Paks II says excavation work complete, awaiting permission for first concrete

Tuesday, 1 April 2025

Paks II says excavation work complete, awaiting permission for first concrete
(Image: ASE Rosatom)

In December excavation of soil to a depth of 23 metres was under way with more than half of the 75,000 required piles drilled into the ground during soil consolidation works. The first large-scale nuclear power plant equipment – the core catcher – was delivered to the site in August. Also known as a melt trap, the core catcher is a container in the form of a cone made of thermally resistant steel which in the unlikely event of an emergency will securely hold the melt of the core and not allow radioactive substances to leave the containment of the reactor.

Hungary’s Foreign Affairs and Trade Minister Péter Szijjártó said in December he expected first concrete to be poured in the first quarter of 2025. But according to a report by Russia’s Tass news agency that timeline has “had to be adjusted following soil fracture somewhere inside the pit. Rosatom said the incident had no effect on the foundation pit’s technical specifications, but work in that area was suspended in accordance with the Hungarian watchdog’s decision” and the authority “requested a report on additional checks and measures taken in connection with the soil fracture, but has not yet issued permission for first concreting. The permission is expected soon”.

In February Paks II Ltd Chairman and CEO Gergely Jákli, together with Andrea Beatrix Kádár, Chairman of the Hungarian Atomic Energy Authority, gave evidence to the Hungarian Parliament’s Sustainable Development Committee. 

Paks II’s report on the session says that they explained that the “working pit did not collapse, but two corners on the prominent ‘peninsula’ in the southern section broke off, affecting half a percent of the more than 700-metre perimeter wall”. That section is around 400 metres from Paks’ unit 4 “and the incident did not affect the operating power plant at all”. The condition of the wall section in question and its surroundings is continuously monitored, said Jákli.


A picture of the affected section, posted as part of the report on the parliamentary session (Image: Paks II Ltd)

He said that following the corner detachment on 30 January, work in the area immediately stopped and the area was fenced off and an investigation begun into what had happened. He emphasised that the company “was under no time pressure regarding the investigation, and the event will be fully investigated. In the nuclear industry preventive measures must be taken and we have done that”, he added.

The February update also added that “groundwater and the technological water generated from the construction activities are present in controlled conditions thanks to the cut-off wall, in an amount corresponding to the size of the working pit and in a smaller amount compared with the design parameters”. He added “safety continues to be the first priority in the decisions of Paks II Ltd”.

The Paks II project
 

The Paks plant, 100 kilometres south of Budapest, currently comprises four Russian-supplied VVER-440 pressurised water reactors, which started up between 1982 and 1987. An inter-governmental agreement was signed in early 2014 for Russian enterprises and their international sub-contractors to supply two VVER-1200 reactors at Paks as well as a Russian state loan of up to EUR10.0 billion (USD10.5 billion) to finance 80% of the project.

The construction licence application was submitted in July 2020, the construction licence was issued in August 2022 and a construction timetable agreed in 2023, including first concrete this year, with a target to connect the new units to the grid at the beginning of the 2030s.

   

  • Related Posts

    Concreting milestones at Chinese Hualong One units

    China National Nuclear Corporation (CNNC) said the last batch of concrete was poured for the inner dome of Zhangzhou unit 3 on 30 September. “This key milestone marks the completion…

    DOE offers Vistra loan for reactor upgrades and uprates

    Vistra’s planned investments at Beaver Valley in Pennsylvania and Davis-Besse and Perry in Ohio will produce more electricity from existing nuclear plants without requiring new transmission corridors or equivalent new…

    Have You Seen?

    Eskom Launches RFQ to Select Partners for 6 GW Renewable Energy and Battery Portfolio by 2030 In South Africa

    • October 7, 2026
    Eskom Launches RFQ to Select Partners for 6 GW Renewable Energy and Battery Portfolio by 2030 In South Africa

    SECI Invites Bids for 3.68 MW Rooftop Solar Projects On NDMC Buildings At Tariff Below INR 5.13/kWh

    • October 7, 2026
    SECI Invites Bids for 3.68 MW Rooftop Solar Projects On NDMC Buildings At Tariff Below INR 5.13/kWh

    U-Solar Targets 200 MW Renewable Asset Delivery as Revenue Crosses INR 1,000 Crore

    • October 7, 2026
    U-Solar Targets 200 MW Renewable Asset Delivery as Revenue Crosses INR 1,000 Crore

    Zelestra Secures $350 Million Green Financing for 203 MW Reclamation Solar Project in Indiana

    • October 7, 2026
    Zelestra Secures $350 Million Green Financing for 203 MW Reclamation Solar Project in Indiana

    MERC Orders Compensation To Rooftop Solar Developer Over Grid Availability Dispute

    • October 7, 2026
    MERC Orders Compensation To Rooftop Solar Developer Over Grid Availability Dispute

    New Fortress Energy’s Altamira LNG unit offline after turbine fault

    • October 7, 2026
    New Fortress Energy’s Altamira LNG unit offline after turbine fault

    MERC Disposes 730 MW Solar Project Dispute Between CMOPL And MSEDCL In Maharashtra

    • October 7, 2026
    MERC Disposes 730 MW Solar Project Dispute Between CMOPL And MSEDCL In Maharashtra

    String vs Central Inverters: Understanding the Two Utility-Scale Solar Architectures

    • October 7, 2026
    String vs Central Inverters: Understanding the Two Utility-Scale Solar Architectures

    GERC Grants Time To APPPL In 40 MW Wind Project Dispute Over No WTG Zone In Gujarat

    • October 7, 2026
    GERC Grants Time To APPPL In 40 MW Wind Project Dispute Over No WTG Zone In Gujarat

    Nordex Secures 389 MW Wind Turbine Orders in Türkiye, Including Energy Storage Requirements

    • October 7, 2026
    Nordex Secures 389 MW Wind Turbine Orders in Türkiye, Including Energy Storage Requirements