KERC Revises APPC To ₹6.73/Unit, Orders Truing-Up For Renewable Energy Payments In Karnataka

Digital payment integration for Karnataka’s renewable energy grid

The Karnataka Electricity Regulatory Commission (KERC) has issued a new order on the Average Pooled Power Purchase Cost (APPC) for the state’s electricity supply companies (ESCOMs), aiming to balance past cost adjustments and provide clarity for the upcoming financial year. The order, dated April 7, 2026, focuses on finalizing the actual costs for FY 2024-25 and setting a provisional benchmark for FY 2026-27 to support stability in the renewable energy sector.

Earlier, the Commission had fixed a provisional APPC of ₹5.54 per unit for FY 2025-26. However, after ESCOMs completed their financial accounts for FY 2024-25, the actual average pooled cost was found to be higher at ₹6.73 per unit. This difference has triggered a truing-up process, which is a standard regulatory mechanism used to reconcile provisional tariffs with actual costs.

Under the existing regulatory framework, including the Seventh Amendment to the Renewable Energy (RE) Regulations, renewable energy generators operating under the Renewable Energy Certificate (REC) mechanism are paid based on a “lower of” formula. They receive either the pooled power purchase cost or 75 percent of the generic tariff determined for their specific technology, whichever is lower.

Since the actual APPC of ₹6.73 per unit is higher than the provisional ₹5.54 per unit, ESCOMs have effectively underpaid renewable energy generators during FY 2025-26. To address this, the Commission has directed ESCOMs to settle the difference between the earlier payments and the revised eligible amount. To ease the financial burden, these payments for energy supplied between April 1, 2025, and March 31, 2026, will be made in three equal installments.

For the upcoming financial year 2026-27, KERC has set a provisional APPC of ₹6.73 per unit, effective April 1, 2026. This rate will serve as an interim value until the actual power purchase data for FY 2025-26 is finalized. During FY 2026-27, ESCOMs will continue to pay renewable energy generators under the REC mechanism using the same “lower of” principle.

The order was passed by a commission panel led by the chairman, along with the member (legal) and the member. The decision provides clarity to both utilities and renewable energy developers by aligning payments with actual market costs while continuing the policy support offered through the REC framework. All figures for FY 2026-27 will be subject to further revision once final data is available at the end of the financial year.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Peak Energy Korea Starts Power Supply From 1.19 MW Youngjin SP Rooftop Solar Plant After Successful Completion

    Peak Energy Korea has announced that the Youngjin SP rooftop solar power plant has officially reached its commercial operation date (COD). This confirms that the facility is now fully generating…

    Electrification Key to India’s Energy Security, Says Incoming ELECRAMA 2027 Chairman

    Electrification is set to play a central role in strengthening India’s energy security framework, particularly amid rising global uncertainties, according to Hartek Singh, who has assumed leadership as Chairman for…

    Have You Seen?

    Peak Energy Korea Starts Power Supply From 1.19 MW Youngjin SP Rooftop Solar Plant After Successful Completion

    • April 13, 2026
    Peak Energy Korea Starts Power Supply From 1.19 MW Youngjin SP Rooftop Solar Plant After Successful Completion

    Electrification Key to India’s Energy Security, Says Incoming ELECRAMA 2027 Chairman

    • April 13, 2026
    Electrification Key to India’s Energy Security, Says Incoming ELECRAMA 2027 Chairman

    APTEL Orders Interest on Refund in Solar Delay Case, Limits Scope of Review Petition

    • April 13, 2026
    APTEL Orders Interest on Refund in Solar Delay Case, Limits Scope of Review Petition

    AdventEnergy Aggregates 746 kW For Two Frabelle Cold Storage Facilities In Navotas Under ERC’s Retail Aggregation Program To Deliver Lower-Priced Power

    • April 13, 2026
    AdventEnergy Aggregates 746 kW For Two Frabelle Cold Storage Facilities In Navotas Under ERC’s Retail Aggregation Program To Deliver Lower-Priced Power

    Telangana Electricity Regulatory Commission Tariff Order FY27 Balancing DISCOM Finances, Consumer Tariffs, And Power Supply Stability

    • April 13, 2026
    Telangana Electricity Regulatory Commission Tariff Order FY27 Balancing DISCOM Finances, Consumer Tariffs, And Power Supply Stability

    NISO Reduces Transmission Losses to 7.05%, Advances Grid Stability Reforms

    • April 13, 2026
    NISO Reduces Transmission Losses to 7.05%, Advances Grid Stability Reforms

    EVN, Quang Tri Authorities Review Progress of Power and Grid Projects in Hanoi

    • April 13, 2026
    EVN, Quang Tri Authorities Review Progress of Power and Grid Projects in Hanoi

    HPERC Finalizes 2026 Conduct Of Business Amendment, Retains Revised Filing Fee Structure Despite Stakeholder Objections In Himachal Pradesh

    • April 13, 2026
    HPERC Finalizes 2026 Conduct Of Business Amendment, Retains Revised Filing Fee Structure Despite Stakeholder Objections In Himachal Pradesh

    OERC Draft 2026 Introduces Renewable Consumption Obligation And Boosts Distributed Solar Adoption In Odisha

    • April 13, 2026
    OERC Draft 2026 Introduces Renewable Consumption Obligation And Boosts Distributed Solar Adoption In Odisha

    PM Narendra Modi Highlights Record Solar Capacity Addition in India

    • April 13, 2026
    PM Narendra Modi Highlights Record Solar Capacity Addition in India