Sizewell C reports project progress to parliament

Friday, 31 January 2025

Sizewell C reports project progress to parliament
The planned Sizewell C plant (Image: EDF Energy)

The update delivered to MPs by Sizewell C – majority owned by the government – outlines the progress made since the project received its Development Consent Order (DCO) one year ago. It was delivered by Julia Pyke and Nigel Cann, Sizewell C’s joint managing directors, at the beginning of Nuclear Week in Parliament.

The MPs also heard that independent due diligence commissioned for the HSBC bank by consultancy firm Enco praised the project’s progress, stating that “Sizewell C is likely the best prepared nuclear project in modern nuclear history”.

The independent assessment concluded: “The Sizewell C project has high chances of avoiding pitfalls that led to a significant schedule and cost overruns on many nuclear projects, including those with EPR reactor models.”

The EDF-led plan is for Sizewell C to feature two EPRs producing 3.2 GW of electricity, enough to power the equivalent of around six million homes for at least 60 years. It would be a similar design to the two-unit plant being built at Hinkley Point C in Somerset, with the aim of building it more quickly and at lower cost as a result of the experience gained from what is the first new nuclear construction project in the UK for about three decades.

The update noted the project is demonstrating the “game-changing benefits” of replicating Hinkley Point C’s reactor design, with GBP1 billion (USD1.2 billion) of cost savings identified so far through innovation and replication.

MPs were told that contracts worth GBP2.5 billion have already been agreed with 290 suppliers across the UK. The project will eventually support over 70,000 jobs across the UK, and generate income for over 2000 UK-based suppliers, with 90% of the supply chain benefits felt in the UK. 1000 people are now employed on site, with a 60% female executive team. Sizewell C’s apprenticeship recruitment has been 50% female since the programme began in 2021. The workforce is currently over 40% female. The project will generate around GBP2.92 of economic value for every GBP1 invested during construction and will create over GBP100 billion of value for the UK over the lifecycle of the project.

Commenting on the update, Pyke and Cann said: “Sizewell C is already a massive driver of growth in the UK, and the team has made extraordinary progress in the year since we received permission to begin construction.

“Sizewell C is on time and on budget and has a stable cost base. That’s in no small part because we’re using exactly the same reactor design as Hinkley Point C, which means we’ve benefitted from the research and innovation already done there.

“Sizewell C is the most important energy project that the UK is likely to undertake in the next two decades, and its benefits will be felt in every constituency across the country.”

The project received an additional GBP2.7 billion in funding from the government in the 2024 Budget and is due to receive its Final Investment Decision in the upcoming Spending Review.

   

  • Related Posts

    NASA, DOE join forces for ‘new era’ of space technologies

    The MoU, titled “Accelerating American Leadership in Space Nuclear Power and Propulsion”, was signed on 8 October by NASA Administrator Jared Isaacman and US Secretary of Energy Chris Wright at…

    Hanhikivi-1 termination decision cases ‘to continue’

    According to Strana Rosatom, the in-house publication of Russia’s state nuclear corporation Rosatom, Director General Alexey Likhachev said a ruling by the International Chamber of Commerce’s International Court of Arbitration…

    Have You Seen?

    Malaysia Accelerates Energy Transition With Grid Investments, Solar Expansion, And Energy Storage

    • October 13, 2026
    Malaysia Accelerates Energy Transition With Grid Investments, Solar Expansion, And Energy Storage

    Oswal Pumps Announces INR 456 Crore Investment Plan for 1.2 GW TOPCon Solar Cell Manufacturing Facility

    • October 13, 2026
    Oswal Pumps Announces INR 456 Crore Investment Plan for 1.2 GW TOPCon Solar Cell Manufacturing Facility

    Power Grid Acquires Lakadia II Transmission Project For Gujarat’s 7,500 MW Renewable Energy Zone

    • October 13, 2026
    Power Grid Acquires Lakadia II Transmission Project For Gujarat’s 7,500 MW Renewable Energy Zone

    CREA: India Curtailed Over 4% of Its Solar Output in July and August

    • October 12, 2026
    CREA: India Curtailed Over 4% of Its Solar Output in July and August

    Saudi Arabia Insists Energy Supply Remains Resilient

    • October 12, 2026
    Saudi Arabia Insists Energy Supply Remains Resilient

    Oil Jumps 2% as Saudi Attacks and Tanker Strikes Revive Hormuz Fears

    • October 12, 2026
    Oil Jumps 2% as Saudi Attacks and Tanker Strikes Revive Hormuz Fears

    On-site oxygen generation offers alternative supply models for African hospitals

    • October 12, 2026
    On-site oxygen generation offers alternative supply models for African hospitals

    QatarEnergy targets new LNG capacity for 2027

    • October 12, 2026
    QatarEnergy targets new LNG capacity for 2027

    BMI Predicts Brent Crude Will Remain Above $100 for Months

    • October 12, 2026
    BMI Predicts Brent Crude Will Remain Above $100 for Months

    Oil Stuck Between Middle East Escalation and Russia-Ukraine Energy Truce

    • October 12, 2026
    Oil Stuck Between Middle East Escalation and Russia-Ukraine Energy Truce