Construction of new Korean reactor begins

Wednesday, 28 May 2025

Construction of new Korean reactor begins
(Image: KHNP)

Korea Hydro & Nuclear Power (KHNP) announced “the start of full-scale structural work by pouring the first concrete for the reactor building, a key construction process for Shin Hanul unit 3, at the Shin Hanul units 3 and 4 construction site on 20 May”.

In November 2014, KHNP signed an agreement with Ulchin County to build Shin Hanul 3 and 4. The company applied for a construction licence for the units in January 2016. Site preparation for the two units was originally scheduled to begin in May 2017, with commercial operation of unit 3 scheduled for December 2022, with unit 4 following a year later.

However, KHNP announced in May 2017 that it had instructed Kepco Engineering & Construction – which signed a design contract in March 2016 – to suspend work for the planned units as a result of the then new President Moon Jae-in’s policy of phasing out nuclear power. Work towards licensing the new units continued.


A ceremony marked the pouring of first concrete (Image: KHNP)

President Yoon Seok-yeol – who assumed power in May 2022 – reversed the former president’s policy of phasing out nuclear power. In July 2022, Yoon encouraged a speedy restoration of the country’s “nuclear power plant ecosystem” after Minister of Trade, Industry and Energy Lee Chang-yang set out plans for revitalising South Korea’s nuclear power industry, including the aim for work on Shin Hanul 3 and 4 to resume as early as 2024.

Preparatory groundwork began for the construction of the two APR1400s following the approval by the South Korean government of the project’s implementation plan in June 2023. This effectively approved 20 licensing and permitting procedures under the jurisdiction of 11 ministries required for the construction of nuclear power plants. South Korea’s Nuclear Safety and Security Commission issued a licence to KHNP for the construction of Shin Hanul 3 and 4 in September last year. A ceremony was held the following month to mark the start of work on the two units.

In March 2023, KHNP and Doosan Enerbility signed a KRW2.9 trillion (USD2.2 billion) contract for the supply of the main equipment for Shin Hanul 3 and 4. Under the contract – which will run for 10 years – Doosan Enerbility will supply the nuclear reactors, steam generators and turbine generators for the two APR1400 units.


An artistic impression of Shin Hanul 3 and 4 (Image: KHNP)

“We will do our best to raise K-Power’s status in the global nuclear power plant construction market by achieving the goal of ‘On-Time, Within Budget’ as well as the safe construction of Shin Hanul units 3 and 4,” said KHNP President Hwang Joo-ho.

“Shin Hanul unit 3 is scheduled to be completed in 2032 after structural construction, installation of equipment such as the reactor, and stage-by-stage testing,” KHNP said. “Shin Hanul units 3 and 4 are expected to contribute significantly to the revitalisation of the nuclear power industry economy as a symbol of strengthening the nuclear power ecosystem after the resumption of operations in 2022, and will become the safest nuclear power plant representing Korea.”

South Korea has four operational APR1400 units – Saeul units 1 and 2 (formerly Shin Kori 3 and 4) and Shin Hanul units 1 and 2. Two further APR1400s are under construction as Saeul units 3 and 4. Four APR1400 units have also been built at the Barakah nuclear power plant in the UAE, which are all now in commercial operation.

Article researched and written by WNN’s

   

  • Related Posts

    Polish companies team up for regional SMR deployment

    The memorandum of understanding (MoU) aims to facilitate collaboration between the companies and establish working groups to jointly explore potential projects in Central and Eastern Europe. These activities will include…

    Reactor vessel installed at Lianjiang unit 2

    State Power Investment Corp (SPIC) said the reactor pressure vessel of unit 2 was successfully hoisted into place on Wednesday, “marking the start of the equipment installation phase for both…

    Have You Seen?

    Russia Preparing to Send 2nd Oil Tanker to Cuba

    • April 3, 2026
    Russia Preparing to Send 2nd Oil Tanker to Cuba

    LNG storage strategies swing into action

    • April 3, 2026
    LNG storage strategies swing into action

    China Directs Private Refiners to Maintain Fuel Output Even At A Loss

    • April 3, 2026
    China Directs Private Refiners to Maintain Fuel Output Even At A Loss

    40% of Russia’s Baltic Oil Export Capacity Offline as Gasoline Ban Widens

    • April 3, 2026
    40% of Russia’s Baltic Oil Export Capacity Offline as Gasoline Ban Widens

    US Crude Jumps More Than 11%, Brent Nearly 8% After Trump Vows More Attacks on Iran

    • April 3, 2026
    US Crude Jumps More Than 11%, Brent Nearly 8% After Trump Vows More Attacks on Iran

    Oil Giants Show Early Interest in US Gulf Deepwater Field Stake, Sources Say

    • April 3, 2026
    Oil Giants Show Early Interest in US Gulf Deepwater Field Stake, Sources Say

    US Regulators Grant California’s Last Nuclear Power Plant 20-Year Operating Life Extension

    • April 3, 2026
    US Regulators Grant California’s Last Nuclear Power Plant 20-Year Operating Life Extension

    US Drillers Add Oil and Gas Rigs for First Time in Three Weeks, Baker Hughes Says

    • April 2, 2026
    US Drillers Add Oil and Gas Rigs for First Time in Three Weeks, Baker Hughes Says

    UK Hosts 36-Country Summit to Reopen Strait of Hormuz

    • April 2, 2026
    UK Hosts 36-Country Summit to Reopen Strait of Hormuz

    Microsoft in Talks With Chevron, Engine No. 1 Over $7 Billion Texas Power Plant

    • April 2, 2026
    Microsoft in Talks With Chevron, Engine No. 1 Over $7 Billion Texas Power Plant