CERC Grants Extension For 300 MW Solar Project Land Compliance In Gujarat

The Central Electricity Regulatory Commission (CERC) has granted a six-week extension to Azure Power Sixty-Three Private Limited (AP63PL) for submitting the required land documents for its 300 MW solar power project in Gujarat. The order, issued on July 2, 2026, provides temporary relief to the company and prevents the immediate cancellation of its grid connectivity. The decision was passed by a CERC bench headed by Chairperson Jishnu Barua.

The matter came before the Commission after Azure Power India Private Limited and its subsidiary, AP63PL, requested additional time to meet the land requirement under Regulation 11A(1) of the General Network Access (GNA) Regulations. According to the rules, the developer had to show possession of at least 50% of the required land for the project by July 2, 2026. For the planned 300 MW solar project, this meant securing around 450 acres of land.

If the company had failed to meet the deadline without receiving an extension, the Central Transmission Utility of India Limited (CTUIL) could have cancelled the project’s connectivity approval. It also had the authority to encash bank guarantees worth about ₹39.5 crore, including a ₹30 crore Land Bank Guarantee and ₹9.5 crore in Connectivity Bank Guarantees.

Azure Power informed the Commission that administrative changes in Gujarat had delayed the land acquisition process. In late 2025, the state government reorganized the Banaskantha district and created the new Vav-Tharad district, where the project’s Raghanesda Pooling Station is located. The restructuring led to changes in local revenue offices and administrative jurisdictions, slowing land registration and mutation procedures.

Despite these delays, the company said it had continued work on the project. It informed the Commission that it had invested nearly ₹50 crore in site development and project mobilization. By the time of the final hearing, the developer had secured around 307 acres of land, which represents nearly 34% of the total land required for the project.

Azure Power also pointed out that CERC had proposed a Milestone Extension Charges (MEC) framework to deal with delays through financial penalties instead of immediate cancellation of connectivity. However, the company argued that the framework was still at the draft stage and would not apply before its compliance deadline. It further stated that the associated interstate transmission infrastructure at the Raghanesda Pooling Station is still under construction and is expected to become operational only by the end of 2027. Therefore, granting a short extension would not affect grid operations or other stakeholders.

After reviewing the case, CERC observed that the developer had made substantial progress and that the delay was mainly due to administrative reasons beyond its control. Using its powers to relax regulatory provisions in appropriate cases, the Commission extended the deadline for submitting the required land documents until August 31, 2026.

However, the relief was granted with a condition. Azure Power must pay a compensation amount equal to 5% of its Land Bank Guarantee to CTUIL within 15 days of the order. If the payment is not made within the specified period, CTUIL will be free to take action under the existing GNA Regulations. The Commission also directed that the compensation collected will be used to reduce monthly transmission charges, benefiting the overall power transmission system.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Middle East Weekly: Oman Plans Musandam RE Study, Kuwait Fund Backs 11 MW Solar, L&T Wins 6 GWh BESS Order, ACWA–KOWEPO Partner on RE, NHC–EDF Partner on Clean Energy, ACWA Signs 6 GWh BESS, Masdar Starts 35 MW BESS, Saudi Signs 2 GW BESS Deals

    Oman’s Nama Power and Water Procurement Company (PWP) has issued an RFP for a techno-economic feasibility study to assess renewable energy opportunities in the Musandam Governorate. The study will evaluate…

    ACME Solar Commissions 15 MW/240.752 MWh BESS Project In Rajasthan

    ACME Solar Holdings Limited has announced the successful commissioning of a 15 MW/240.752 MWh Battery Energy Storage System (BESS) project in Rajasthan. The project was commissioned on August 27, 2026,…

    Have You Seen?

    Middle East Weekly: Oman Plans Musandam RE Study, Kuwait Fund Backs 11 MW Solar, L&T Wins 6 GWh BESS Order, ACWA–KOWEPO Partner on RE, NHC–EDF Partner on Clean Energy, ACWA Signs 6 GWh BESS, Masdar Starts 35 MW BESS, Saudi Signs 2 GW BESS Deals

    • August 29, 2026
    Middle East Weekly: Oman Plans Musandam RE Study, Kuwait Fund Backs 11 MW Solar, L&T Wins 6 GWh BESS Order, ACWA–KOWEPO Partner on RE, NHC–EDF Partner on Clean Energy, ACWA Signs 6 GWh BESS, Masdar Starts 35 MW BESS, Saudi Signs 2 GW BESS Deals

    ACME Solar Commissions 15 MW/240.752 MWh BESS Project In Rajasthan

    • August 29, 2026
    ACME Solar Commissions 15 MW/240.752 MWh BESS Project In Rajasthan

    SMBC Reaches Financial Close on JSW Energy’s 210 MW Hybrid Renewable Energy Project in Maharashtra

    • August 29, 2026
    SMBC Reaches Financial Close on JSW Energy’s 210 MW Hybrid Renewable Energy Project in Maharashtra

    SECI Invites Cybersecurity Auditors To Strengthen Renewable Energy Sector Security

    • August 29, 2026
    SECI Invites Cybersecurity Auditors To Strengthen Renewable Energy Sector Security

    The Lifeline of Solar: Why the Right Cable Matters  

    • August 29, 2026
    The Lifeline of Solar: Why the Right Cable Matters  

    Ukraine Drones Spark Fire at Russian Refinery as Fuel Crisis Worsens

    • August 29, 2026
    Ukraine Drones Spark Fire at Russian Refinery as Fuel Crisis Worsens

    India Surpasses 300 GW of Non-Fossil Power Capacity

    • August 28, 2026
    India Surpasses 300 GW of Non-Fossil Power Capacity

    Pakistan’s Five Refineries Set for $6 Billion Upgrade Push

    • August 28, 2026
    Pakistan’s Five Refineries Set for $6 Billion Upgrade Push

    Amazon Nears 1 GW of Wind Power in Sweden With Four New Deals

    • August 28, 2026
    Amazon Nears 1 GW of Wind Power in Sweden With Four New Deals

    Qatar Extends Force Majeure as Hormuz Crisis Still Blocks LNG Traffic

    • August 28, 2026
    Qatar Extends Force Majeure as Hormuz Crisis Still Blocks LNG Traffic