Flushing work under way for Changjiang unit 4

The flushing process is a key stage before cold and hot testing during the commissioning steps taken for a new nuclear power unit.

It involves the core pipelines and equipment, including the reactor coolant system, residual heat removal system and the safety systems. The flushing removes debris from inside pipelines, verifies flow capacity, and checks leak tightness and that everything has been installed correctly.

China National Nuclear Corporation said: “It is a crucial preliminary process for maintaining nuclear safety and ensuring the long-term stable operation of the unit.

“This flushing task has a tight schedule, frequent cross-operations of multiple systems, and stringent cleanliness acceptance standards. The Hainan Changjiang Nuclear Power Project Department, in collaboration with the owner, supervisor, general contractor, and other construction units, refined specialised construction plans and optimised on-site work procedures … preemptive hazard identification and mitigation were conducted to ensure the smooth, safe, and standardised implementation of flushing operations.”

Two Hualong One reactors are being constructed in the second phase of the Changjiang plant. First concrete was poured for the base slab of unit 3’s nuclear island in March 2021, with that of unit 4 being poured in the December of that year. Changjiang Phase II – units 3 and 4 – represents a total estimated investment of CNY40 billion (USD5.9 billion), according to China Huaneng, which holds a 51% share in the project. The outer dome was installed on unit 4 in April. The construction period is expected to be 60 months. Both units are scheduled to be fully operational in early 2027.

The Changjiang nuclear site is already home to two operating CNP-600 pressurised water reactors (PWRs) – Changjiang 1 and 2 – which entered commercial operation in 2015 and 2016, respectively. In 2021, CNNC also began construction of a demonstration ACP100 small modular reactor at the site. The multi-purpose 125 MWe PWR – also referred to as the Linglong One – is designed for electricity production, heating, steam production or seawater desalination. It is currently undergoing pre-commissioning tests.

The island province of Hainan is China’s southernmost point. Energy policies published in 2019 by Hainan Province Development and Reform Commission specify that nuclear power will become the primary source of electricity for the island, which has a population of close to 10 million.
 

   

  • Related Posts

    Major component milestone for Indian reactor

    Manufactured by L&T Heavy Engineering, the manufacturing arm of Larsen & Toubro, at its Hazira facility, the component weighs 107 tonnes and is about 9.3 metres across with a thickness…

    Fusion supply chain spend up, but challenges remain

    The figure, in the report, is based on interviews with 25 fusion companies and 67 fusion suppliers. It suggests that progress is being made to overcome the “chicken-and-egg” problem of fusion…

    Have You Seen?

    India Boosts U.S. LPG Imports to Record High

    • June 23, 2026
    India Boosts U.S. LPG Imports to Record High

    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions

    • June 23, 2026
    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions

    Iran Says U.S. Agreed to Unblock $12 Billion in Frozen Funds

    • June 23, 2026
    Iran Says U.S. Agreed to Unblock $12 Billion in Frozen Funds

    IOC’s Tanker Tender Comes Up Empty as Hormuz Risk Lingers

    • June 23, 2026
    IOC’s Tanker Tender Comes Up Empty as Hormuz Risk Lingers

    Europe’s Battery Storage Installations Set to Quadruple by 2030

    • June 23, 2026
    Europe’s Battery Storage Installations Set to Quadruple by 2030

    Tankers Emerge from Dark Mode amid Tentative Hormuz ReopeningTankers Emerge from

    • June 23, 2026
    Tankers Emerge from Dark Mode amid Tentative Hormuz ReopeningTankers Emerge from

    Ballard’s GeoPura buy marks business model shift from hydrogen equipment seller

    • June 23, 2026
    Ballard’s GeoPura buy marks business model shift from hydrogen equipment seller

    Posco opens rare gas plant for South Korean semiconductor market

    • June 23, 2026
    Posco opens rare gas plant for South Korean semiconductor market

    Oil Steady as Investors Focus on Hormuz Flows After Peace Talks

    • June 23, 2026
    Oil Steady as Investors Focus on Hormuz Flows After Peace Talks

    US Gasoline Prices Tumble for Sixth Straight Week

    • June 23, 2026
    US Gasoline Prices Tumble for Sixth Straight Week