Akkuyu 2’s turbine generator stator installed

The 12-metre-long, 4.2-metre-diameter generator stator is one of the heaviest components in a nuclear power plant, with preparations including reinforcement of the turbine hall floor, Rosatom said.


Being transported to the turbine hall ​(Image: Akkuyu NPP)

It was lifted into the pre-design position, 18.5 metres above ground level, using a hydraulic rigging system.


(Image: Akkuyu NPP)

Akkuyu Nuclear JSC CEO Sergei Butskikh said: “Commissioning works continue at Unit 1, while construction and installation operations are simultaneously performed consistently at other units. With assistance of an experienced Turkish company, which specialises in transportation and rigging operations, we completed transportation and lifting of the turbine generator stator to the design elevation, as well as its installation into the pre-design position at unit 2. Thus, in the turbine hall we are gradually switching from construction works to installation of turbine plant components, while ensuring the required margin for subsequent installation and commissioning works.”


(Image: Rosatom)

Background

Akkuyu, in the southern Mersin province, is Turkey’s first nuclear power plant. Rosatom is building four VVER-1200 reactors, under a so-called BOO (build-own-operate) model. According to the terms of the 2010 Intergovernmental Agreement between the Russian Federation and the Republic of Turkey, the commissioning of the first power unit of the nuclear power plant must take place within seven years from receipt of all permits for the construction of the unit.

The licence for the construction of the first unit was issued in 2018, with construction work beginning that year. Nuclear fuel was delivered to the site in April 2023. Turkey’s Nuclear Regulatory Agency issued permission for the first unit to be commissioned in December 2023, and in February 2024 it was announced that the reactor compartment had been prepared for controlled assembly of the reactor – and the generator stator had also been installed in its pre-design position.

The aim is for unit 1 to begin supplying Turkey’s energy system during 2026. When the 4800 MWe plant is completed, it is expected to meet about 10% of Turkey’s electricity needs. All four units are under construction – first concrete for the fourth unit was poured in July 2022.

   

  • Related Posts

    India begins public consultation on SHANTI Bill rules

    The SHANTI Bill – to give it its full name, the Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India (SHANTI) Bill, 2025 – completed the legislative process in…

    Blue Energy, GE Vernova take gas-plus-nuclear collaboration to next stage

    In May, Blue Energy – a vertically integrated deployment platform for financeable, turnkey nuclear power plants compatible with leading reactor technology – announced it was joining up with GE Vernova…

    Have You Seen?

    Will Oil Prices Keep Rising?

    • August 18, 2026
    Will Oil Prices Keep Rising?

    UCLR completes first hot fire of cryogenic LOX engine

    • August 18, 2026
    UCLR completes first hot fire of cryogenic LOX engine

    Analysis: The key role of LNG in the UK North Sea debate

    • August 18, 2026
    Analysis: The key role of LNG in the UK North Sea debate

    Linde and Monash University Malaysia partner on industrial decarbonisation

    • August 18, 2026
    Linde and Monash University Malaysia partner on industrial decarbonisation

    UK CO2 supply resilience consultation closes this week

    • August 18, 2026
    UK CO2 supply resilience consultation closes this week

    Libya Power Crisis Explodes as Grid Fails Again

    • August 18, 2026
    Libya Power Crisis Explodes as Grid Fails Again

    Chevron Strikes Oil and Gas Offshore Angola in Major Discovery

    • August 18, 2026
    Chevron Strikes Oil and Gas Offshore Angola in Major Discovery

    Russia Receives First Gasoline Cargo From India as Fuel Shortages Spread

    • August 18, 2026
    Russia Receives First Gasoline Cargo From India as Fuel Shortages Spread

    ExxonMobil awards $1.1bn in contracts for Mozambique LNG project

    • August 18, 2026
    ExxonMobil awards $1.1bn in contracts for Mozambique LNG project

    What is the near-term feasibility of helium-3 fuel for fusion power?

    • August 18, 2026
    What is the near-term feasibility of helium-3 fuel for fusion power?