Mozambique Contests TotalEnergies’ $2 Billion Cost from LNG Project Delay

The government of Mozambique disagrees with TotalEnergies’ estimate that the years-long delay in the Mozambique LNG project has cost it and its partners $2 billion in overruns, a source familiar with the matter told Bloomberg on Wednesday.

TotalEnergies and its partners in the $20-billion Mozambique LNG project had to suspend work and declare force majeure for several years amid serious concerns about security due to Islamist attacks near the site.

A recent audit report by UK-based consultancy Bayphase could not confirm the costs TotalEnergies claims to have incurred due to the delay. So Mozambique is not inclined to accept the $2-billion cost overrun estimate, according to Bloomberg’s anonymous source.

Mozambique has yet to approve an updated development plan for the massive LNG export project, which could transform the economy of one of Africa’s poorest countries and increase supply to the global LNG market in the medium to long term.

Set OilPrice.com as a preferred source in Google .

However, in order to approve the updated plan, Mozambique and the project developers need to be on the same page about costs. The government and the French supermajor continue discussions on the costs and the plan and they could still reach an agreement on how to proceed, Bloomberg’s source said.

After a five-year hiatus, in January 2026 TotalEnergies formally re-launched the Mozambique LNG project.

At the end of last year, TotalEnergies lifted the four-year-long force majeure on the Mozambique LNG project, which was stalled due to the precarious security situation near the site of the planned export facility. The project site is close to the town of Palma in the Cabo Delgado province, where Islamic State-affiliated militants were active for years.

In the spring of 2021, following Islamist militant attacks in towns close to the construction site, TotalEnergies declared force majeure and suspended works on the project. Mozambique LNG was Africa’s largest foreign investment when announced.

Due to the force majeure, the goal to achieve first LNG production has slipped, first to 2027, and later, to 2029.

By Tsvetana Paraskova for Oilprice.com

More Top Reads From Oilprice.com

 

  • Related Posts

    Dallas Fed Pres Says World Needs To Consume Less Oil And Gas

    Federal Reserve Bank of Dallas President Lorie Logan says that the world may eventually have to reduce its consumption of oil and natural gas to bring volatile energy markets into…

    China’s CNOOC Starts Production at Bohai Sea Oilfield

    China’s top offshore crude oil and natural gas producer, CNOOC, on Wednesday announced the launch of full production from phase one development of the Kenli 10-2 oilfield in the south…

    Have You Seen?

    American Airlines Sees Resilient Demand Cushioning Fuel-Price Hit

    • May 27, 2026
    American Airlines Sees Resilient Demand Cushioning Fuel-Price Hit

    Chevron Shareholders Reject Proposal for Independent Board Chair

    • May 27, 2026
    Chevron Shareholders Reject Proposal for Independent Board Chair

    Fed’s Logan Warns US Oil Production Won’t Fill Global Supply Gap

    • May 27, 2026
    Fed’s Logan Warns US Oil Production Won’t Fill Global Supply Gap

    China’s CNOOC Starts Production at Bohai Sea Oilfield

    • May 27, 2026
    China’s CNOOC Starts Production at Bohai Sea Oilfield

    Mozambique Contests TotalEnergies’ $2 Billion Cost from LNG Project Delay

    • May 27, 2026
    Mozambique Contests TotalEnergies’ $2 Billion Cost from LNG Project Delay

    Dallas Fed Pres Says World Needs To Consume Less Oil And Gas

    • May 27, 2026
    Dallas Fed Pres Says World Needs To Consume Less Oil And Gas

    France grants €550m to IPCEI for EU semiconductor advancement

    • May 27, 2026
    France grants €550m to IPCEI for EU semiconductor advancement

    Podcast | Technical debrief: solar-powered green hydrogen

    • May 27, 2026
    Podcast | Technical debrief: solar-powered green hydrogen

    Dongfeng claims 1,700km range from new fuel cell-truck tractor combo

    • May 27, 2026
    Dongfeng claims 1,700km range from new fuel cell-truck tractor combo

    Oil Cargo From US Emergency Reserve Heads to Asia, First in Over 3 Years 

    • May 27, 2026
    Oil Cargo From US Emergency Reserve Heads to Asia, First in Over 3 Years