APTEL Reviews KERC Order On 50 MW Solar Project Delay And Liquidated Damages

Representational image. Credit: Canva

Hero Future Energies filed an appeal challenging the Karnataka Electricity Regulatory Commission’s (KERC) order that denied the company an extension of 180 days for commissioning its solar project. The company argued that the delay was not entirely their fault and was caused by procedural and administrative delays beyond their control. The main dispute began after the original Power Purchase Agreement (PPA) was signed on 19 February 2014. Although the PPA was approved by KERC on 13 March 2014, the approval took 22 days and this delay was not immediately factored into the project timeline.

Hero Future Energies contended that the effective date of the PPA should be considered from the date of KERC’s approval, not the date of signing. They also highlighted that the signed copy of the PPA was only received on 13 August 2014, causing further delays in initiating project financing and land acquisition. Despite this, the company completed the commissioning of the solar plant on 14 August 2015.

To accommodate the delay, the second respondent, Hubli Electricity Supply Company (HESCOM), granted an extension of 5 months and 8 days through a letter dated 17 October 2014. This extension was later formalized through a Supplementary PPA signed on 20 October 2015. However, when this Supplementary PPA was submitted to KERC for approval, KERC pointed out deficiencies and insisted on reducing the tariff from ₹7.47 per kWh to ₹6.50 per kWh, the latter being applicable on the date of commissioning.

When Hero Future Energies took the matter to the High Court, the court directed them to approach KERC. The company filed a petition with KERC, seeking approval of the Supplementary PPA and the originally agreed tariff. While KERC upheld the original tariff of ₹7.47 per kWh, it rejected the extension of 180 days, citing that the delay could not be justified under force majeure clauses or the terms of the PPA.

Following this decision, HESCOM issued a letter demanding ₹12.05 crore in liquidated damages from Hero Future Energies for the delay in commissioning. This amount was partially recovered through deductions from energy bills, prompting the company to approach the Appellate Tribunal for Electricity (APTEL) for relief.

Hero Future Energies argued that similar delays had been treated differently in other cases, and the extension granted by HESCOM should be considered valid. They emphasized that the delay occurred due to KERC’s approval process and procedural issues, and not due to any default on their part. They sought restitution and cancellation of the liquidated damages.

The tribunal acknowledged that delays in approval by the regulator could justify time extensions and that natural justice requires giving the developer a proper opportunity to explain the delays. The tribunal found merit in Hero’s claim for part of the extension and noted that denying the full 180-day extension without a hearing was unjust.

 

  • Related Posts

    Kalpa Power Secures 286 MWp Utility-Scale Solar Project in Madhya Pradesh

    Kalpa Power Secures 286 MWp Utility-Scale Solar Project in Madhya Pradesh Representational image. Credit: Canva Kalpa Power Private Limited has secured a 286 MWp utility-scale solar project in Madhya Pradesh,…

    Indian Green Energy Stocks Trade Mixed As Sensex, Nifty Decline (26 August 2026)

    Indian green energy and utility stocks witnessed mixed trading activity today as the broader equity market remained under pressure. The BSE Sensex and Nifty 50 both declined 0.24%, closing at…

    Have You Seen?

    Japan to Unveil New Oil Diversification Strategy

    • August 26, 2026
    Japan to Unveil New Oil Diversification Strategy

    Hormuz Traffic Remains Depressed as Iran and Oman Weigh Temporary Corridor

    • August 26, 2026
    Hormuz Traffic Remains Depressed as Iran and Oman Weigh Temporary Corridor

    Qatar Loses $24 Billion as LNG Exports Collapse 96%

    • August 26, 2026
    Qatar Loses $24 Billion as LNG Exports Collapse 96%

    India’s Russian Oil Imports Slide From Record High as Supply Tightens

    • August 26, 2026
    India’s Russian Oil Imports Slide From Record High as Supply Tightens

    UK Energy Bills to Hit Three-Year High as Gas Prices Surge

    • August 26, 2026
    UK Energy Bills to Hit Three-Year High as Gas Prices Surge

    Preview: Swagelok webinar to explore gas distribution system design

    • August 26, 2026
    Preview: Swagelok webinar to explore gas distribution system design

    Preview: Swagelok webinar to explore gas distribution system design

    • August 26, 2026
    Preview: Swagelok webinar to explore gas distribution system design

    Development and production offer biggest AI prizes – McKinsey

    • August 26, 2026
    Development and production offer biggest AI prizes – McKinsey

    SLB selected as reservoir partner for Havstjerne carbon storage project

    • August 26, 2026
    SLB selected as reservoir partner for Havstjerne carbon storage project

    BLM Sets October Oil and Gas Lease Sale for Montana and Dakotas

    • August 26, 2026
    BLM Sets October Oil and Gas Lease Sale for Montana and Dakotas