UPERC Allows UPNEDA To Withdraw Petition Seeking Amendments To RPO Regulations

Representational image. Credit: Canva

The Uttar Pradesh New & Renewable Energy Development Agency (UPNEDA) had filed a petition seeking amendments to the Uttar Pradesh Electricity Regulatory Commission (UPERC) regulations on the Promotion of Green Energy through the Renewable Purchase Obligation (RPO). The petition aimed to align the state’s RPO framework with the trajectory set by the Ministry of Power, Government of India, as per an order issued on July 22, 2022, and its subsequent corrigendum.

During a previous hearing on December 10, 2024, the petitioner was not present. The Commission, in its order dated December 24, 2024, granted UPNEDA another opportunity to pursue the case. However, in the latest hearing, the petitioner’s counsel stated that the petition had been filed in June 2023 for formal adoption, but due to several policy and regulatory changes since then, the petition was no longer relevant in its current form. As a result, UPNEDA requested permission to withdraw the petition.

The Commission reviewed the request and noted that the relief sought in the petition fell under its legislative functions. Even if the petitioner had proceeded with the case, the Commission would not have been able to grant the request in its current form. Since the petitioner no longer wished to pursue the matter, the Commission accepted the withdrawal request and officially disposed of the petition.

This decision indicates that amendments to the RPO regulations in Uttar Pradesh may require a fresh petition reflecting the latest policy changes. The Commission’s ruling highlights the importance of aligning regulatory requests with ongoing policy developments to ensure compliance with national renewable energy goals.

 

  • Related Posts

    India Daily: India Power Capacity Tops 550 GW, CEA Sets New Cybersecurity Rules, CSPDCL Advances 500 MWh BESS, India Accelerates Smart Meters, Kerala Rejects KINESCO Licence and More…

    India’s installed power capacity reached around 552 GW by July 2026, with non-fossil sources contributing more than 300 GW, or over 54% of the total. Solar has emerged as a…

    CERC Approves GNA Milestone Extensions With New Charges For Renewable Energy Projects

    The Central Electricity Regulatory Commission (CERC) has approved a uniform framework allowing renewable power developers additional time to meet key operational milestones under the General Network Access (GNA) Regulations. The…

    Have You Seen?

    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    • August 15, 2026
    Kazakhstan Accuses Big Oil of $10.7 Billion Corruption in Kashagan Oil Project

    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    • August 14, 2026
    Hormuz Tanker Traffic Slumps as U.S.-Iran Standoff Drags On

    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    • August 14, 2026
    Vance Says Cheap Oil and Gas Is Top U.S. Priority in Iran War

    Middle East Oil Tankers Are Going Dark for Longer

    • August 14, 2026
    Middle East Oil Tankers Are Going Dark for Longer

    Drone Strike Sparks Blaze at Key Russian Oil and Fuel Terminal

    • August 14, 2026
    Drone Strike Sparks Blaze at Key Russian Oil and Fuel Terminal

    Hormuz Crisis Pushes Asian Refiners Toward U.S. Oil

    • August 14, 2026
    Hormuz Crisis Pushes Asian Refiners Toward U.S. Oil

    India’s Coal Demand Set to Hit 1.6 Billion Tons by 2030

    • August 14, 2026
    India’s Coal Demand Set to Hit 1.6 Billion Tons by 2030

    Holcim UAE starts cement carbon capture pilot project

    • August 14, 2026
    Holcim UAE starts cement carbon capture pilot project

    Qatar Ras Laffan train five ‘goes offline’

    • August 14, 2026
    Qatar Ras Laffan train five ‘goes offline’

    Vietnam’s Bac Ninh semiconductor investment hits $2.7bn

    • August 14, 2026
    Vietnam’s Bac Ninh semiconductor investment hits $2.7bn