IAEA mission sees commitment to safety at Shin Kori 2

The 16-day Operational Safety Review Team (OSART) mission included experts from China, the Czech Republic, France, Germany, Spain, the UAE, the UK and the USA.

The purpose of the mission was to independently assess safety performance, identify good practices to share and to propose recommendations for further improvement at the 1 GWe pressurised water reactor which started commercial operation in 2012.

Areas of good practice to be shared with the global nuclear industry were: the development of a virtual field operation system that enables field and control room operators to train together in realistic scenarios; the use of a mechanical process for activated carbon filter waste that reduces manual handling and contamination risks; and the implementation of an integrated disaster monitoring system that consolidates real-time information on external hazards and provides plant-specific warnings.

According to the International Atomic Energy Agency (IAEA) the mission team “found the plant’s staff to be knowledgeable, professional and strongly committed to continuously improving operational safety and reliability of the plant”.

Recommendations for areas to consider to further improve safety included: the implementation and reinforcement of its industrial safety arrangements; and arrangements and practices for contamination control to minimise the risk of contamination spreading.

Juraj Rovny, OSART Team Leader and Head of the Operational Safety Section at the IAEA, said: “The IAEA established the programme in 1982, and the first OSART mission was conducted at Kori Nuclear Power Plant in August 1983. Returning to the Kori site more than four decades later demonstrates the Republic of Korea’s long-standing engagement with international peer review and its commitment to the continuous improvement of operational safety.”

Song Chang-Soo, Director General of Kori NPP, said: “The findings of the mission will help us further strengthen our safety culture and continuously improve operational safety and reliability. We remain firmly committed to making nuclear safety our highest priority.”

The final report from the mission, which was carried out at the request of the South Korean government, will be delivered within three months.

   

  • Related Posts

    Prototype aseismic bearing completed for Rolls-Royce SMR

    Rolls-Royce SMR contracted Skanska UK – a subsidiary of Sweden’s Skanska – in January this year to deliver an aseismic bearing pedestal demonstrator for its small modular reactor (SMR). Aseismic…

    Maritime nuclear project awarded Norwegian public funds

    The Marine Nuclear Propulsion System project is led by Emerald Nuclear Norway and includes participation by Vard Group, Vard Electro, Island Offshore, the Norwegian University of Science and Technology (NTNU), Imperial…

    Have You Seen?

    Empowering Combined Cycle Plants

    • November 18, 2026
    Empowering Combined Cycle Plants

    Small Vessel Trade Thrives in Hormuz as Iran Targets Supertankers

    • November 18, 2026
    Small Vessel Trade Thrives in Hormuz as Iran Targets Supertankers

    EnQuest Exits UK North Sea in $960 Million Deal

    • November 18, 2026
    EnQuest Exits UK North Sea in $960 Million Deal

    Fracking Giants Tapped to Drill Gas Project in Western Australia

    • November 18, 2026
    Fracking Giants Tapped to Drill Gas Project in Western Australia

    China Gas Upsizes Long-Term LNG Supply with U.S. Venture Global

    • November 18, 2026
    China Gas Upsizes Long-Term LNG Supply with U.S. Venture Global

    Intel puts $600m price tag on Israel fab explosion and spec gas leak

    • November 18, 2026
    Intel puts $600m price tag on Israel fab explosion and spec gas leak

    Western Australia Wins Battle Over Federal Gas Reservation Scheme

    • November 18, 2026
    Western Australia Wins Battle Over Federal Gas Reservation Scheme

    EU Moves to Fast-Track Renewables as Oil Import Costs Soar

    • November 18, 2026
    EU Moves to Fast-Track Renewables as Oil Import Costs Soar

    ADNOC Ship Attacked in Hormuz as Maritime Security Risks Rise

    • November 18, 2026
    ADNOC Ship Attacked in Hormuz as Maritime Security Risks Rise

    Agency Reports Suggest Oil Market Approaching Turning Point

    • November 18, 2026
    Agency Reports Suggest Oil Market Approaching Turning Point