Rooppur unit 1 turbine installation completed

Tuesday, 25 March 2025

Rooppur unit 1 turbine installation completed
(Image: Rosatom)

Alexey Deriy, Atomstroyexport JSC Vice President for Projects in Bangladesh, said: “Installation of the turbine at Rooppur nuclear power plant unit 1 has been completed successfully and this is an important step to the physical start-up of the plant. The turbine set placement on the barring gear and successful control checks confirm accuracy of the assembly and reliability of the equipment.”

Last week, hydraulic tests were completed on the unit, paving the way for hot functional tests to begin.

Rosatom in February 2011 signed an agreement for two reactors to be built at Rooppur, about 160 kilometres from the capital Dhaka, for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015. The Bangladesh Atomic Regulatory Authority issued the first site licence for the Rooppur plant in June 2016, allowing preliminary site works, including geological surveys, to begin.

Construction of the first unit began in November 2017. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

The first batch of nuclear fuel was delivered to the site in October 2023 – the moment that the site got its status as a nuclear facility. Rosatom says that grid connection for Rooppur unit 1 is one of its key targets for the current year.

   

  • Related Posts

    Construction starts at Saskatchewan uranium mine

    The groundbreaking ceremony comes after the company received the final regulatory approval for the project – described by NexGen as the largest development-stage uranium project in Canada – in March.…

    Nuclea Energy to acquire Moltex Energy technology portfolio

    Ontario-headquartered Nuclea is designing the Morpheus microreactor, a compact, transportable and factory-fabricated lead-cooled, graphite-moderated microreactor which is currently in the conceptual design stage. The Moltex asset acquisition would extend Nuclea’s…

    Have You Seen?

    AWG appoints Vice-President of Operations for the North Region

    • August 17, 2026
    AWG appoints Vice-President of Operations for the North Region

    Tencent drives carbon utilisation ‘out of the lab’

    • August 17, 2026
    Tencent drives carbon utilisation ‘out of the lab’

    US CO2 Outlook Report H1 2026

    • August 17, 2026
    US CO2 Outlook Report H1 2026

    U.S. West Coast Refiners Tap Malaysian Supply

    • August 17, 2026
    U.S. West Coast Refiners Tap Malaysian Supply

    South Africa’s Top Court Blocks Shell Wild Coast Exploration

    • August 17, 2026
    South Africa’s Top Court Blocks Shell Wild Coast Exploration

    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    • August 15, 2026
    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    • August 14, 2026
    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    • August 14, 2026
    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    Middle East Oil Tankers Are Going Dark for Longer

    • August 14, 2026
    Middle East Oil Tankers Are Going Dark for Longer

    Drone Strike Sparks Blaze at Key Russian Oil and Fuel Terminal

    • August 14, 2026
    Drone Strike Sparks Blaze at Key Russian Oil and Fuel Terminal