GERC Urged To Approve Temporary Bay Use For 127.3 MW Amid Delays At Kalavad Substation In Gujarat

Representational image. Credit: Canva

M/s. Morjar Renewables Pvt. Ltd. approached the Gujarat Electricity Regulatory Commission (GERC) seeking relief regarding the continued use of a temporary 220 kV GIS Feeder Bay at Kalavad Substation. The company had already begun supplying 127.3 MW (64.8 MW wind + 62.5 MW solar) of renewable power through this temporary arrangement, which was initially allowed by the Gujarat Energy Transmission Corporation Limited (GETCO) due to delays in the construction of a permanent bay.

The petitioner cited several uncontrollable challenges that led to the delay. Initially, GETCO allowed temporary bay use until June 30, 2024, which was later extended until December 31, 2024, and finally until March 31, 2025. These extensions were sought because the permanent bay construction, though actively pursued by Morjar Renewables, faced technical hurdles involving different GIS systems—Siemens and Chint—requiring adapter modules, redesigns, and precise measurements. The presence of Chint’s representatives was mandatory for measurements, but repeated non-responsiveness from Chint caused over three months of delay.

Even after placing orders with Siemens in August 2023 and making efforts to secure drawing approvals, delays in approvals from GETCO and coordination issues among the four renewable energy developers (Cleanmax, Suzlon, OP Wind, and Morjar) caused further setbacks. The electrical commissioning of the permanent bay depends on the completion of all four bays due to the interconnected design of the busbar system. The end cap for testing can only be installed after the fourth bay is completed, which means all bays must be ready for testing and commissioning to proceed together.

Morjar emphasized that despite its advanced progress and substantial investment, the delays were entirely beyond its control and largely due to vendor delays, uncoordinated approvals, and a lack of timely response from GETCO-approved vendors. They urged the Commission to allow continued use of the temporary bay until the other developers complete their work. The company feared that without this extension, the renewable capacity would become stranded, harming both the company and consumers who rely on cleaner energy.

Further, GETCO warned of disconnection after March 31, 2025, unless all approvals, testing, and commissioning of the permanent bay were completed. Morjar responded with detailed representations, asserting that disconnection due to delays not caused by them would be unfair and against the spirit of clean energy promotion. The company requested protection from coercive actions, continued connectivity, and equitable consideration from GERC.

The petition concluded that the project is a must-run renewable plant, supplying clean and affordable energy. If forced to disconnect, not only would the petitioner suffer unjustly, but Gujarat’s consumers would also be deprived of renewable power. The Commission was urged to direct GETCO to maintain temporary connectivity until full commissioning of all permanent bays is achieved.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Malaysia Accelerates Energy Transition With Grid Investments, Solar Expansion, And Energy Storage

    Malaysia’s energy transition is expected to gain momentum through increased investments in electricity grid infrastructure, renewable energy projects and energy storage systems, according to a recent analysis by CGS International.…

    Oswal Pumps Announces INR 456 Crore Investment Plan for 1.2 GW TOPCon Solar Cell Manufacturing Facility

    Oswal Pumps Limited has announced plans to establish a 1.2 GW TOPCon (Tunnel Oxide Passivated Contact) solar cell manufacturing facility through its wholly owned subsidiary, Oswal Solar Energy Private Limited…

    Have You Seen?

    Malaysia Accelerates Energy Transition With Grid Investments, Solar Expansion, And Energy Storage

    • October 13, 2026
    Malaysia Accelerates Energy Transition With Grid Investments, Solar Expansion, And Energy Storage

    Oswal Pumps Announces INR 456 Crore Investment Plan for 1.2 GW TOPCon Solar Cell Manufacturing Facility

    • October 13, 2026
    Oswal Pumps Announces INR 456 Crore Investment Plan for 1.2 GW TOPCon Solar Cell Manufacturing Facility

    Power Grid Acquires Lakadia II Transmission Project For Gujarat’s 7,500 MW Renewable Energy Zone

    • October 13, 2026
    Power Grid Acquires Lakadia II Transmission Project For Gujarat’s 7,500 MW Renewable Energy Zone

    CREA: India Curtailed Over 4% of Its Solar Output in July and August

    • October 12, 2026
    CREA: India Curtailed Over 4% of Its Solar Output in July and August

    Saudi Arabia Insists Energy Supply Remains Resilient

    • October 12, 2026
    Saudi Arabia Insists Energy Supply Remains Resilient

    Oil Jumps 2% as Saudi Attacks and Tanker Strikes Revive Hormuz Fears

    • October 12, 2026
    Oil Jumps 2% as Saudi Attacks and Tanker Strikes Revive Hormuz Fears

    On-site oxygen generation offers alternative supply models for African hospitals

    • October 12, 2026
    On-site oxygen generation offers alternative supply models for African hospitals

    QatarEnergy targets new LNG capacity for 2027

    • October 12, 2026
    QatarEnergy targets new LNG capacity for 2027

    BMI Predicts Brent Crude Will Remain Above $100 for Months

    • October 12, 2026
    BMI Predicts Brent Crude Will Remain Above $100 for Months

    Oil Stuck Between Middle East Escalation and Russia-Ukraine Energy Truce

    • October 12, 2026
    Oil Stuck Between Middle East Escalation and Russia-Ukraine Energy Truce