DOE’s Section 202(c) Emergency Orders Since May 2025: 43 and Counting

  • Coal
  • April 2, 2026
DOE Has Issued More Than 40 Section 202(c) Emergency Orders Since May 2025. Here’s an Updated Log.

Since May 2025, the U.S. Department of Energy (DOE) has issued more than 40 emergency orders and extensions under Section 202(c) of the Federal Power Act—more than in any comparable period in the past two decades. The orders have fallen into two broad categories: retirement deferrals, which compel utilities and grid operators to keep specific generating units online past their planned shutdown dates, and active emergency dispatches, which authorize or require generators to exceed normal operating or environmental permit limits during acute grid stress events.

grants the Secretary of Energy broad authority to temporarily direct the operation of the U.S. electricity system during emergencies—defined as a sudden increase in electricity demand, a shortage of generation or transmission capacity, or a wartime situation. The authority dates to the FPA’s enactment in 1935 and was transferred to DOE when the department was established in 1977.

A 2015 amendment added provisions allowing emergency orders to temporarily override federal, state, and local environmental permit requirements, subject to 90-day renewal limits. From 2000 through June 2025, the DOE exercised the authority in response to 20 events, 11 of them weather-related, according to a  published July 1, 2025. The CRS report noted that the Trump administration’s May 2025 orders—which directed delays in the retirements of coal and gas plants in Michigan and Pennsylvania—represented a novel interpretation of the authority. Unlike prior orders, the relevant grid operators had neither requested DOE action nor identified reliability risks specifically tied to those plant retirements at the time they approved them.

As of March 2026, across all orders issued since May 2025, the DOE has stalled the retirement of at least 4.4 GW of coal capacity.

Scorecard — Updated March 17, 2026

Total orders and extensions since May 2025 40
MW currently held open by retirement-deferral orders ~4.4 GW
Plants currently compelled to stay online 6
Most recent order No. 202-26-18—TransAlta / Centralia Unit 2 (March 16, 2026)
Currently active orders 8

🟢 Active Orders

Orders currently in force. Retirement-deferral orders compel utilities and grid operators to keep specific generating units online past their planned shutdown dates. Ongoing emergency orders authorize generators to exceed normal operating or environmental permit limits. This section is updated as new orders are issued or existing orders are extended.

Retirement Deferrals

Currently Active

  1. West Olive, Mich. (1,560 MW)

  2. Eddystone, Pa. (760 MW)

  3. Centralia, Wash. (~730 MW)

  4. Craig, Colo. (~446 MW)

  5. Wheatfield, Ind. (~847 MW)

  6. Warrick County, Ind. (~103 MW)

Retirement Deferral — Coal
Active
3rd Extension

J.H. Campbell Generating Station — West Olive, Mich.

Original retirement date: May 31, 2025 | Currently active under through May 18, 2026

Current order
Issued Feb. 17, 2026
Expires May 18, 2026
Recipient MISO / Consumers Energy
Grid region MISO
Capacity 1,560 MW
Fuel Coal (subbituminous)
Units 3 units; commissioned 1962, 1967, 1980
Original retirement date May 31, 2025
Order chain

FERC docket

FERC cost‑recovery proceeding on Consumers’ complaint—see FERC’s Aug. 15, 2025 order accepting tariff revisions and related filings in the J.H. Campbell case as linked from DOE’s .

Challenged?

Yes—Michigan, Illinois, Minnesota, and several public interest groups have petitioned the D.C. Circuit to review DOE’s ; opening briefs were filed Dec. 19, 2025, and a related petition challenges FERC’s Aug. 15, 2025, cost‑allocation order referenced in DOE’s .

Why it mattersCampbell is Michigan’s largest remaining coal plant and a critical baseload resource for the MISO North/Central zone. Consumers Energy had announced plans to close the 1,560-MW, three-unit plant—commissioned between 1962 and 1980—15 years ahead of schedule, and MISO approved the retirement in March 2022, finding no reliability problem with the closure.The DOE’s original , issued May 23, 2025, cited NERC’s , which warned MISO faced “elevated risk of operating reserve shortfalls” during peak demand periods, combined with the retirement of approximately 2,700 MW of Michigan coal generation since 2020. Subsequent extensions leaned on operational data. Over the summer of 2025, MISO issued grid alerts on at least 40 of 69 days between June 11 and August 18, including an Energy Emergency Alert on June 23.The DOE also cited the OMS‑MISO annual survey, which projected MISO would face a capacity deficit of 1.4 GW in 2027, growing to 8.2 GW by 2030, as retirements outpace new firm capacity additions.

As POWER reported in , the DOE used that operational record to justify continued emergency intervention through fall and winter. The plant has now been kept online nearly a full year past its planned closure—the longest-running retirement deferral in this series of orders—with the current  running through May 18, 2026.

Retirement Deferral — Gas/Oil
Active
3rd Extension

Eddystone Generating Station, Units 3 & 4 — Eddystone, Pa.

Original retirement date: May 31, 2025 | Currently active under through May 24, 2026

Current order
Issued Feb. 23, 2026
Expires May 24, 2026
Recipient PJM / Constellation Energy
Grid region PJM
Capacity 760 MW combined (380 MW each)
Fuel Dual-fuel (natural gas/distillate oil)
Units Unit 3 commissioned 1974; Unit 4 commissioned 1976
Original retirement date May 31, 2025
Order chain

FERC docket PJM RAA/tariff cost‑allocation proceeding for Eddystone—PJM’s June 26, 2025 filing and FERC’s Aug. 15, 2025 order accepting revisions, as described in DOE’s —plus a generic PJM RAA filing accepted Dec. 5, 2025 establishing a regionwide 202(c) cost‑allocation framework.
Challenged? Yes—the Illinois Office of Attorney General, Maryland Office of People’s Counsel, New Jersey Division of Rate Counsel and several public‑interest organizations also petitioned the D.C. Circuit in September 2025 to review DOE’s emergency  regarding the Eddystone Generating Station, requesting that the court set the order aside, as summarized in DOE’s  and the public‑interest .

Why it mattersEddystone Units 3 and 4 are dual-fuel (natural gas/distillate oil) steam turbines on the Delaware River just south of Philadelphia—380 MW each—and among the last dispatchable peakers in the densely loaded PJM East zone. Constellation submitted its deactivation notice to PJM in December 2023, citing economic pressures, and PJM approved the retirement, finding no reliability concerns. As POWER , the units were more than 50 years old and had seen maintenance deferred in anticipation of shutdown.

The DOE’s original , issued May 30, 2025—the last day before the planned retirement—cited PJM’s own reliability projections showing that under extreme conditions the grid could face supply shortfalls requiring emergency demand response, combined with a tightening supply-demand outlook driven by accelerating retirements across PJM’s footprint. Unlike the Campbell case, PJM publicly supported the order, stating it had “repeatedly documented and voiced its concerns over the growing risk of a supply and demand imbalance driven by the confluence of generator retirements and demand growth.”

Subsequent extensions pointed to PJM’s broader capacity crunch. As POWER reported in , the DOE’s extension orders cited continued tightening reserve margins in PJM East and the absence of near-term replacement firm capacity. The February 2026 extension order also noted that the DOE’s July 2025 Resource Adequacy Report projected mounting national capacity deficits absent intervention.

The units have now been kept online nearly a full year past their planned closure, with the current  running through May 24, 2026.

Retirement Deferral — Coal
Active
1st Extension

Centralia Generating Station, Unit 2—Centralia, Wash.

Original retirement date: Dec. 31, 2025 | Currently active under through June 14, 2026

Current order
Issued March 16, 2026
Expires June 14, 2026
Recipient TransAlta Centralia Generation LLC
Grid region WECC (Pacific Northwest)
Capacity ~730 MW
Fuel Coal
Original retirement date Dec. 31, 2025
Order chain
FERC docket
Challenged?

Yes—on March 2, 2026,  petitioned the Ninth Circuit Court of Appeals to vacate the DOE’s emergency order requiring TransAlta to keep Centralia Unit 2 online; Earthjustice and other environmental groups have filed separate challenges in the same court

Why it matters

Centralia Unit 2 is Washington state’s last coal-fired power plant—a 729.9-MW unit commissioned in 1973, with Unit 1 retired in 2020. Its planned 2025 closure was anchored in both a 2011 state law and a memorandum of agreement between TransAlta and the state that locked in the retirement dates ahead of the units’ expected 2035 end-of-life. As As POWER , Washington state officials said the original order would violate state law, and opponents—including Earthjustice—called it a “manufactured” emergency issued “against everyone’s wishes.”

The DOE’s original , issued Dec. 16, 2025, cited which found the WECC Northwest region at “elevated risk during periods of extreme weather, such as prolonged, far-reaching cold snaps,” and an as retirements outpace new capacity development. The DOE also emphasized that, as a coal-fired unit, Centralia would be difficult to restart once retired. Thermal cycling alone could trigger failures requiring 30–60 days to repair, it said. 

The March 2026 extension () acknowledged a new stressor: which Bonneville Power Administration (BPA) modeling projected would significantly cut hydro generation from March through November and raise the risk of regional outages during summer heat waves. On Jan. 13, 2026,  to intervene and a request for rehearing and stay of the original order, marking one of the more direct state challenges to the DOE’s actions. 

The current order runs through June 14, 2026. Notably, it will put the DOE in direct conflict with which bans coal-generated electricity starting in 2026.

Retirement Deferral — Coal
Active

Craig Station, Unit 1—Craig, Colo.

Original retirement date: Dec. 31, 2025 | Currently active under through March 30, 2026

Current order
Issued Dec. 30, 2025
Expires March 30, 2026
Recipient Tri-State G&T / Platte River Power Authority / Salt River Project / PacifiCorp / Xcel Energy / WAPA Rocky Mountain Region / SPP West
Grid region WECC (Mountain West)
Capacity ~446 MW
Fuel Coal
Original retirement date Dec. 31, 2025
FERC docket
Challenged?

Why it mattersCraig Station Unit 1 is a ~446-MW coal unit in Craig, Colo., co-owned by five utilities—Tri-State G&T, Platte River Power Authority, Salt River Project, PacifiCorp, and Xcel Energy—and coordinated through WAPA Rocky Mountain Region and SPP West. Its retirement had been planned since 2016, driven by both economics and state and federal environmental compliance requirements, including Colorado’s 2016 regional haze State Implementation Plan.

As POWER , the DOE’s , issued Dec. 30, 2025—one day before the planned shutdown—cited a shortage of electric energy and generation facilities in the WECC Mountain West region under the same resource adequacy framework driving other December orders.

The Craig order stands out for two specific reasons. First, the unit went on Dec. 19, 2025, due to a mechanical valve failure, which means it was not even operational when the order was issued. Tri-State confirmed the unit was not made available to operate until Jan. 20, 2026. Second, and more unusually, two of the order’s own recipients—Tri-State and Platte River Power Authority— arguing the order was unwarranted and that keeping the unit available “will not best meet the DOE’s goal of securing dispatchable electricity resources.” The  and , including Sierra Club, GreenLatinos, Vote Solar, Public Citizen, and EDF, have  to intervene and requests for rehearing and stay on Jan. 28, 2026.

Retirement Deferral — Coal
Active

Schahfer Generating Station, Units 17 & 18—Wheatfield, Ind.

Original retirement date: Dec. 31, 2025 | Currently active under through March 23, 2026

Current order
Issued Dec. 23, 2025
Expires March 23, 2026
Recipient NIPSCO / MISO
Grid region MISO
Capacity ~847 MW combined
Fuel Coal
Units Unit 17 commissioned 1983; Unit 18 commissioned 1986
Original retirement date Dec. 31, 2025
FERC docket
Challenged?

Why it mattersSchahfer Units 17 and 18—commissioned in 1983 and 1986, respectively—at ~847 MW combined, represent the largest single block of capacity frozen by a retirement-deferral order after Campbell. Northern Indiana Public Service Co. (NIPSCO), a regulated natural gas and electric utility, had planned to cease coal combustion at Schahfer by year-end 2025 as part of its long-running “, which included significant investment in renewables and storage. MISO reviewed and approved the retirement plan, finding no reliability concerns with the closures.

The DOE’s , issued Dec. 23, 2025, determined that an “emergency exists in portions of the Midwest region of the U.S. due to a shortage of electric energy, a shortage of facilities for the generation of electricity, and other causes.” The order cited the same MISO capacity deficit projections driving the Campbell extensions—a 1.4 GW shortfall projected for 2027 growing to 8.2 GW by 2030—and the same national resource adequacy framing from the DOE’s July 2025 Resource Adequacy Report. As POWER , the Schahfer and Culley orders were part of a rapid-fire series of December 202(c) actions that collectively froze more than 2 GW of coal capacity in a single week.

NIPSCO said publicly that the order delays its retirement plans and noted in that it “now expects” to keep Units 17 and 18 available through March 23, 2026, consistent with the order’s terms. The order will expire on March 23, 2026.

Retirement Deferral — Coal
Active

F.B. Culley Generating Station, Unit 2—Warrick County, Ind.

Original retirement date: Dec. 2025 | Currently active under through March 23, 2026

Current order
Issued Dec. 23, 2025
Expires March 23, 2026
Recipient CenterPoint Energy / MISO
Grid region MISO
Capacity ~103 MW
Fuel Coal
Unit commissioned 1966
Original retirement date Dec. 2025
FERC docket [update when filed]
Challenged? [update]

Why it matters

F.B. Culley Unit 2 is a small, aging coal unit in Warrick County, Indiana—about 103 MW and nearly 60 years old—that CenterPoint Energy had planned to retire by the end of 2025 as part of its long-term coal transition. It is one of the last coal units in CenterPoint’s Indiana portfolio. Culley is also the smallest plant in this series of retirement-deferral orders, underscoring that the DOE is willing to intervene even for relatively modest capacity when it believes regional reserves are tight.

The DOE’s , issued Dec. 23, 2025, paired Culley with NIPSCO’s much larger Schahfer plant in its description of an “emergency” in MISO’s footprint due to a shortage of electric energy, a shortage of facilities for generation, and other causes. The order relied on the same building blocks used in the Campbell and Schahfer orders: NERC’s 2025–2026 Winter Reliability Assessment describing elevated risk in MISO during extreme cold, the OMS‑MISO survey projecting a capacity deficit of 1.4 GW in 2027 growing to 8.2 GW by 2030, and the The DOE’s July 2025 Resource Adequacy Report warning that accelerated retirements and surging load from data centers and industrial growth are outpacing new firm capacity additions.

The Culley order is notable given the DOE’s signal that even relatively small coal units can be deemed “critical” under national emergency framing—potentially affecting dozens of similar aging plants across MISO.

Active Emergency — Ongoing

Active Emergency — Capacity/Reliability
Active
3rd Extension

Puerto Rico Electric Power Authority (PREPA)

Original orders issued May 16, 2025 | Currently active under through May 11, 2026

Current orders
Issued Feb. 10, 2026
Expires May 11, 2026
Recipient PREPA
Grid region Puerto Rico
Order chain

FERC docket N/A
Challenged? No

Why it mattersThe PREPA orders were the first in this series and remain the longest-running, continuous since May 16, 2025. The DOE’s initial  followed an island‑wide blackout and warnings that Puerto Rico could face up to 135 days of forced load shedding absent emergency action. Order 202‑25‑1 directs PREPA to dispatch specified fossil generation units “necessary to expand baseload generation for the island and maintain grid reliability, closing the gap in generation shortfall,” while Order 202‑25‑2 requires aggressive vegetation management and asset management on key transmission corridors to keep critical lines in service.

Three successive renewals— (Aug. 15–Nov. 12, 2025),  (Nov. 13, 2025–Feb. 10, 2026), and  (Feb. 10–May 11, 2026) keep those directives in place, expanding them to cover ongoing “asset management” of specified transmission facilities. The orders effectively federalize key aspects of PREPA’s dispatch and line maintenance under an open‑ended emergency rationale, even as Puerto Rico moves through grid privatization and post‑Hurricane Maria reconstruction.

⚫ Expired Orders

Orders that have expired and were not extended. Orders for an active extension chain are documented in the order chain field of each active card listed above.

Retirement Deferrals Approaching Expiry With No Active Extension

Order Plant / Recipient Region Capacity Issued Expires Type
Craig Station Unit 1 — Tri-State G&T et al.
Craig, Colo.
WECC ~446 MW Dec. 30, 2025 March 30, 2026 No extension issued
Schahfer Station Units 17 & 18 — NIPSCO / MISO
Wheatfield, Ind.
MISO ~847 MW Dec. 23, 2025 March 23, 2026 No extension issued
F.B. Culley Station Unit 2 — CenterPoint / MISO
Warrick County, Ind.
MISO ~103 MW Dec. 23, 2025 March 23, 2026 No extension issued

Active Emergency Dispatches — Expired

Active Emergency — Extreme Weather / Capacity
Expired

January 2026 Cold Weather Emergency

A series of orders issued Jan. 24–31, 2026, across ERCOT, PJM, ISO-NE, NYISO, Duke Energy (Carolinas and Florida), FMPA, OUC, Lakeland Electric, and HPS Energy in response to extreme cold weather. All orders expired by Feb. 14, 2026.

Order Recipient Region Authorization Issued Expired
ERCOT ERCOT Data center backup gen, EEA 3 Jan. 24, 2026 Jan. 27, 2026
PJM PJM All units, max output, permit waiver Jan. 25, 2026 Jan. 31, 2026
ISO-NE ISO-NE All units, max output, permit waiver Jan. 25, 2026 Jan. 31, 2026
ERCOT ERCOT Specified resources, as-needed dispatch Jan. 25, 2026 Jan. 27, 2026
Duke Energy SERC All Duke units, max output, permit waiver Jan. 26, 2026 Jan. 30, 2026
PJM PJM Data center backup gen, EEA 3 Jan. 26, 2026 Jan. 31, 2026
Duke Energy Carolinas / Duke Energy Progress SERC Data center backup gen, EEA 3 Jan. 26, 2026 Jan. 30, 2026
NYISO NYISO All units, max output, permit waiver Jan. 26, 2026 Feb. 2, 2026
HPS Energy Florida (FRCC) All units, max output, permit waiver Jan. 30, 2026 Feb. 3, 2026
Duke Energy (ext.) SERC All Duke units, max output, permit waiver Jan. 29, 2026 Feb. 3, 2026
PJM (ext.) PJM Data center backup gen, EEA 3 Jan. 29, 2026 Feb. 2, 2026
PJM (ext.) PJM All units, max output, permit waiver Jan. 29, 2026 Feb. 2, 2026
Duke Energy Florida Florida (FRCC) All units, max output, permit waiver Jan. 31, 2026 Feb. 3, 2026
OUC Florida (FRCC) All units, max output, permit waiver Jan. 31, 2026 Feb. 6, 2026
FMPA Florida (FRCC) All units, max output, permit waiver Jan. 31, 2026 Feb. 3, 2026
FMPA Florida (FRCC) Backup units, max output, permit waiver Jan. 31, 2026 Feb. 3, 2026
Lakeland Electric Florida (FRCC) Specified resources, as-needed dispatch Jan. 31, 2026 Feb. 6, 2026
OUC Florida (FRCC) Backup units, max output, permit waiver Jan. 31, 2026 Feb. 6, 2026
Duke Energy Carolinas / Duke Energy Progress (ext.) SERC Data center backup gen, EEA 3 Jan. 30, 2026 Feb. 3, 2026
ISO-NE (ext.) ISO-NE All units, max output, permit waiver Jan. 30, 2026 Feb. 14, 2026
Active Emergency — Environmental Run-Hour Waiver
Expired

Wagner Generating Station, Unit 4 — PJM / Talen Energy

PJM | Two orders authorized Talen Energy to operate Wagner Unit 4 beyond its environmental run-hour limits. Both expired Dec. 31, 2025.

Order Type Issued In Effect Expired
Original July 28, 2025 July 28, 2025 Oct. 26, 2025
Extension Oct. 24, 2025 Oct. 26, 2025 Dec. 31, 2025
Active Emergency — Extreme Weather
Expired

Duke Energy Carolinas — June 2025 Heat Emergency

SERC | Issued June 24, 2025, due to extreme weather conditions threatening grid reliability in the Duke Energy Carolinas service area. Expired without extension.

Order Recipient Authorization Issued Expired
Duke Energy Carolinas Specified units, max output, permit waiver June 24, 2025 June 25, 2025

Sonal C. Patel is a POWER senior editor ().

Editor’s Note: This is a living resource tracking every Section 202(c) emergency order issued by the Department of Energy since May 2025. The piece is updated as new orders are issued and as existing orders are extended or expire. Order details are sourced directly from DOE’s CESER office. Readers who identify errors or omissions are encouraged to contact the editors.

Last updated March 18, 2026.

Tagged in:

   

  • Related Posts

    • Coal
    • March 19, 2026
    South Korean Groups Backing New 1.25-GW Coal-Fired Power Plant in Alaska

    A fact sheet published by the U.S. Dept. of the Interior notes a $1-billion agreement between Hyundai Heavy Industries Power Systems and developers of the proposed 1.25-GW Terra Energy Center,…

    • Coal
    • March 6, 2026
    Coal-to-Gas Conversions Approved for Two Arizona Power Plants

    Energy regulators in Arizona have given the go-ahead to convert several units at two coal-fired power plants in the state to burn natural gas. The Arizona Corporation Commission (ACC), which…

    Have You Seen?

    US Drillers Add Oil and Gas Rigs for First Time in Three Weeks, Baker Hughes Says

    • April 2, 2026
    US Drillers Add Oil and Gas Rigs for First Time in Three Weeks, Baker Hughes Says

    UK Hosts 36-Country Summit to Reopen Strait of Hormuz

    • April 2, 2026
    UK Hosts 36-Country Summit to Reopen Strait of Hormuz

    Microsoft in Talks With Chevron, Engine No. 1 Over $7 Billion Texas Power Plant

    • April 2, 2026
    Microsoft in Talks With Chevron, Engine No. 1 Over $7 Billion Texas Power Plant

    US Not Engaged in Any Talks About New Oil Stocks Release, Official Says

    • April 2, 2026
    US Not Engaged in Any Talks About New Oil Stocks Release, Official Says

    BP Names Carol Howle as Deputy CEO, to Oversee Portfolio Review, Strategy

    • April 2, 2026
    BP Names Carol Howle as Deputy CEO, to Oversee Portfolio Review, Strategy

    Trump Speech Unleashes More Pain on US Consumers With $5 Gasoline, Record Diesel in Sight

    • April 2, 2026
    Trump Speech Unleashes More Pain on US Consumers With $5 Gasoline, Record Diesel in Sight

    Australia Considers Emergency Powers to Protect Domestic Gas Supply

    • April 2, 2026
    Australia Considers Emergency Powers to Protect Domestic Gas Supply

    DOE’s Section 202(c) Emergency Orders Since May 2025: 43 and Counting

    • April 2, 2026
    DOE’s Section 202(c) Emergency Orders Since May 2025: 43 and Counting

    Artemis II sets off on cryogenics-fuelled Moonshot

    • April 2, 2026
    Artemis II sets off on cryogenics-fuelled Moonshot

    Oil Surges on Fears of Prolonged War

    • April 2, 2026
    Oil Surges on Fears of Prolonged War