Eletronuclear cost-savings, plans for Angra 3 operation in 2031

Monday, 10 February 2025

Eletronuclear cost-savings, plans for Angra 3 operation in 2031
Angra 3 is currently about 65% complete (Image: Eletronuclear)

Brazil has two operating reactors – Angra 1 and Angra 2 – which generate about 3% of the country’s electricity. Work on the Angra 3 project – to feature a Siemens/KWU 1405 MW pressurised water reactor – began in 1984 but was suspended two years later, before construction began. The scheme was resurrected in 2006, with first concrete in 2010. However, amid a corruption probe into government contracts, construction of the unit was halted for a second time in 2015, when it was 65% complete.

The project resumed again in November 2022 – at the time of the project’s revitalisation, Eletronuclear’s aim was to start operations by the end of 2026. However, work halted again in April 2023 after disputes with the municipality of the City of Angra dos Reis over agreements relating to “environmental compensation” payments and also changes relating to the granted planning permission.

The company is currently awaiting a government decision on completing Angra 3 – it said in September that a study by Brazil’s National Bank for Economic and Social Development had concluded that the cost of abandoning construction of the part-built nuclear power unit could be about BRL21 billion (USD3.7 billion), which it says was about the same as the cost of completing it.

It says the unit’s generating capacity will be sufficient to supply 4.5 million inhabitants and would also create around 7000 direct jobs at its peak, in addition to a much larger number of indirect jobs. It also noted that about BRL800 million in Angra 3 equipment was used in Angra 2 and between BRL500-600 million in nuclear fuel, which had been initially purchased for Angra 3, had been used in Angra 2.

Eletronuclear says its restructuring plan was approved by the board at the end of January and will come into effect on 1 April. It will reduce management levels and end overlapping activities, with management positions cut from 116 to 73. The changes are together said to be likely to bring annual savings of about BRL 3 million.

In its announcement, the company says it aims to reduce spending on materials and third party services – by reviewing contracts, and ensuring optimisation of processes – to help improve the economic viability of the company and strategic projects such as Angra 3.

It said “the new organisational chart is in line with the current stage of the Angra 3 project. Previous planning predicted the plant would be completed in 2028, but with the new estimates, it is expected to start operating in 2031. In this way, the new format allows for better use of labour, reallocating employees who were focused on the unit’s operations and engineering services to the two plants in operation (Angra 1 and 2)”.

Raul Lycurgo, president of Eletronuclear, said: “This organisational reformulation allows for a leaner and more efficient model, aligned with good sector practices, without compromising the safety and quality of the services provided.”

   

  • Related Posts

    Major component milestone for Indian reactor

    Manufactured by L&T Heavy Engineering, the manufacturing arm of Larsen & Toubro, at its Hazira facility, the component weighs 107 tonnes and is about 9.3 metres across with a thickness…

    Fusion supply chain spend up, but challenges remain

    The figure, in the report, is based on interviews with 25 fusion companies and 67 fusion suppliers. It suggests that progress is being made to overcome the “chicken-and-egg” problem of fusion…

    Have You Seen?

    Video | The role of connected devices in modern hospital gas systems

    • June 24, 2026
    Video | The role of connected devices in modern hospital gas systems

    Poland bank invests €25m in pan-European biomethane fund

    • June 24, 2026
    Poland bank invests €25m in pan-European biomethane fund

    Stegra closes $1.4bn rescue package for green hydrogen-based steel plant

    • June 24, 2026
    Stegra closes $1.4bn rescue package for green hydrogen-based steel plant

    Tanker Owners Are Having the Best Week of the Hormuz Crisis

    • June 24, 2026
    Tanker Owners Are Having the Best Week of the Hormuz Crisis

    Pemex Wants Petrobras’ Deepwater Magic

    • June 24, 2026
    Pemex Wants Petrobras’ Deepwater Magic

    Asian Demand for Mideast Oil Slows after Splurge

    • June 24, 2026
    Asian Demand for Mideast Oil Slows after Splurge

    Tankers Emerge from Dark Mode amid Tentative Hormuz Reopening

    • June 24, 2026
    Tankers Emerge from Dark Mode amid Tentative Hormuz Reopening

    Novak: Russia Considers Complete Ban on Diesel Exports

    • June 24, 2026
    Novak: Russia Considers Complete Ban on Diesel Exports

    Europe’s Top Gas Distributor to Invest $14.8 Billion in AI-Backed Networks

    • June 24, 2026
    Europe’s Top Gas Distributor to Invest $14.8 Billion in AI-Backed Networks

    Trump Insists Iran Has Agreed to Nuclear Inspections

    • June 23, 2026
    Trump Insists Iran Has Agreed to Nuclear Inspections