GERC Reserves Final Order On Extension Request For 9 MW Hybrid Project Evacuation Delay

Representational image. Credit: Canva

JSW Renewable Energy (Anjar) Limited filed a petition before the Gujarat Electricity Regulatory Commission (GERC) seeking an extension for completing the evacuation system of its 9 MW hybrid power project. The project is being developed under JSW Neo Energy Limited at the 66/11 kV Gangiyavadar substation of GETCO in Surendranagar district. The petitioner had earlier obtained Stage-I connectivity approval on 30.09.2023 and Stage-II approval on 31.03.2024 after submitting a bank guarantee of ₹90 lakhs.

A connection agreement was executed between the petitioner and GETCO on 23.05.2024. However, on 18.02.2025, GETCO issued a letter instructing the petitioner to commission the evacuation system within 12 months, i.e., by 30.03.2025, failing which actions like encashment of bank guarantee or cancellation of connectivity would be initiated. The petitioner then sought an extension, citing various unforeseen challenges.

The petitioner submitted that delays were primarily due to Right of Way (ROW) issues, heavy rainfall, and Cyclone Asana in August 2024, which impacted project activities until October 2024. Other factors included delays in raw material deliveries due to market demand crises and global supply chain disruptions. Specific ROW disputes included intervention by local authorities, legal cases filed by landowners, and disputes between vendors and sub-vendors. These issues resulted in the obstruction of site access and delayed construction.

The petitioner referred to several legal judgments to support its request and argued that the evacuation line could not be completed due to factors beyond its control. It requested an extension of 158 days to commission the full system.

In response, GETCO’s counsel argued that the company was reminded only of its obligations as per the approved procedure and that the extension could only be granted by the Commission, not GETCO. The respondent emphasized that many of the petitioner’s claims were not substantiated with evidence, such as the exact timing of supply delays or court-ordered restrictions. GETCO also pointed out that Cyclone Asana lasted from 25 August to 2 September 2024 and did not justify delays claimed from July to October 2024.

Further, GETCO argued that regular monsoon disruptions were already factored into project timelines and that delays due to vendor-related issues did not qualify as unforeseen. It also noted that the petitioner’s own status report dated January 2025 projected commissioning by 31.03.2025, indicating it did not anticipate delays at that time.

After hearing both sides, the Commission stated that arguments were completed and directed both parties to file written submissions within four weeks. The matter is now reserved for final order, as recorded in the daily order dated 24.07.2025.

 

  • Related Posts

    Enfinity Expands $183M Bond Facility with Eiffel to Scale Solar and BESS in U.S. and Europe

    Representational image. Credit: Canva Enfinity Global Inc. has expanded its bond facility with Eiffel Investment Group to up to $183 million (€155 million), strengthening its financial capacity to accelerate solar…

    Saatvik Green Energy to Acquire 49% Stake in Intelligent Hydel Solutions, Enters IPP Segment

    Representational image. Credit: Canva Saatvik Green Energy Limited, a fully integrated renewable energy company listed on the BSE and NSE, has announced that its wholly owned subsidiary, Saatvik Cleantech EPC…

    Have You Seen?

    Exxon Mobil Can Sue California Attorney General for Defamation Over Recycling, Judge Rules

    • February 14, 2026
    Exxon Mobil Can Sue California Attorney General for Defamation Over Recycling, Judge Rules

    Enfinity Expands $183M Bond Facility with Eiffel to Scale Solar and BESS in U.S. and Europe

    • February 14, 2026
    Enfinity Expands $183M Bond Facility with Eiffel to Scale Solar and BESS in U.S. and Europe

    Saatvik Green Energy to Acquire 49% Stake in Intelligent Hydel Solutions, Enters IPP Segment

    • February 14, 2026
    Saatvik Green Energy to Acquire 49% Stake in Intelligent Hydel Solutions, Enters IPP Segment

    US Drillers Cut Three Oil Rigs, Add Three Gas Rigs, Leaving Weekly Count Unchanged, Says Baker Hughes

    • February 13, 2026
    US Drillers Cut Three Oil Rigs, Add Three Gas Rigs, Leaving Weekly Count Unchanged, Says Baker Hughes

    Caturus Signs LNG Supply Deal with Saudi Aramco

    • February 13, 2026
    Caturus Signs LNG Supply Deal with Saudi Aramco

    India Explores Gas Power Boost to Stabilize Grid During Peak Hours

    • February 13, 2026
    India Explores Gas Power Boost to Stabilize Grid During Peak Hours

    Enbridge Reports Record 2025 Financial Results, Reaffirms 2026 Financial Guidance, and Grows Secured Backlog to $39 Billion

    • February 13, 2026
    Enbridge Reports Record 2025 Financial Results, Reaffirms 2026 Financial Guidance, and Grows Secured Backlog to $39 Billion

    Pentagon to Move Carrier to Middle East From Caribbean, Officials Say

    • February 13, 2026
    Pentagon to Move Carrier to Middle East From Caribbean, Officials Say

    India’s Reliance Wins US Licence for Venezuelan Oil, Sources Say

    • February 13, 2026
    India’s Reliance Wins US Licence for Venezuelan Oil, Sources Say

    US Allows Oil Majors to Broadly Operate in Venezuela, New Energy Investments

    • February 13, 2026
    US Allows Oil Majors to Broadly Operate in Venezuela, New Energy Investments