Coal-Fired Delaware Plant Will Close Two Years Early

  • Coal
  • December 26, 2024

Officials with PJM Interconnection said a coal-fired power unit in Delaware can be closed two years ahead of schedule. The grid operator this month announced the Indian River Unit 4, a 411-MW generator in southern Delaware owned by NRG, can be taken offline without negative impacts to power reliability. The Indian River plant, located in Sussex County and which at one time operated four coal-fired units, first came online in 1957.

PJM in an announcement said Delmarva Power, which owns regional transmission, has completed system upgrades supporting grid reliability, enabling the coal-fired unit to shut down 22 months ahead of its scheduled decommissioning date. Delmarva Power on Dec. 18 said it had completed the Vienna-Nelson line upgrade, the last piece of transmission upgrades that will allow Indian River 4 to be retired without creating grid reliability issues.

NRG in June 2021 told PJM it wanted to retire Indian River 4 by June 2022. PJM conducted an analysis of grid reliability and at that time said closing the unit would create issues for grid. The grid operator identified several possible transmission upgrades to address those issues, and said it estimated those upgrades could be completed by year-end 2026.

PJM in a formal request asked NRG to keep Indian River 4 online under a Reliability Must-Run, or RMR, agreement while those upgrades were being completed. NRG agreed to maintain the coal-fired unit under a rate schedule that was approved by the Federal Energy Regulatory Commission. PJM has notified NRG of its intent to terminate the RMR arrangement with the grid upgrades completed.

The RMR will officially end in February of next year, or 22 months prior to the original end-date of December 2026. That will enable a savings of about two years of RMR payments, estimated at about $93 million according to the settlement rate filed with FERC.

“Delmarva’s good work to complete this project far ahead of schedule is a win for our customers, both from a reliability and affordability perspective,” said Mike Bryson, senior vice president-operations at PJM, in a statement. “PJM regards RMR arrangements as a last resort to keep units temporarily operational to maintain system reliability while we make transmission improvements to balance the system, so the sooner we can get the work done, the better.”

Unit 4 at Indian River entered commercial operation in 1980. Units 1 and 2, each with about 82 MW of generation capacity, were retired in 2013. The 177-MW Unit 3 at the site was taken offline in 2014.

Darrell Proctor is a senior editor for POWER.

   

  • Related Posts

    • Coal
    • August 3, 2026
    In the Thar Desert, Pakistan Proves Its Indigenous Coal Can Be a Reliable Power Resource

    Engro Powergen Thar Limited turned an untapped desert coalfield into Pakistan’s cheapest power—and a template for energy independence. Pakistan entered the second half of the 2010s in chronic power deficit.…

    APS Will Convert Retired Coal Units to Burn Natural Gas at Cholla Site

    Arizona Public Service (APS) said it plans to convert two closed coal-fired units at its Cholla Power Plant to burn natural gas. The utility this month said construction on the…

    Have You Seen?

    Oil Price Uncertainty as Negotiations Continue

    • August 8, 2026
    Oil Price Uncertainty as Negotiations Continue

    ADNOC Reports 15 Vessel Attacks as Hormuz Risks Mount

    • August 8, 2026
    ADNOC Reports 15 Vessel Attacks as Hormuz Risks Mount

    Sembcorp Gets Conditional Approval for 300 MW Malaysia-Singapore Renewable Power Project, with 2.2 GWp Floating Solar and 4.3 GWh BESS

    • August 8, 2026
    Sembcorp Gets Conditional Approval for 300 MW Malaysia-Singapore Renewable Power Project, with 2.2 GWp Floating Solar and 4.3 GWh BESS

    Delhi’s Clean Energy Transition: IEEFA-Ember Study Calls for Battery Storage and Rooftop Solar as Demand Rises to 38,482 MU

    • August 8, 2026
    Delhi’s Clean Energy Transition: IEEFA-Ember Study Calls for Battery Storage and Rooftop Solar as Demand Rises to 38,482 MU

    US Energy Firms Leave Rig Count Unchanged in Latest Week, Baker Hughes Says

    • August 8, 2026
    US Energy Firms Leave Rig Count Unchanged in Latest Week, Baker Hughes Says

    US Senate Passes Sweeping Russia Energy Sanctions, Next Stop US House

    • August 8, 2026
    US Senate Passes Sweeping Russia Energy Sanctions, Next Stop US House

    Hundreds of Millions in Grid Deposits Linger in Uncertainty Following Texas Data Center Pause

    • August 8, 2026
    Hundreds of Millions in Grid Deposits Linger in Uncertainty Following Texas Data Center Pause

    Navgrun Plans 1.2 GW TOPCon G12R Manufacturing Facility, Complementing Existing 700 MW Module Capacity in India

    • August 8, 2026
    Navgrun Plans 1.2 GW TOPCon G12R Manufacturing Facility, Complementing Existing 700 MW Module Capacity in India

    LONGi to Supply Hi-MO 9 Modules for 71 MWp Solar Portfolio in Italy

    • August 8, 2026
    LONGi to Supply Hi-MO 9 Modules for 71 MWp Solar Portfolio in Italy

    India Remains Dependent on Imports for 90% of Oil Demand

    • August 7, 2026
    India Remains Dependent on Imports for 90% of Oil Demand