Environmental approval for Saskatchewan uranium project

The Saskatchewan Minister of Environment the company’s Environmental Impact Statement (EIS) for the shallow, high grade Patterson Lake South (PLS) project on 18 February. The approval follows technical acceptance of the document in June 2025 and an extensive public review period from July to September last year.

Paladin is proposing to construct, operate and decommission underground and surface facilities to support the mining and processing of uranium ore at the PLS project, which it acquired in 2024 through its acquisition of Canadian uranium project developer Fission Uranium Corporation. The main components include an underground mine, an onsite mill to process an average of 1,000 tonnes of ore per day, surface facilities to support the short- and long-term storage of waste rock and ore, an underground tailings management facility, water-handling infrastructure and an effluent treatment circuit, and additional infrastructure to support mining activities.

“The Environmental Assessment approval is an important regulatory milestone for the PLS Project and a prerequisite for permits and licences issued by provincial and federal authorities leading to construction and operation,” Paladin said.

The company said it continues to work closely with the Canadian Nuclear Safety Commission (CNSC) to progress the project within its licensing process at the federal level. Paladin is advancing the technical detail needed to support the application for a construction licence submitted to the CNSC by Fission Uranium Corporation in April 2023.

“The Patterson Lake South Project supports the province’s Growth Plan and Saskatchewan’s role as an energy supplier,” added Minister of Environment Darlene Rowden. “I am pleased to see this project moving forward with strong environmental safeguards. The environmental and sustainability aspects of the PLS Project have been subject to our robust Environmental Assessment process including scrutiny of our review panel of subject matter experts and having undergone considerable public and indigenous consultation. I commend Paladin on its approach to the approval process and congratulate their team on achieving this important milestone in their development.”

Paladin Managing Director and CEO Paul Hemburrow said: “Paladin is delighted that the Minister, the Saskatchewan Government and its environmental regulatory agency have formally recognised that our approach to delivering a sustainable and safe development at the PLS Project is both environmentally and socially appropriate and achievable. The PLS Project is an economically and strategically important development within Canada and we will continue to progress the construction licencing process with the CNSC.”

PLS is on the southwest margin of the Athabasca Basin and incorporates the Triple R deposit, which is both high grade and shallow – mineralisation starts just 50 metres below the surface. The deposit has indicated mineral resources of 114.9 million pounds U3O8 (44,196 tU) at an average grade of 1.94% U3O8, inferred resources of 15.4 million pounds at an average grade of 1.10% and probable reserves of 93.7 million pounds at an average 1.41% U3O8, all reported at a cut-off grade of 0.25%.

In 2023, Fission Uranium Corporation filed an NI 43-101 technical report summarising the feasibility study for the project, including a construction timeline of 3 years with an estimated initial capital cost of CAD1.155 billion (USD840 million) for a ten-year life-of-mine with total production of 90.9 million lbs U3O8 (35,000 tU), and an average unit operating cost of CAD13.02 per pound U3O8.

   

  • Related Posts

    NPCIL signs MoU for Gujarat nuclear power projects

    In what it called “a significant step towards exploring new horizons for nuclear power development in Gujarat”, Nuclear Power Corporation of India Limited (NPCIL) said the MoU would “facilitate collaboration between…

    Hinkley Point B becomes second AGR plant transferred for decommissioning

    Hinkley Point B – comprising two Advanced Gas-cooled Reactors (AGRs) – was first synchronised to the electricity grid in February 1976. The plant generated more than 311 terawatt-hours of electricity…

    Have You Seen?

    Japan’s JERA Creates Oil Storage Firm to Manage National Reserve Sites

    • October 2, 2026
    Japan’s JERA Creates Oil Storage Firm to Manage National Reserve Sites

    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    • October 2, 2026
    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    • October 2, 2026
    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    Latest Dallas Fed Survey Reveals Theme Among Respondents

    • October 2, 2026
    Latest Dallas Fed Survey Reveals Theme Among Respondents

    What is the near-term feasibility of helium-3 fuel for fusion power?

    • October 2, 2026
    What is the near-term feasibility of helium-3 fuel  for fusion power?

    UN Says Global Fuel Subsidies Could Top $1 Trillion

    • October 2, 2026
    UN Says Global Fuel Subsidies Could Top $1 Trillion

    JERA CEO Warns LNG Prices Have Further to Climb

    • October 2, 2026
    JERA CEO Warns LNG Prices Have Further to Climb

    Scaling up: Blue Star’s next phase in Colorado

    • October 2, 2026
    Scaling up: Blue Star’s next phase in Colorado

    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    • October 2, 2026
    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    Oil Prices Come Under Pressure

    • October 2, 2026
    Oil Prices Come Under Pressure