NERSA Publishes Reasons For Eskom Generation Asset Base Redetermination, Confirms No Retrospective Tariff Increase

The National Energy Regulator of South Africa (NERSA) has published its official Reasons for Decision on the redetermination of Eskom’s Generation Regulatory Asset Base (RAB), following approval by the Energy Regulator during its meeting on July 10, 2026. The publication explains the regulatory process and the reasons behind the revised decision affecting Eskom’s allowable revenue.

The redetermination follows a High Court judgment issued on December 21, 2025, which set aside NERSA’s earlier decision and directed the regulator to conduct a new, procedurally fair review. In response to the court’s ruling, NERSA completed a fresh assessment and, on February 7, 2026, approved an additional allowable revenue of R54.734 billion for Eskom.

To comply with legal requirements, NERSA carried out an extensive public consultation process in line with the National Energy Regulator Act of 2004 and the Promotion of Administrative Justice Act of 2000. The regulator invited comments from Eskom, business organizations, industry associations, agricultural and mining groups, municipalities, civil society organizations, and members of the public.

During the consultation, stakeholders raised several important issues, including the valuation of Eskom’s assets, the impact of electricity tariffs on the economy, affordability for consumers, and the importance of maintaining consistency in regulatory decisions. NERSA stated that it carefully considered all submissions while remaining within the limits set by the court order and the evidence already available. The regulator also confirmed that the review was conducted using the approved Multi-Year Price Determination (MYPD4) Methodology.

As part of the redetermination, NERSA reviewed each component of Eskom’s generation asset base. Costs calculated under the Depreciated Replacement Cost method were approved after international benchmarking showed they were reasonable. Transfers of completed projects into commercial operation were also approved to ensure Eskom could recover eligible costs, while expenditures that did not create additional generation capacity were excluded.

The regulator also limited the inclusion of Work Under Construction to projects that will add new electricity generation capacity. Maintenance expenses and outage-related costs were excluded to avoid consumers paying twice for the same services. For coal inventory, NERSA approved a limit of 42 days in line with Eskom’s stockholding policy. Coal stock held beyond this level because of construction delays was excluded from the regulatory asset base to prevent operational inefficiencies from increasing electricity costs for consumers.

NERSA also approved Eskom’s treatment of asset purchases and depreciation, supported by trend analysis and existing regulatory safeguards. The regulator emphasized that the redetermination was limited to the generation asset base, depreciation, and their impact on allowable revenue. It also confirmed that no retrospective electricity tariff adjustments will be applied for the 2025/2026 financial year. The complete Reasons for Decision document has been published on NERSA’s official website for public access and stakeholder review.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    South Africa Farm To Build 4.89 MW Solar PV And 20 MWh BESS For Complete Off-Grid Operations

    Belle Rive Farm in South Africa is taking a major step toward energy independence by developing what is expected to be the country’s largest solar and battery energy storage system…

    Solar Industries India Limited Incorporates South African Investment Subsidiary Through Mauritius Arm

    Solar Industries India Limited has incorporated Solar SA Investments (Pty) Ltd in South Africa through its wholly owned subsidiary, Solar Overseas Mauritius Limited, as part of an internal group restructuring…

    Have You Seen?

    CK Supply expands cylinder filling capacity at Kansas City site

    • July 13, 2026
    CK Supply expands cylinder filling capacity at Kansas City site

    Ampo Poyam wins 15,000-valve Rio Grande LNG contract

    • July 13, 2026
    Ampo Poyam wins 15,000-valve Rio Grande LNG contract

    CMA CGM completes first bioLNG bunkering operation in Rotterdam

    • July 13, 2026
    CMA CGM completes first bioLNG bunkering operation in Rotterdam

    NERSA Publishes Reasons For Eskom Generation Asset Base Redetermination, Confirms No Retrospective Tariff Increase

    • July 13, 2026
    NERSA Publishes Reasons For Eskom Generation Asset Base Redetermination, Confirms No Retrospective Tariff Increase

    South Africa Farm To Build 4.89 MW Solar PV And 20 MWh BESS For Complete Off-Grid Operations

    • July 13, 2026
    South Africa Farm To Build 4.89 MW Solar PV And 20 MWh BESS For Complete Off-Grid Operations

    Solar Industries India Limited Incorporates South African Investment Subsidiary Through Mauritius Arm

    • July 13, 2026
    Solar Industries India Limited Incorporates South African Investment Subsidiary Through Mauritius Arm

    CEA Invites Stakeholder Comments On New BESS Safety Audit Framework, Feedback Due By July 28

    • July 13, 2026
    CEA Invites Stakeholder Comments On New BESS Safety Audit Framework, Feedback Due By July 28

    Vikram Solar Targets 30 GWh BESS Capacity, Plans 12 GW Solar Cell Manufacturing by FY28

    • July 13, 2026
    Vikram Solar Targets 30 GWh BESS Capacity, Plans 12 GW Solar Cell Manufacturing by FY28

    Mufin Green Finance Board To Consider ECB Bonds And NCD Fundraising In July

    • July 13, 2026
    Mufin Green Finance Board To Consider ECB Bonds And NCD Fundraising In July

    Torrent Power Targets 10 GW Renewable Capacity by 2030, Advances 4 GW Project Pipeline

    • July 13, 2026
    Torrent Power Targets 10 GW Renewable Capacity by 2030, Advances 4 GW Project Pipeline