PFC Consulting Floats ₹43.4 Crore Bid For 3 GW Kurnool-IV Transmission Evacuation Project

Representational image. Credit: Canva

PFC Consulting Limited, a wholly owned subsidiary of Power Finance Corporation Limited, has released a Request for Proposal (RFP) on May 5, 2025, for selecting a bidder to act as a Transmission Service Provider (TSP) for the establishment of the Inter-State Transmission System titled “Transmission System for Kurnool-IV REZ – Phase-II (3 GW).” This project is to be developed through a Tariff-Based Competitive Bidding (TBCB) process following guidelines set by the Government of India under Section 63 of the Electricity Act, 2003.

The scope of the project includes significant augmentation of transmission infrastructure at Kurnool-IV and the development of a new 765/400 kV Shadnagar station. Key components include ICTs of various voltage capacities, multiple 220kV and 400kV line bays, bus couplers, and bus sectionalizers. The timeline for completing these components ranges from 24 to 30 months from the effective date.

The Ministry of Power notified PFCCL as the Bid Process Coordinator via a Gazette Notification dated March 27, 2025. The transmission scheme was also endorsed during the 36th CMETS-SR meeting held on December 19, 2024, and in a special SRPC meeting on February 4, 2025. The National Committee on Transmission approved it on March 6, 2025.

The RFP document was made available for purchase starting May 5, 2025, and can be acquired until July 7, 2025. The deadline for bid submission is July 8, 2025, at 3:00 PM IST. Technical bids will be opened on the same day at 3:30 PM IST.

The bidding process involves a single-stage, two-envelope system conducted electronically via the MSTC platform. Technical and financial capabilities are key criteria, with the financial bid comprising an initial and a final offer through an e-reverse auction.

The selected bidder will acquire 100% equity of the Special Purpose Vehicle (SPV under incorporation, which will implement the project on a build, own, operate, and transfer basis. After 35 years from the Commercial Operation Date (COD), the project assets must be transferred to the Central Transmission Utility or a successor entity at zero cost, free of encumbrances, within 90 days.

Important financial terms include the requirement of a Bid Bond of ₹43.40 crore and a non-refundable RFP purchase fee of ₹5,00,000 plus 18% GST. The selected bidder must also furnish a Contract Performance Guarantee (CPG) whose terms are detailed in the RFP.

All interested parties must ensure full compliance with the RFP’s eligibility and submission criteria to qualify for the bid. This project is a crucial part of the government’s broader initiative to integrate renewable energy zones, supporting the national goal of achieving 500 GW of non-fossil fuel energy capacity by 2030.

 

  • Related Posts

    Top Stories Of The Day: MNRE Moves RE Extensions Online; 14,000 Punjab Solar Projects at Risk and More…

    The Ministry of New and Renewable Energy has mandated that renewable energy project extension requests must now be submitted online through the DCR Portal. The move is expected to streamline…

    IEA Reports Record 108 GW Of Global Battery Storage Additions In 2025

    Representational image. Credit: Canva Battery energy storage is rapidly becoming one of the most important technologies supporting the global energy transition. Driven by declining costs, increasing deployment of renewable energy,…

    Have You Seen?

    Air Liquide launches Kazakhstan business to support Central Asia expansion

    • June 1, 2026
    Air Liquide launches Kazakhstan business to support Central Asia expansion

    Cleaner F-gas options gain ground, but chips still depend on them

    • June 1, 2026
    Cleaner F-gas options gain ground, but chips still depend on them

    H2 Mobility cuts green hydrogen prices 10% at five sites after quota credit sales

    • June 1, 2026
    H2 Mobility cuts green hydrogen prices 10% at five sites after quota credit sales

    Honeywell to create tech and aerospace firms from spin off

    • June 1, 2026
    Honeywell to create tech and aerospace firms from spin off

    Tessalia plans €250m advanced semiconductor packaging site in France

    • June 1, 2026
    Tessalia plans €250m advanced semiconductor packaging site in France

    Record-Low U.S. Shale Well Backlog Curbs Fast Output Gains Amid Export Surge

    • June 1, 2026
    Record-Low U.S. Shale Well Backlog Curbs Fast Output Gains Amid Export Surge

    Oil Prices Rise as US, Iran Trade Strikes, Israel Moves Further Into Lebanon

    • June 1, 2026
    Oil Prices Rise as US, Iran Trade Strikes, Israel Moves Further Into Lebanon

    Danish Shipyard Remains Key Lifeline for Russia’s Yamal LNG Fleet

    • June 1, 2026
    Danish Shipyard Remains Key Lifeline for Russia’s Yamal LNG Fleet

    India’s LNG Industry Pushes for Government Backing as Diesel Costs Surge

    • June 1, 2026
    India’s LNG Industry Pushes for Government Backing as Diesel Costs Surge

    French Navy Seizes Russia-Linked Tanker in the Atlantic

    • June 1, 2026
    French Navy Seizes Russia-Linked Tanker in the Atlantic