Permission granted for commissioning work on Akkuyu 2

The application for the permit was submitted to the regulator – Nükleer Düzenleme Kurumu (NDK) – in May 2025. The documents detailed “the unit’s commissioning stages, associated technological operations, and the operating personnel training process”, and exceeded 22,000 pages in total.

In granting the permit, the NDK said “Akkuyu Nuclear Inc is authorised to conduct commissioning tests prior to nuclear fuel loading” in accordance with its regulatory requirements.

Turkey’s nuclear regulator issued a permit for the first unit to be commissioned in December 2023, and it is currently preparing for hot and cold testing with dummy fuel loaded.

Developments this year at unit 2 include the 437-tonne turbine generator stator being moved on a special track before being lifted into place in the turbine hall of unit 2 in January, and in March the polar crane was installed in its position, which will be under the reactor building’s inner containment dome. Last month the passive core flooding system tanks – the last large components of the reactor plant primary circuit to be installed using the Open Top technology – were installed. The next phase of work includes installing the sixth tier and the dome of the inner containment building.

Sergey Butskikh, CEO of Akkuyu Nuclear JSC, said: “Obtaining the commissioning permit confirms compliance with regulatory requirements regarding the preparation of supporting documentation and allows us to begin preparations for commissioning operations at the second power unit. In parallel with construction work, specialists will begin the sequential testing and adjustment of equipment.”

Background

Akkuyu, in the southern Mersin province, is Turkey’s first nuclear power plant. Rosatom is building four VVER-1200 reactors, under a so-called BOO (build-own-operate) model. According to the terms of the 2010 Intergovernmental Agreement between the Russian Federation and the Republic of Turkey, the aim was for the commissioning of the first power unit of the nuclear power plant to take place within seven years from receipt of all permits for the construction of the unit.

The licence for the construction of the first unit was issued in 2018, with construction work beginning that year. Nuclear fuel was delivered to the site in April 2023. The aim is for unit 1 to begin supplying Turkey’s energy system during 2026. When the 4,800 MWe plant is completed, it is expected to meet about 10% of Turkey’s electricity needs. All four units are under construction – first concrete for the fourth unit was poured in July 2022.

Turkey has plans for a second nuclear power plant, at Sinop, and has also been in talks with China about plans for a third plant, in the Thrace region in the country’s northwest.

The country is also developing plans for small modular reactors, with the aim of adding 5 GWe of capacity by 2050 – which would mean the equivalent of at least 16 individual SMRs.

   

  • Related Posts

    NPCIL signs MoU for Gujarat nuclear power projects

    In what it called “a significant step towards exploring new horizons for nuclear power development in Gujarat”, Nuclear Power Corporation of India Limited (NPCIL) said the MoU would “facilitate collaboration between…

    Hinkley Point B becomes second AGR plant transferred for decommissioning

    Hinkley Point B – comprising two Advanced Gas-cooled Reactors (AGRs) – was first synchronised to the electricity grid in February 1976. The plant generated more than 311 terawatt-hours of electricity…

    Have You Seen?

    Japan’s JERA Creates Oil Storage Firm to Manage National Reserve Sites

    • October 2, 2026
    Japan’s JERA Creates Oil Storage Firm to Manage National Reserve Sites

    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    • October 2, 2026
    Alaska LNG Hinges on How Much Asian Buyers Will Pay for Energy Security

    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    • October 2, 2026
    WTI Sinks Nearly 4% as EU Weighs Emergency Stockpile Release

    Latest Dallas Fed Survey Reveals Theme Among Respondents

    • October 2, 2026
    Latest Dallas Fed Survey Reveals Theme Among Respondents

    What is the near-term feasibility of helium-3 fuel for fusion power?

    • October 2, 2026
    What is the near-term feasibility of helium-3 fuel  for fusion power?

    UN Says Global Fuel Subsidies Could Top $1 Trillion

    • October 2, 2026
    UN Says Global Fuel Subsidies Could Top $1 Trillion

    JERA CEO Warns LNG Prices Have Further to Climb

    • October 2, 2026
    JERA CEO Warns LNG Prices Have Further to Climb

    Scaling up: Blue Star’s next phase in Colorado

    • October 2, 2026
    Scaling up: Blue Star’s next phase in Colorado

    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    • October 2, 2026
    Shougang, Rio Tinto commission carbon capture trial facility at China steel plant

    Oil Prices Come Under Pressure

    • October 2, 2026
    Oil Prices Come Under Pressure