GERC Urged To Approve Temporary Bay Use For 127.3 MW Amid Delays At Kalavad Substation In Gujarat

Representational image. Credit: Canva

M/s. Morjar Renewables Pvt. Ltd. approached the Gujarat Electricity Regulatory Commission (GERC) seeking relief regarding the continued use of a temporary 220 kV GIS Feeder Bay at Kalavad Substation. The company had already begun supplying 127.3 MW (64.8 MW wind + 62.5 MW solar) of renewable power through this temporary arrangement, which was initially allowed by the Gujarat Energy Transmission Corporation Limited (GETCO) due to delays in the construction of a permanent bay.

The petitioner cited several uncontrollable challenges that led to the delay. Initially, GETCO allowed temporary bay use until June 30, 2024, which was later extended until December 31, 2024, and finally until March 31, 2025. These extensions were sought because the permanent bay construction, though actively pursued by Morjar Renewables, faced technical hurdles involving different GIS systems—Siemens and Chint—requiring adapter modules, redesigns, and precise measurements. The presence of Chint’s representatives was mandatory for measurements, but repeated non-responsiveness from Chint caused over three months of delay.

Even after placing orders with Siemens in August 2023 and making efforts to secure drawing approvals, delays in approvals from GETCO and coordination issues among the four renewable energy developers (Cleanmax, Suzlon, OP Wind, and Morjar) caused further setbacks. The electrical commissioning of the permanent bay depends on the completion of all four bays due to the interconnected design of the busbar system. The end cap for testing can only be installed after the fourth bay is completed, which means all bays must be ready for testing and commissioning to proceed together.

Morjar emphasized that despite its advanced progress and substantial investment, the delays were entirely beyond its control and largely due to vendor delays, uncoordinated approvals, and a lack of timely response from GETCO-approved vendors. They urged the Commission to allow continued use of the temporary bay until the other developers complete their work. The company feared that without this extension, the renewable capacity would become stranded, harming both the company and consumers who rely on cleaner energy.

Further, GETCO warned of disconnection after March 31, 2025, unless all approvals, testing, and commissioning of the permanent bay were completed. Morjar responded with detailed representations, asserting that disconnection due to delays not caused by them would be unfair and against the spirit of clean energy promotion. The company requested protection from coercive actions, continued connectivity, and equitable consideration from GERC.

The petition concluded that the project is a must-run renewable plant, supplying clean and affordable energy. If forced to disconnect, not only would the petitioner suffer unjustly, but Gujarat’s consumers would also be deprived of renewable power. The Commission was urged to direct GETCO to maintain temporary connectivity until full commissioning of all permanent bays is achieved.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    AGL Energy To Build One Of Australia’s Largest Solar And Battery Microgrids For Koompartu Farms

    Australian energy retailer AGL Energy is set to develop one of Australia’s largest privately owned, non-mining renewable energy microgrids for Koompartu Farms, the largest almond orchard in South Australia. The…

    Weekly Tech Newsletter | Battery Intelligence, AI & Solar Innovation

    State of Charge (SoC) is one of the most critical indicators of battery health and performance, representing the amount of usable energy available in a battery. This edition of Solarpedia…

    Have You Seen?

    OPEC+ to raise oil production by 188,000 bpd in August

    • July 5, 2026
    OPEC+ to raise oil production by 188,000 bpd in August

    America’s Energy Dominance: The Fruit of Freedom on Our 250th

    • July 4, 2026
    America’s Energy Dominance: The Fruit of Freedom on Our 250th

    Oil Prices Little Changed for Week as US-Iran Peace Efforts Hold

    • July 4, 2026
    Oil Prices Little Changed for Week as US-Iran Peace Efforts Hold

    AGL Energy To Build One Of Australia’s Largest Solar And Battery Microgrids For Koompartu Farms

    • July 4, 2026
    AGL Energy To Build One Of Australia’s Largest Solar And Battery Microgrids For Koompartu Farms

    Weekly Tech Newsletter | Battery Intelligence, AI & Solar Innovation

    • July 4, 2026
    Weekly Tech Newsletter | Battery Intelligence, AI & Solar Innovation

    Aboitiz Renewables Inaugurates 92.55 MWp San Manuel Solar Power Plant In Pangasinan, Philippines

    • July 4, 2026
    Aboitiz Renewables Inaugurates 92.55 MWp San Manuel Solar Power Plant In Pangasinan, Philippines

    Bhutan Commissions 7.83 MW Rooftop Solar Project Across 187 Public Buildings

    • July 4, 2026
    Bhutan Commissions 7.83 MW Rooftop Solar Project Across 187 Public Buildings

    Green Guarantee Company Mobilizes USD 70 Million To Expand Clean Energy Access Across Africa

    • July 4, 2026
    Green Guarantee Company Mobilizes USD 70 Million To Expand Clean Energy Access Across Africa

    Brent Oil Curve Weakens Further as Prompt Supply Glut Swamps Market

    • July 4, 2026
    Brent Oil Curve Weakens Further as Prompt Supply Glut Swamps Market

    What Natural Gas’s Ascendancy Says About the US

    • July 4, 2026
    What Natural Gas’s Ascendancy Says About the US