madhya Pradesh and had also secured approval to integrate an additional 45 MW solar power component, converting the project into a hybrid renewable energy installation with a total capacity of 196.8 MW.

Under the revised regulations, developers were directed to submit two mandatory Connectivity Bank Guarantees, identified as Conn-BG1 and Conn-BG3, by November 8, 2025. The total value of these guarantees was approximately ₹1.4 crore. However, VJRPL failed to meet the prescribed deadline and submitted the guarantees on December 8, 2025, exactly one month after the due date.

The company explained before the Commission that the delay occurred due to internal administrative procedures and approval requirements involving its Australia-based investors. VJRPL stated that the delay was procedural in nature and not an indication that the company intended to abandon or delay the project.

Despite the company’s request for additional time, Central Transmission Utility of India Limited rejected the late submission and revoked the connectivity approval for the 45 MW solar component in March 2026. CTUIL maintained that the timelines mentioned in the regulations were mandatory and needed to be followed strictly to maintain discipline and transparency in the connectivity approval process.

VJRPL subsequently approached the CERC seeking restoration of the connectivity approval. During the hearing, the company argued that the project had already reached an advanced stage of commissioning and that cancellation of the approval would create significant financial and operational difficulties. The developer also informed the Commission that all other statutory permissions and project-related clearances were already in place.

After reviewing the submissions and circumstances of the case, the Commission observed that the delay was unintentional and inadvertent. The CERC noted that the company had eventually complied with the financial guarantee requirements and invoked its “Power to Relax” provisions to prevent undue hardship to the developer.

However, the Commission also imposed a financial penalty on the company for the delayed compliance. VJRPL has been directed to pay ₹7 lakh, which is equal to 5% of the required bank guarantee amount, within 30 days. Following the payment, CTUIL has been instructed to restore the connectivity approval within one week and process the required technical data so that the hybrid renewable energy project can proceed toward operations and planned captive renewable power supply.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    India Daily: Andaman & Nicobar Tenders 20 MWh BESS, NLC–OREDA Form Green JV, UPCL Tenders BESS, BERC Reviews 70 MW LTA, REC Transfers Luhri SPV, BERC Reviews OA Charges

    The Andaman and Nicobar administration has invited bids for a 20 MWh grid-connected Battery Energy Storage System (BESS) at Dollygunj, Port Blair. The project is aimed at strengthening grid stability…

    Yellow Door Energy, Nedbank CIB Reach Financial Close on 49 MWp Lion Thorn Solar Park in South Africa

    Yellow Door Energy and Nedbank Corporate and Investment Banking (Nedbank CIB) have achieved financial close for the 49 MWp Lion Thorn Solar Park in Leeudoringstad, North West, South Africa, paving…

    Have You Seen?

    AI Could Unlock $230B for Oil, Gas, OFSE Cos, McKinsey Says

    • September 2, 2026
    AI Could Unlock $230B for Oil, Gas, OFSE Cos, McKinsey Says

    Galactic Energy joins reusable rocket race

    • September 2, 2026
    Galactic Energy joins reusable rocket race

    Galactic Energy joins reusable rocket race

    • September 2, 2026
    Galactic Energy joins reusable rocket race

    Meritus enters Arizona market with Allied Gases and Welding Supplies acquisition

    • September 2, 2026
    Meritus enters Arizona market with Allied Gases and Welding Supplies acquisition

    US LNG exports up 23% in first half of 2026, reports EIA

    • September 2, 2026
    US LNG exports up 23% in first half of 2026, reports EIA

    Switzerland launches cross-border BECCS CO2 supply chain

    • September 2, 2026
    Switzerland launches cross-border BECCS CO2 supply chain

    Column: How energy-efficient motors can cut biogas plant costs

    • September 2, 2026
    Column: How energy-efficient motors can cut biogas plant costs

    Qatar and UAE LNG cargoes transferred ship-to-ship outside Hormuz

    • September 2, 2026
    Qatar and UAE LNG cargoes transferred ship-to-ship outside Hormuz

    India Daily: Andaman & Nicobar Tenders 20 MWh BESS, NLC–OREDA Form Green JV, UPCL Tenders BESS, BERC Reviews 70 MW LTA, REC Transfers Luhri SPV, BERC Reviews OA Charges

    • September 2, 2026
    India Daily: Andaman & Nicobar Tenders 20 MWh BESS, NLC–OREDA Form Green JV, UPCL Tenders BESS, BERC Reviews 70 MW LTA, REC Transfers Luhri SPV, BERC Reviews OA Charges

    Yellow Door Energy, Nedbank CIB Reach Financial Close on 49 MWp Lion Thorn Solar Park in South Africa

    • September 2, 2026
    Yellow Door Energy, Nedbank CIB Reach Financial Close on 49 MWp Lion Thorn Solar Park in South Africa