Higher headcount at Air Products ‘led to cost overruns and project delays’

  • Gas
  • May 6, 2025

Air Products has talked more about the extra recruits it hired from 2018, principally to drive forward its hydrogen projects, several of which it has now .

Newly installed CEO Eduardo Menezes said in the , “The company grew by almost 7,000 employees since 2018 to execute the capital plan, [and] this had a negative impact on both cost and execution quality, leading to significant project delays.”

He said the lesson from this phase was to embrace the importance of refocusing on the company’s core merchant industrial gases business.

A chart illustrated the source of the problem – a 6,700-person surge in staff numbers between 2018 and 2024, climbing to a peak of 23,000 employees globally.

… to continue reading this article and more, please login, register for free, or consider subscribing to gasworld

   

  • Related Posts

    • Gas
    • March 20, 2026
    New group of startups to advance CO2 mineralisation for buildings

       

    • Gas
    • March 20, 2026
    Vallourec secures Indonesia CCS contract

       

    Have You Seen?

    US Loans 45.2 Million Barrels of Strategic Reserve Oil in First Batch Since Iran War

    • March 21, 2026
    US Loans 45.2 Million Barrels of Strategic Reserve Oil in First Batch Since Iran War

    NTPC Explores Power Sector Collaboration with Tajikistan at Bharat Electricity Summit 2026

    • March 21, 2026
    NTPC Explores Power Sector Collaboration with Tajikistan at Bharat Electricity Summit 2026

    MNRE Seeks Expanded Powers Under Electricity Act to Strengthen Renewable Energy Governance

    • March 21, 2026
    MNRE Seeks Expanded Powers Under Electricity Act to Strengthen Renewable Energy Governance

    PM Narendra Modi Shares Article Highlighting India’s Transformative Energy Transition

    • March 21, 2026
    PM Narendra Modi Shares Article Highlighting India’s Transformative Energy Transition

    CEO Roundtable Highlights Urgent Reforms for Power Distribution under Draft National Electricity Policy 2026

    • March 21, 2026
    CEO Roundtable Highlights Urgent Reforms for Power Distribution under Draft National Electricity Policy 2026

    Power Sector: Centre, States Align on Energy Security and Reforms at BES 2026 Ministerial Meet

    • March 21, 2026
    Power Sector: Centre, States Align on Energy Security and Reforms at BES 2026 Ministerial Meet

    Vikram Solar Limited Appoints Sameer Nagpal as CEO

    • March 21, 2026
    Vikram Solar Limited Appoints Sameer Nagpal as CEO

    India Pushes DISCOM Reforms: Shripad Yesso Naik Chairs GoM Meet at Bharat Electricity Summit 2026

    • March 21, 2026
    India Pushes DISCOM Reforms: Shripad Yesso Naik Chairs GoM Meet at Bharat Electricity Summit 2026

    European Commission Launches Consultation for Post-2030 Renewable Energy Framework

    • March 21, 2026
    European Commission Launches Consultation for Post-2030 Renewable Energy Framework

    Energy Storage Growth: India’s BESS Pipeline Hits 92 GWh, Capacity Set to Surge to 346 GWh by 2033

    • March 21, 2026
    Energy Storage Growth: India’s BESS Pipeline Hits 92 GWh, Capacity Set to Surge to 346 GWh by 2033