Fourth shell of BREST-OD-300 peripheral cavity installed

Ivan Babich, from theExperimental and Demonstration Energy Complex at the Siberian Chemical Combine, said: “At the moment, the pressure vessel of the BREST-OD-300 reactor block is approximately 70% assembled.”

He said that during 2026 the lead coolant circulation circuit will be formed, the vessel concrete will be completed, and all major internal devices will be installed. “Completion of the reactor vessel assembly is scheduled for the end of 2026,” he added.

The next stage will see the reactor’s peripheral cavities connected to the central cladding, which was installed in September, forming a closed circuit for the lead coolant circulation. This circuit will eventually house steam generators, main circulation pumps, coolant purification system equipment, and other internal reactor equipment. The central cladding is designed to accommodate the core basket and fuel assemblies, Rosatom said.

The BREST-OD-300 reactor has an integral layout – its vessel is not an all-metal structure, instead it is a metal-concrete structure with the space between the cavities gradually filled with concrete during construction. Because of its large size, it can only be delivered in parts, with assembly only possible at the construction site.

The background

The BREST-OD-300 fast reactor is part of Rosatom’s Proryv, or Breakthrough, project to enable a closed nuclear fuel cycle. The 300 MWe unit will be the main facility of the Pilot Demonstration Energy Complex at the Siberian Chemical Combine site. The complex will demonstrate an on-site closed nuclear fuel cycle with a facility for the fabrication/re-fabrication of mixed uranium-plutonium nitride nuclear fuel, as well as a used fuel reprocessing facility.

Recent progress updates included the news in October that the last roofing truss had been moved into place on the turbine hall and the metal shell for the central cavity- which weighs 143 tonnes and is more than 14 metres tall with a diameter of 8 metres – had been installed in place. The four perpheral cavity shells were all installed during December.

Initial operation of the demonstration unit will be focused on performance and after 10 years or so it will be commercially oriented. The plan has been that if it is successful as a 300 MWe (700 MWt) unit, a 1200 MWe (2800 MWt) version will follow – the BR-1200.

   

  • Related Posts

    Deep Isolation launches full-scale demonstration programme

    A groundbreaking event was held on 28 January to mark the beginning of the demonstration project, which is aimed at building stakeholder and regulatory confidence in the company’s deep borehole…

    WANO rolls out new enhanced monitoring initiative

    World Association of Nuclear Operators (WANO), which has traditionally focused on peer review visits to nuclear units every four years, is now also getting key data from each of the…

    Have You Seen?

    US Refiners Struggle to Absorb Sudden Surge in Venezuelan Oil Imports

    • February 4, 2026
    US Refiners Struggle to Absorb Sudden Surge in Venezuelan Oil Imports

    Commonwealth LNG Strikes 20-Year Supply Deal With Mercuria as US Pushes LNG Export Growth

    • February 4, 2026
    Commonwealth LNG Strikes 20-Year Supply Deal With Mercuria as US Pushes LNG Export Growth

    US Soon to Issue General License for Oil Production in Venezuela, Sources Say

    • February 4, 2026
    US Soon to Issue General License for Oil Production in Venezuela, Sources Say

    Marathon Petroleum Beats Earnings Expectations as Refining Margins Surge

    • February 4, 2026
    Marathon Petroleum Beats Earnings Expectations as Refining Margins Surge

    Oil Tanker Rates Soar Amid Shipping Shortages and Middle East Tensions

    • February 3, 2026
    Oil Tanker Rates Soar Amid Shipping Shortages and Middle East Tensions

    Libya Signals a New Gas Push as Europe Searches for Supply

    • February 3, 2026
    Libya Signals a New Gas Push as Europe Searches for Supply

    Ørsted to Sell European Onshore Business for $1.7 Billion

    • February 3, 2026
    Ørsted to Sell European Onshore Business for $1.7 Billion

    Kuwait Seeks Foreign Majors’ Help to Develop Offshore Fields

    • February 3, 2026
    Kuwait Seeks Foreign Majors’ Help to Develop Offshore Fields

    Qatar Moves to Reclaim Japan’s LNG Market With Major Jera Deal

    • February 3, 2026
    Qatar Moves to Reclaim Japan’s LNG Market With Major Jera Deal

    Devon, Coterra Sign ‘Blockbuster’ Merger Deal

    • February 3, 2026
    Devon, Coterra Sign ‘Blockbuster’ Merger Deal