Dismantling of Hamaoka 2 reactor starts

Monday, 17 March 2025

Dismantling of Hamaoka 2 reactor starts
The opening of the reactor pressure vessel of Hamaoka 2 (Image: Chubu)

Hamaoka 1 and 2 are both boiling water reactors, starting up in 1973 and 1978, respectively. Unit 1 had a capacity of 540 MWe while unit 2’s capacity was 840 MWe. Chubu decided to close both units in January 2009 as they required expensive modifications to meet seismic standards imposed after the July 2007 Niigata Chuetsu offshore earthquake.

The utility submitted a decommissioning plan for Hamaoka 1 and 2 in June 2009, which was subsequently revised in September of that year. The overall plan divided the decommissioning of the two units into four stages. The first stage is for preparations for dismantling work at the units, while the second stage covers the dismantling and removal of equipment surrounding the reactors. The third stage is for the dismantling of the reactors themselves, while the fourth covers the demolition of buildings at both units.

The plan was approved by the Ministry of Economy, Trade and Industry in November 2009, when Chubu began stage 1 of the decommissioning programme.

Having completed stage two work at both units, on 18 December last year the Nuclear Regulation Authority approved Chubu’s application to move to the third stage of decommissioning at the units.

Chubu announced on Monday that it has removed the upper lid of the pressure vessel of unit 2, marking the start of the dismantling of the reactor itself. As well as the reactor pressure vessel, the reactor internals and radiation shielding surrounding the vessel will be dismantled.

“Demolition and removal work will proceed steadily with safety as the top priority, and radioactive waste generated will be stored safely within the building until a disposal site is determined,” the utility said.

Chubu plans to dismantle units 1 and 2 over a period of about 12 years, starting with the reactor of unit 2 first. The decommissioning of the two reactors is expected to be completed in fiscal 2042 after the reactor buildings are demolished.

   

  • Related Posts

    Viewpoint: Mindset shift for leadership in era of Final Investment Decisions

    In 2050, we will look back on 2025 as a pivotal time. The question is not whether this period was a turning point, but how boldly we chose the right…

    Five companies selected for HALEU transport funding

    The awards are part of the Department of Energy’s (DOE) HALEU availability programme, established in 2020 to secure a domestic supply of HALEU for civilian domestic research, development, demonstration, and…

    Have You Seen?

    GE Vernova Hits Record High on Bullish 2026 Revenue Outlook, Buyback Boost

    • December 10, 2025
    GE Vernova Hits Record High on Bullish 2026 Revenue Outlook, Buyback Boost

    Venture Global Hits Back at Shell’s Fraud Claims in LNG Arbitration Battle

    • December 10, 2025
    Venture Global Hits Back at Shell’s Fraud Claims in LNG Arbitration Battle

    US Crude Stocks Fall, Fuel Inventories Rise On Robust Refining, EIA Says

    • December 10, 2025
    US Crude Stocks Fall, Fuel Inventories Rise On Robust Refining, EIA Says

    Energy Transfer Says Lake Charles LNG Investment Nod Expected in Early 2026

    • December 10, 2025
    Energy Transfer Says Lake Charles LNG Investment Nod Expected in Early 2026

    BP, Chevron Are Top Bidders at First Trump Gulf of Mexico Oil and Gas Auction

    • December 10, 2025
    BP, Chevron Are Top Bidders at First Trump Gulf of Mexico Oil and Gas Auction

    Coal’s Not Dead Yet: B&W CTO Suggests Fossil Fuels Are Back in Favor

    • December 10, 2025
    Coal’s Not Dead Yet: B&W CTO Suggests Fossil Fuels Are Back in Favor

    New Rules Make German Electricity Grid Investment More Appealing

    • December 10, 2025
    New Rules Make German Electricity Grid Investment More Appealing

    Nigerian Oil Companies Look to Monetize Gas and Reduce Flaring

    • December 10, 2025
    Nigerian Oil Companies Look to Monetize Gas and Reduce Flaring

    New Permitting Freeze Threatens Hundreds of U.S. Solar and Wind Projects

    • December 10, 2025
    New Permitting Freeze Threatens Hundreds of U.S. Solar and Wind Projects

    Senegal Moves to Seize Kosmos Offshore Gas Project

    • December 10, 2025
    Senegal Moves to Seize Kosmos Offshore Gas Project