CERC Approves GNA Milestone Extensions With New Charges For Renewable Energy Projects

The Central Electricity Regulatory Commission (CERC) has approved a uniform framework allowing renewable power developers additional time to meet key operational milestones under the General Network Access (GNA) Regulations. The decision was issued on August 14, 2026, in Petition No. 5/SM/2026.

Under the existing GNA framework, connectivity granted to renewable projects can be revoked if developers fail to meet deadlines related to land documents, Financial Closure (FC), or Commercial Operation Date (COD). CERC has now introduced a structured extension mechanism for projects that demonstrate genuine progress but are unable to meet the prescribed timelines.

The Commission exercised its Power to Relax under Regulation 41 and its authority to issue suo moto directions under Regulation 44. The framework was finalized after considering written comments from 42 stakeholders, including DISCOMs, renewable energy developers and the Central Transmission Utility of India Limited (CTUIL), followed by a public hearing on May 19, 2026.

Developers must meet specific eligibility conditions to obtain extensions. For land document and financial closure milestones, at least 20% of the required land must be supported by verified documents submitted at least 15 working days before the applicable deadline.

For COD extensions, projects using the Land or Land-BG route must demonstrate land compliance covering at least 75% of the required area. Projects following the LOA/PPA route must demonstrate at least 50% compliance. Developers must also provide executed contracts for major equipment supplies or EPC civil and electrical works.

The extensions will be subject to Milestone Extension Charges (MEC). Land-related extensions can be granted for up to three months, with charges increasing from ₹1,000 per MW per day in the first month to ₹1,200 per MW per day in the third month.

Financial closure extensions can run for up to six months. Charges begin at ₹1,000 per MW per day for the first three months and rise progressively to ₹1,300 per MW per day by the sixth month.

COD extensions can be granted for up to 12 months. Charges are ₹3,000 per MW per day for the first six months, increasing thereafter to ₹3,900 per MW per day and reaching ₹6,000 per MW per day during months ten to twelve.

MEC payments must be deposited 15 days in advance on a daily pro-rata basis.

The order also provides financial relief. Developers achieving full or partial COD within the permitted period can receive a 50% refund, without interest, on MEC paid for earlier land and financial closure extensions, subject to the specified conditions.

CERC has further directed that 100% of MEC collected for COD extensions and at least 50% of land and FC charges be used to reduce monthly inter-State transmission system charges, helping limit the impact of project delays on consumers and DISCOMs.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    India Daily: India Power Capacity Tops 550 GW, CEA Sets New Cybersecurity Rules, CSPDCL Advances 500 MWh BESS, India Accelerates Smart Meters, Kerala Rejects KINESCO Licence and More…

    India’s installed power capacity reached around 552 GW by July 2026, with non-fossil sources contributing more than 300 GW, or over 54% of the total. Solar has emerged as a…

    Saatvik Green Energy Reports INR 511 Crore Q1 FY27 Revenue, Order Book Reaches 5.89 GW

    Saatvik Green Energy Limited has reported revenue from operations of ₹5,110 million (₹511 crore) for the quarter ended June 30, 2026 (Q1 FY27), compared with ₹9,157 million (₹915.7 crore) in…

    Have You Seen?

    Holcim UAE starts cement carbon capture pilot project

    • August 14, 2026
    Holcim UAE starts cement carbon capture pilot project

    Qatar Ras Laffan train five ‘goes offline’

    • August 14, 2026
    Qatar Ras Laffan train five ‘goes offline’

    Vietnam’s Bac Ninh semiconductor investment hits $2.7bn

    • August 14, 2026
    Vietnam’s Bac Ninh semiconductor investment hits $2.7bn

    India Daily: India Power Capacity Tops 550 GW, CEA Sets New Cybersecurity Rules, CSPDCL Advances 500 MWh BESS, India Accelerates Smart Meters, Kerala Rejects KINESCO Licence and More…

    • August 14, 2026
    India Daily: India Power Capacity Tops 550 GW, CEA Sets New Cybersecurity Rules, CSPDCL Advances 500 MWh BESS, India Accelerates Smart Meters, Kerala Rejects KINESCO Licence and More…

    CERC Approves GNA Milestone Extensions With New Charges For Renewable Energy Projects

    • August 14, 2026
    CERC Approves GNA Milestone Extensions With New Charges For Renewable Energy Projects

    Saatvik Green Energy Reports INR 511 Crore Q1 FY27 Revenue, Order Book Reaches 5.89 GW

    • August 14, 2026
    Saatvik Green Energy Reports INR 511 Crore Q1 FY27 Revenue, Order Book Reaches 5.89 GW

    Green Energy Stocks Deliver Mixed Performance As Sensex And Nifty End Lower (14 August 2026)

    • August 14, 2026
    Green Energy Stocks Deliver Mixed Performance As Sensex And Nifty End Lower (14 August 2026)

    CIP Closes USD 3 Billion Growth Markets Fund II to Back Large-Scale Renewable Energy Projects

    • August 14, 2026
    CIP Closes USD 3 Billion Growth Markets Fund II to Back Large-Scale Renewable Energy Projects

    Neogenyx to break ground on Nebraska RNG facility

    • August 14, 2026
    Neogenyx to break ground on Nebraska RNG facility

    US to Soon Unveil Unprecedented Sanctions on Iran

    • August 14, 2026
    US to Soon Unveil Unprecedented Sanctions on Iran