Sizewell C reports project progress to parliament

Friday, 31 January 2025

Sizewell C reports project progress to parliament
The planned Sizewell C plant (Image: EDF Energy)

The update delivered to MPs by Sizewell C – majority owned by the government – outlines the progress made since the project received its Development Consent Order (DCO) one year ago. It was delivered by Julia Pyke and Nigel Cann, Sizewell C’s joint managing directors, at the beginning of Nuclear Week in Parliament.

The MPs also heard that independent due diligence commissioned for the HSBC bank by consultancy firm Enco praised the project’s progress, stating that “Sizewell C is likely the best prepared nuclear project in modern nuclear history”.

The independent assessment concluded: “The Sizewell C project has high chances of avoiding pitfalls that led to a significant schedule and cost overruns on many nuclear projects, including those with EPR reactor models.”

The EDF-led plan is for Sizewell C to feature two EPRs producing 3.2 GW of electricity, enough to power the equivalent of around six million homes for at least 60 years. It would be a similar design to the two-unit plant being built at Hinkley Point C in Somerset, with the aim of building it more quickly and at lower cost as a result of the experience gained from what is the first new nuclear construction project in the UK for about three decades.

The update noted the project is demonstrating the “game-changing benefits” of replicating Hinkley Point C’s reactor design, with GBP1 billion (USD1.2 billion) of cost savings identified so far through innovation and replication.

MPs were told that contracts worth GBP2.5 billion have already been agreed with 290 suppliers across the UK. The project will eventually support over 70,000 jobs across the UK, and generate income for over 2000 UK-based suppliers, with 90% of the supply chain benefits felt in the UK. 1000 people are now employed on site, with a 60% female executive team. Sizewell C’s apprenticeship recruitment has been 50% female since the programme began in 2021. The workforce is currently over 40% female. The project will generate around GBP2.92 of economic value for every GBP1 invested during construction and will create over GBP100 billion of value for the UK over the lifecycle of the project.

Commenting on the update, Pyke and Cann said: “Sizewell C is already a massive driver of growth in the UK, and the team has made extraordinary progress in the year since we received permission to begin construction.

“Sizewell C is on time and on budget and has a stable cost base. That’s in no small part because we’re using exactly the same reactor design as Hinkley Point C, which means we’ve benefitted from the research and innovation already done there.

“Sizewell C is the most important energy project that the UK is likely to undertake in the next two decades, and its benefits will be felt in every constituency across the country.”

The project received an additional GBP2.7 billion in funding from the government in the 2024 Budget and is due to receive its Final Investment Decision in the upcoming Spending Review.

   

  • Related Posts

    Swiss nuclear plants to be fuelled by Kazakh uranium

    Monday, 17 February 2025 Zimmermann and Baiguzhin at Axpo AG’s Swiss headquarters, where the contract was signed (Image: Kazatomprom) The contract between Kazatomprom and Axpo Power AG, alongside Kernkraftwerk Leibstadt…

    Croatia to study potential locations for new nuclear capacity

    Monday, 17 February 2025 (Image: Ministry of Economy) The working group, created by the Ministry of the Economy, brings together experts from academia, the energy sector and government, with a…

    Have You Seen?

    India’s Top Power Firm to Invest $62 Billion in Nuclear Capacity

    • February 17, 2025
    India’s Top Power Firm to Invest $62 Billion in Nuclear Capacity

    Global Warming May Be Reducing Wind Speeds in Europe

    • February 17, 2025
    Global Warming May Be Reducing Wind Speeds in Europe

    Trinasolar Receives World’s First UL 61730 2000V Certification for 210R Modules

    • February 17, 2025
    Trinasolar Receives World’s First UL 61730 2000V Certification for 210R Modules

    Soros to Slim Families Are Plowing Money Into US Shale Oil as Private Equity Retreats

    • February 17, 2025
    Soros to Slim Families Are Plowing Money Into US Shale Oil as Private Equity Retreats

    The West Faces Uranium Shortage Amid Competition From China and Russia

    • February 17, 2025
    The West Faces Uranium Shortage Amid Competition From China and Russia

    Kurdistan Set to Resume Oil Exports in March

    • February 17, 2025
    Kurdistan Set to Resume Oil Exports in March

    Russia Claims OPEC+ Has Not Discussed Delaying Its Oil Supply Increase

    • February 17, 2025
    Russia Claims OPEC+ Has Not Discussed Delaying Its Oil Supply Increase

    Chevron Vice Chairman Confirms Job Cuts

    • February 17, 2025
    Chevron Vice Chairman Confirms Job Cuts

    Masdar, TotalEnergies and EPointZero Sign Framework for Action to Drive Clean Energy Access in Africa and Asia

    • February 17, 2025

    LONGi and Erco Energía Win “Outstanding Project Award 2024” for Pioneering Solar Innovation in Colombia

    • February 17, 2025
    LONGi and Erco Energía Win “Outstanding Project Award 2024” for Pioneering Solar Innovation in Colombia