EDF to seek approval for new acoustic fish deterrent system

The original plan

The company building the Hinkley Point C nuclear power plant in southwest England had originally been given planning permission in 2013 for a scheme with low velocity cooling water intake heads and a fish return system to minimise the numbers of fish getting sucked into the plant’s cooling water system. It also involved having 280 underwater speakers to blast out noises – sometimes referred to as a ‘fish disco’ – to keep fish away from the intake areas.

However, EDF later said that the “fast-flowing tides and poor visibility posed significant risks for divers” and instead it was considering replacing the acoustic fish deterrent plan and instead creating up to 900 acres (324 hectares) of saltmarsh in environmental mitigation. However, that plan faced local opposition in community consultations, and legal challenges threatened to add to delays for the nuclear power plant project.

The new acoustic fish deterrent system

In March 2025 EDF announced that trials were beginning on an “innovative” new type of acoustic fish deterrent that it had previously not known about. It involves using ceramic transducers to make targeted very high-frequency sound and was a fairly new technology deployed in the fishing industry to reduce by-catch and had not been considered for use for a power station before.

The company said it would not require a lot of power, so high-voltage power cables would not be needed and it can be lowered into place and maintained from the surface without the need for divers.

EDF said that the high-frequency system would be tuned to “maximise the effectiveness of fish deterrence whilst minimising impacts on larger marine mammals like seals and dolphins”.


The new system can be lowered from surface (Image: EDF)

The trials update

EDF has now reported that  the sea trials ”have been successful and show the system is highly effective at keeping targeted fish species away from Hinkley Point C’s water intake tunnels. For example, testing of tagged twaite shad showed that after the acoustic fish deterrent was turned on, only one tagged shad came within 30 metres of the intake heads. This compares with 14 shad seen in the same area without the system turned on.  The data suggests an effectiveness of more than 90%.  Additional testing in tanks will continue throughout the first half of 2026″.

David Clarke, fisheries scientist and marine ecologist at Swansea University, which carried out the trials, said early results showed the system “clearly working … our results show that a large majority of the tagged shad avoid an area extending some 60 metres from the intake heads protected by the acoustic fish deterrent system”.

Research by Swansea University also showed “that salmon, migrating to the Atlantic, generally use the main channel - well away from Hinkley Point C’s water intakes. In two years, only two tagged salmon were detected within 1km of the intakes”.

What are the other fish protection measures?

Power stations on the coast use seawater in their cooling water systems and Hinkley Point C is using “specially designed intake heads to slow the speed of water entering the cooling tunnels, allowing fish to escape from as close 2 metres in the 20-kilometre-wide channel”. There is also a fish return system to transfer fish back to the sea. Taken together, EDF says that the GBP700 million (USD955 million) fish protection systems means the new plant will have more fish protection measures than any other power plant in the world.

What is the next step?

EDF says the research results will be submitted for regulatory consideration and approval later in 2026 as part of an application for system deployment.

Chris Fayers, Head of Environment at Hinkley Point C, said: “Because the system works even better than we had hoped, it means we can meet all of our  planning obligations and should not need to create 900 acres of saltmarsh as environmental compensation.”

Pete Kibel, Managing Director, Fishtek Marine, said: “Building on our existing acoustic deterrent technology we have now developed a highly effective system that will protect fish in the Severn Estuary and potentially be an option for many more power stations throughout the world.”

The Hinkley Point C project
 
Construction of Hinkley Point C – composed of two EPR pressurised water reactors of 1630 MWe each – began in December 2018, with unit 1 of the plant originally scheduled to start up by the end of 2025, before that was revised to 2027 in May 2022. In 20024, EDF announced that the “base case” was now for unit 1 being operational in 2030, with the cost revised from GBP26 billion (USD32.8 billion) to between GBP31-34 billion, in 2015 prices.

When complete, the two EPR reactors will produce enough carbon-free electricity for six million homes, and are expected to operate for as long as 80 years.

   

  • Related Posts

    Eagles and Newcleo team up for LFR technology demonstrator

    Four European nuclear technology organisations launched the Eagles Consortium in June last year to develop and commercialise the EAGLES-300 small modular reactor (SMR) with the aim of delivering a first…

    India’s Rajasthan unit 7 reaches full power

    Nuclear Power Corporation of India Limited (NPCIL) announced on LinkedIn: “Rajasthan Atomic Power Project – Unit-7 (RAPP-7) successfully achieved rated power operation of 700 MW for the first time on…

    Have You Seen?

    Big Oil Courts Syria for Major Exploration Deals

    • February 11, 2026
    Big Oil Courts Syria for Major Exploration Deals

    Indian Refiners Urged to Buy More U.S. and Venezuela Oil

    • February 11, 2026
    Indian Refiners Urged to Buy More U.S. and Venezuela Oil

    OPEC Data Indicate Small Q2 Surplus Ahead of Key OPEC+ Decision on Resuming Oil Output Hikes

    • February 11, 2026
    OPEC Data Indicate Small Q2 Surplus Ahead of Key OPEC+ Decision on Resuming Oil Output Hikes

    Trump Allows U.S. Firms to Provide Services for Venezuela’s Oil

    • February 11, 2026
    Trump Allows U.S. Firms to Provide Services for Venezuela’s Oil

    TotalEnergies Q4 Profit Slips on Lower Oil Prices

    • February 11, 2026
    TotalEnergies Q4 Profit Slips on Lower Oil Prices

    Novatek’s 2025 Profit Tumbles 60% as Sanctions Bite

    • February 11, 2026
    Novatek’s 2025 Profit Tumbles 60% as Sanctions Bite

    EIA Sees Brent Price Dropping in 2026 and 2027

    • February 11, 2026
    EIA Sees Brent Price Dropping in 2026 and 2027

    US Energy Secretary Set to arrive in Venezuela with Herculean Task of Oil Recovery

    • February 11, 2026
    US Energy Secretary Set to arrive in Venezuela with Herculean Task of Oil Recovery

    TotalEnergies Seizes Full Control of Lukoil Refinery in Netherlands

    • February 11, 2026
    TotalEnergies Seizes Full Control of Lukoil Refinery in Netherlands

    Trump to Order Pentagon to Buy Coal Power for National Security

    • February 11, 2026
    Trump to Order Pentagon to Buy Coal Power for National Security