The Central Electricity Regulatory Commission (CERC) has extended the scheduled commercial operation date (SCOD) of Avaada Inclean Private Limited’s 50 MW solar power project in Gujarat to February 24, 2026, allowing it to retain eligibility for an exemption from inter-state transmission system (ISTS) charges. The decision was issued through an order dated November 9, 2026, under the applicable sharing regulations.
The project is located at Rampar village in Gujarat’s Kutch district and is connected to the 220 kV Lakadiya ISTS pooling sub-station. Avaada Inclean approached CERC seeking an extension after delays in the commissioning of the common transmission system (CTS) infrastructure required to operationalise the project.
The company explained that the project was being developed through Avaada GJ Lakadia Private Limited, with both entities operating as wholly owned subsidiaries of Avaada Energy Private Limited. At the time connectivity was granted, the project’s operationalization was linked to the completion of transmission augmentation work at the Lakadiya sub-station. The work was being executed by WRSS XXI(A) Transco Limited.
According to the petition, Avaada completed its generation facilities and associated transmission readiness within the original timeline. The Central Electricity Authority (CEA) granted approval for energization on June 30, 2025, which was also the project’s original scheduled commercial operation date. However, delays in the required transmission infrastructure prevented the project from being commissioned as planned.
The transmission-related delays were discussed during several joint coordination meetings. Meanwhile, the prospective power buyer, Vretanta Clean India Private Limited, deferred signing a binding power purchase agreement in April 2025 because of uncertainty surrounding the transmission infrastructure timeline. The parties subsequently entered into a conditional, non-binding memorandum of understanding.
Following a representation submitted in September 2025, a committee constituted under the sharing regulations examined the matter and submitted reports in November 2025 and March 2026. The committee concluded that the delay was not attributable to the project developer. It recommended two six-month extensions of the SCOD, up to June 30, 2026, or until the commissioning of the CTS infrastructure, whichever occurred earlier. It also recommended allowing up to 60 days for project commissioning preparations after transmission infrastructure became operational, within the prescribed overall limit.
Records provided by the Central Transmission Utility of India Limited confirmed that WRSS XXI(A) Transco Limited declared commercial operation of the Lakadiya transformation augmentation and associated 220 kV line bay on February 10, 2026. Connectivity for the project became effective on March 28, 2026.
Avaada’s solar project completed its trial run on February 19, 2026, and achieved commercial operation for its entire 50 MW capacity on February 24, 2026.
After examining the regulatory provisions and supporting documents, CERC concluded that the project fulfilled the conditions for extending ISTS charge waiver eligibility. The commission considered the original SCOD, the delay caused by transmission infrastructure unavailability and the project’s subsequent commissioning.
Accordingly, CERC approved the SCOD extension to February 24, 2026, strictly for the purpose of eligibility under the ISTS charge waiver provisions.
Discover more from SolarQuarter
Subscribe to get the latest posts sent to your email.
RELATED ARTICLES
Subscribe Today
GET EXCLUSIVE FULL ACCESS TO PREMIUM CONTENT
SUPPORT CLEANTECH JOURNALISM
EXPERT ANALYSIS OF AND EMERGING TRENDS
TOPICAL VIDEO WEBINARS
Get unlimited access to our EXCLUSIVE Content and our archive of subscriber stories.
Exclusive content this week
Latest article