Dismantling of Brunsbüttel vessel progresses

Monday, 6 January 2025

Dismantling of Brunsbüttel vessel progresses
(Image: Vattenfall)

Weighing almost 70 tonnes and with a diameter of more than 6 metres, the lid of the reactor pressure vessel was heavier than any of its internal components, Vattenfall noted. Like the internal components, it has now been dismantled and packed.

The cover dome was made of 8-centimetre-thick heat-resistant steel and was coated on the inside with a 6-millimetre-thick stainless steel plating to protect it from corrosion. The flange had a wall thickness of 42 centimetres. The cover dome was cut into eight segments, with each segment weighing 2.8 tonnes. Six pieces, each weighing 7.7 tonnes, were cut from the surrounding flange.


(Image: Vattenfall)

Some of the tools used in the segmentation process had to be specially made for this project, including the substructure to secure the individual dome segments during cutting and the wire saw used.

“When you break the lid dome down into individual parts, you need a support so that the cut-out parts can be handled safely,” said Michael Maassen, who was responsible for the work on site. “The lid was placed on the substructure and turned seven times. So we moved the lid, not the saw.”

The dismantled parts of the cover have been packed in a total of four 20-foot IP2 containers. The cut pieces will be melted down by a contract partner as part of the release process. The steel produced can then be used for other applications.


(Image: Vattenfall)

The single-unit Brunsbüttel plant was among the eight oldest German reactors taken out of service in March 2011. The 771 MWe boiling water reactor had been idle since 2007 following a grid-facilitated trip. Brunsbüttel was one of eight older power reactors that had their operating licences withdrawn by the federal government shortly after the Fukushima accident in Japan in March 2011. Vattenfall – which owns a 66.7% stake in the plant with PreussenElektra holding the remaining 33.3% – applied in late 2012 to decommission that plant.

With the removal of the last fuel element in June 2017 and the last fuel rods in February 2018, around 99% of the radioactive inventory has left the plant. Of the remaining 1% of the radioactive inventory, more than 90% is in the reactor pressure vessel and its internals. The internals are currently being removed, dismantled and packaged for final storage.

   

  • Related Posts

    US establishes Nuclear Energy Launch Pad

    The Nuclear Energy Launch Pad is intended to build on the Department of Energy (DOE) Reactor Pilot Program – which has 11 projects accepted and a target for three reactors to…

    Decommissioning of Finnish research reactor completed

    The Finnish Reactor 1 (FiR1) water-cooled, pool-type TRIGA Mark II research reactor was commissioned by the Helsinki University of Technology in 1962. The reactor was originally built for research and…

    Have You Seen?

    Helium shortages becoming more likely

    • March 7, 2026
    Helium shortages becoming more likely

    White House Seeks Bolder Action on Energy Prices Amid Iran Conflict

    • March 7, 2026
    White House Seeks Bolder Action on Energy Prices Amid Iran Conflict

    Goldman Sachs Warns Oil May Surge Above $100/bbl if Hormuz Flows Don’t Recover

    • March 7, 2026
    Goldman Sachs Warns Oil May Surge Above $100/bbl if Hormuz Flows Don’t Recover

    American Clean Power Association Report Shows U.S. Added Over 50 GW of Clean Energy Capacity in 2025

    • March 7, 2026
    American Clean Power Association Report Shows U.S. Added Over 50 GW of Clean Energy Capacity in 2025

    E.ON Connects Two-Millionth Renewable Energy Installation To Its Distribution Network In Germany

    • March 7, 2026
    E.ON Connects Two-Millionth Renewable Energy Installation To Its Distribution Network In Germany

    FTC Solar Reports Strong Q4 2025 Results With Revenue Up Nearly 150% Year-Over-Year

    • March 7, 2026
    FTC Solar Reports Strong Q4 2025 Results With Revenue Up Nearly 150% Year-Over-Year

    IFC Backs Major Wind Power And Transmission Project In Argentina

    • March 7, 2026
    IFC Backs Major Wind Power And Transmission Project In Argentina

    IGBC Green Telangana Summit 2026 Brings Global Leaders To Hyderabad To Discuss Net-Zero Cities

    • March 7, 2026
    IGBC Green Telangana Summit 2026 Brings Global Leaders To Hyderabad To Discuss Net-Zero Cities

    Iran War Sends US Crude Up Over $10 a Barrel, Topping $90

    • March 7, 2026
    Iran War Sends US Crude Up Over $10 a Barrel, Topping $90

    Venture Global’s CP2 LNG Plant Costs Increase by $4 Billion

    • March 7, 2026
    Venture Global’s CP2 LNG Plant Costs Increase by $4 Billion