Reactor vessel completed for Hinkley Point C’s second unit

The vessel – measuring 13 metres in length and weighing 500 tonnes – was fabricated by Framatome at its Saint-Marcel plant in Chalon-sur-Saône, eastern France.

In a post on LinkedIn, EDF said that a celebration was held at the Saint-Marcel plant on 28 November to mark the completion of the vessel. “The Hinkley Point C delegation watched as the reactor was prepared for shipping to Somerset,” it said.

The reactor pressure vessel is the high strength steel cylinder that will house the reactor core and all associated components, including the reactor vessel internals which support and stabilise the core within the reactor vessel, as well as providing the path for coolant flow and guiding movement of the control rods.

The reactor pressure vessel for unit 1 at Hinkley Point C was completed at Framatome’s Le Creusot facility in Burgundy, central France, in December 2022. It was delivered to the plant construction site in February 2023 and was kept in storage until it was installed within the unit’s reactor building in December 2024.

EDF said the Hinkley Point C delegation “also formally received the first two completed steam generators for unit 2, which will be sent later, in 2026”.


One of the two completed steam generators (Image: EDF)

Steam generators transfer the thermal energy generated in the reactor vessel of a pressurised water reactor from the primary (reactor) cooling system to the secondary (turbine) cooling system, producing the steam to drive the electricity generation turbine.

The first of the eight 25-metre-high, 520-tonne steam generators that the two-unit Hinkley Point C plant will feature was delivered to the site in May 2024 after a journey by sea and road. It was installed in the reactor building of unit 1 in July this year.

Construction of the first of two 1630 MWe EPR reactors at Hinkley Point C began in December 2018, with construction of unit two beginning a year later. The dome of unit 1 was put in place in December 2023. The dome was lifted into place on the second unit’s containment building last week. Last year, EDF announced that the “base case” was now for unit 1 being operational in 2030, with the cost revised from GBP26 billion (USD32.8 billion) to between GBP31-34 billion, in 2015 prices. When complete, the two EPR reactors will produce enough carbon-free electricity for six million homes, and are expected to operate for as long as 80 years.

   

  • Related Posts

    Regulator extends Hermes 1 reactor construction deadline

    Kairos Power was granted a construction permit by the Nuclear Regulatory Commission (NRC) in December 2023 for the Hermes 1 molten salt-cooled demonstration reactor at the Heritage Center Industrial Park…

    Indiana pharma company explores nuclear energy options

    Under the agreement, the parties will: 1. Explore and evaluate the technical, economic, regulatory, and environmental feasibility of nuclear energy solutions in Indiana. 2. Consider potential structures for future procurement…

    Have You Seen?

    TECHNOLOGY: China’s CATL Debuts EV Battery With Speedy Six-Minute Recharge and a 1,000-km Range

    • April 22, 2026
    TECHNOLOGY: China’s CATL Debuts EV Battery With Speedy Six-Minute Recharge and a 1,000-km Range

    US Supreme Court Rrejects Enbridge Challenge to Michigan Pipeline Case

    • April 22, 2026
    US Supreme Court Rrejects Enbridge Challenge to Michigan Pipeline Case

    Oil Flows via Druzhba Set To Restart Today

    • April 22, 2026
    Oil Flows via Druzhba Set To Restart Today

    UK, France Lead 30-Nation Military Push to Reopen Strait of Hormuz

    • April 22, 2026
    UK, France Lead 30-Nation Military Push to Reopen Strait of Hormuz

    Lufthansa Cancels Unprofitable European Summer Routes to Save Jet Fuel

    • April 22, 2026
    Lufthansa Cancels Unprofitable European Summer Routes to Save Jet Fuel

    Traders Place $430 Million Bet on Lower Oil Price Before Trump Ceasefire Extension

    • April 22, 2026
    Traders Place $430 Million Bet on Lower Oil Price Before Trump Ceasefire Extension

    Iran Ceasefire Extension Reduces Immediate Escalation Risk

    • April 22, 2026
    Iran Ceasefire Extension Reduces Immediate Escalation Risk

    Air Liquide to build $350m ASU for Louisiana steel plant

    • April 22, 2026
    Air Liquide to build $350m ASU for Louisiana steel plant

    Terra Innovatum secures helium circulator supply deal

    • April 22, 2026
    Terra Innovatum secures helium circulator supply deal

    Death Toll From Boiler Explosion at Vedanta’s India Coal Power Plant Rises to 24, Triggers Probes

    • April 22, 2026
    Death Toll From Boiler Explosion at Vedanta’s India Coal Power Plant Rises to 24, Triggers Probes