Akkuyu 2’s turbine generator stator installed

The 12-metre-long, 4.2-metre-diameter generator stator is one of the heaviest components in a nuclear power plant, with preparations including reinforcement of the turbine hall floor, Rosatom said.


Being transported to the turbine hall ​(Image: Akkuyu NPP)

It was lifted into the pre-design position, 18.5 metres above ground level, using a hydraulic rigging system.


(Image: Akkuyu NPP)

Akkuyu Nuclear JSC CEO Sergei Butskikh said: “Commissioning works continue at Unit 1, while construction and installation operations are simultaneously performed consistently at other units. With assistance of an experienced Turkish company, which specialises in transportation and rigging operations, we completed transportation and lifting of the turbine generator stator to the design elevation, as well as its installation into the pre-design position at unit 2. Thus, in the turbine hall we are gradually switching from construction works to installation of turbine plant components, while ensuring the required margin for subsequent installation and commissioning works.”


(Image: Rosatom)

Background

Akkuyu, in the southern Mersin province, is Turkey’s first nuclear power plant. Rosatom is building four VVER-1200 reactors, under a so-called BOO (build-own-operate) model. According to the terms of the 2010 Intergovernmental Agreement between the Russian Federation and the Republic of Turkey, the commissioning of the first power unit of the nuclear power plant must take place within seven years from receipt of all permits for the construction of the unit.

The licence for the construction of the first unit was issued in 2018, with construction work beginning that year. Nuclear fuel was delivered to the site in April 2023. Turkey’s Nuclear Regulatory Agency issued permission for the first unit to be commissioned in December 2023, and in February 2024 it was announced that the reactor compartment had been prepared for controlled assembly of the reactor – and the generator stator had also been installed in its pre-design position.

The aim is for unit 1 to begin supplying Turkey’s energy system during 2026. When the 4800 MWe plant is completed, it is expected to meet about 10% of Turkey’s electricity needs. All four units are under construction – first concrete for the fourth unit was poured in July 2022.

   

  • Related Posts

    NPCIL signs MoU for Gujarat nuclear power projects

    In what it called “a significant step towards exploring new horizons for nuclear power development in Gujarat”, Nuclear Power Corporation of India Limited (NPCIL) said the MoU would “facilitate collaboration between…

    Hinkley Point B becomes second AGR plant transferred for decommissioning

    Hinkley Point B – comprising two Advanced Gas-cooled Reactors (AGRs) – was first synchronised to the electricity grid in February 1976. The plant generated more than 311 terawatt-hours of electricity…

    Have You Seen?

    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    • October 2, 2026
    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    • October 2, 2026
    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    Latest Dallas Fed Survey Reveals Theme Among Respondents

    • October 2, 2026
    Latest Dallas Fed Survey Reveals Theme Among Respondents

    What is the near-term feasibility of helium-3 fuel for fusion power?

    • October 2, 2026
    What is the near-term feasibility of helium-3 fuel  for fusion power?

    UN Says Global Fuel Subsidies Could Top $1 Trillion

    • October 2, 2026
    UN Says Global Fuel Subsidies Could Top $1 Trillion

    JERA CEO Warns LNG Prices Have Further to Climb

    • October 2, 2026
    JERA CEO Warns LNG Prices Have Further to Climb

    Scaling up: Blue Star’s next phase in Colorado

    • October 2, 2026
    Scaling up: Blue Star’s next phase in Colorado

    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    • October 2, 2026
    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    Oil Prices Come Under Pressure

    • October 2, 2026
    Oil Prices Come Under Pressure

    China Halts October Fuel Exports as Global Diesel Crunch Deepens

    • October 2, 2026
    China Halts October Fuel Exports as Global Diesel Crunch Deepens