APTEL Upholds PSERC’s Authority To Regulate PEDA In Renewable Energy Disputes

Representational image. Credit: Canva

The Appellate Tribunal for Electricity delivered a significant judgment on 10th July 2025 in a batch of appeals involving the Punjab Energy Development Agency (PEDA), various solar and hydro power developers, and the Punjab State Electricity Regulatory Commission (PSERC). The appeals primarily revolved around the powers of the State Commission to adjudicate disputes involving entities like PEDA, which is neither a licensee nor a generating company under the Electricity Act, 2003.

Several appeals were filed against PSERC’s orders directing PEDA to refund performance bank guarantees (PBGs) or provide relief in matters involving delays in project commissioning. In one instance, a hydroelectric project by a private developer faced local objections and required infrastructure modifications. A tripartite agreement was executed with PEDA and the Punjab State Power Corporation Limited (PSPCL), and the company later approached PSERC seeking compensation for additional costs. While PSERC refused to revise the tariff, it allowed cost recovery for infrastructure works from PEDA’s energy share.

Similarly, solar project developers, including Mihit Solar Pvt. Ltd. and others, had sought relief from PSERC for delays in commissioning their projects and prayed for extension of the commercial operation date (COD) and release of PBGs. PSERC granted partial extensions and directed PEDA to return the guarantees accordingly. PEDA challenged these orders, questioning whether PSERC could issue directions to a non-licensee, non-generator entity like itself.

The Tribunal analyzed Section 86(1)(f) of the Electricity Act, which empowers State Commissions to adjudicate disputes between licensees and generating companies. PEDA argued that the Commission lacked jurisdiction since it is not a party defined under the section. However, power developers and PSERC maintained that since PEDA is involved in project implementation and the agreements are linked with Power Purchase Agreements (PPAs), PEDA is a necessary party in such disputes.

After reviewing various judgments, including those of the Supreme Court and past orders of the Tribunal, it was concluded that the Commission has the power to regulate interconnected agreements and processes under its broad regulatory functions under Section 86(1)(b). The Tribunal held that activities undertaken by PEDA in the energy procurement chain, such as issuing tenders and signing implementation agreements, fall within the ambit of regulation. It emphasized that the Commission’s jurisdiction extends to regulating processes involving such agencies when they are linked to power generation and procurement.

The Tribunal thus upheld the Commission’s right to issue directions to PEDA in specific cases where its actions are interwoven with agreements affecting tariff, project delivery timelines, and contractual obligations tied to energy supply. This judgment clarifies the regulatory scope of State Commissions and reinforces the accountability of nodal agencies like PEDA in India’s renewable energy framework.

 

  • Related Posts

    Wood Mackenzie Says Middle East Conflict Is Disrupting Gulf LNG And Shaking Global Power Markets

    The disruption of oil and LNG supplies from the Gulf, driven by the ongoing Middle East conflict, is creating significant challenges for global power markets. Gas and electricity prices are…

    Amazon Commits $30 Million To Carbon Credit Deal Transforming Sustainable Rice Farming In India

    Representational image. Credit: Canva Amazon has announced a $30 million investment to purchase more than 685,000 carbon credits from The Good Rice Alliance (TGRA) in India. The move is aimed…

    Have You Seen?

    Gulf LNG shipping ‘last to recover’ in September

    • April 27, 2026
    Gulf LNG shipping ‘last to recover’ in September

    Eni Misses Q1 Earnings But Lifts Buyback To €2.8 Billion

    • April 27, 2026
    Eni Misses Q1 Earnings But Lifts Buyback To €2.8 Billion

    Baker Hughes Q1 Revenue Beats Estimates by $260 Million as LNG Orders Surge

    • April 27, 2026
    Baker Hughes Q1 Revenue Beats Estimates by $260 Million as LNG Orders Surge

    Analysis: Is neon the next rising gas concern?

    • April 26, 2026
    Analysis: Is neon the next rising gas concern?

    Trump Tells Fox News Iran Can Call US if it Wants to Negotiate

    • April 26, 2026
    Trump Tells Fox News Iran Can Call US if it Wants to Negotiate

    Iran Peace Hopes Fade as Trump Scraps Talks

    • April 26, 2026
    Iran Peace Hopes Fade as Trump Scraps Talks

    Wood Mackenzie Says Middle East Conflict Is Disrupting Gulf LNG And Shaking Global Power Markets

    • April 25, 2026
    Wood Mackenzie Says Middle East Conflict Is Disrupting Gulf LNG And Shaking Global Power Markets

    Amazon Commits $30 Million To Carbon Credit Deal Transforming Sustainable Rice Farming In India

    • April 25, 2026
    Amazon Commits $30 Million To Carbon Credit Deal Transforming Sustainable Rice Farming In India

    U.S. Imposes Preliminary Antidumping Duties On Solar Imports From India, Indonesia, And Laos

    • April 25, 2026
    U.S. Imposes Preliminary Antidumping Duties On Solar Imports From India, Indonesia, And Laos

    SECI Awards 5.6 MW Rooftop Solar Projects Across 14 Government Buildings Under RESCO Model

    • April 25, 2026
    SECI Awards 5.6 MW Rooftop Solar Projects Across 14 Government Buildings Under RESCO Model