US Offshore Wind Farms in Service, in Construction and Under Development

Crane hangs over the first jacket installed to support a turbine for a wind farm in the waters of the Atlantic Ocean off Block Island
A crane hangs over the first jacket support structure installed to support a turbine for a wind farm in the waters of the Atlantic Ocean off Block Island, Rhode Island July 27, 2015. REUTERS/Brian Snyder/File Photo

(Reuters) – U.S. President Donald Trump suspended new federal offshore wind leasing on his first day back in the Oval Office on Jan. 20, pending an environmental and economic review.

On the same day, Danish energy company Orsted, the world’s biggest offshore wind firm, posted another impairment charge on delays to a U.S. offshore project.

Those are just the latest blows for the offshore wind industry that former President Joe Biden and several states considered key to meeting federal and state clean energy targets.

“Halting offshore wind represents a huge step backward in our efforts to advance a clean energy future and damages the state’s economic opportunities,” North Carolina Governor Josh Stein, a Democrat, told Reuters in an email.

“Investors have signed leases and invested significant resources. They deserve certainty,” Governor Stein said.

In California, where offshore wind is in early stages of development, Adam Stern, Executive Director of Offshore Wind California, an industry trade group, said most of the work was happening at the state level.

“As an industry, we’re focused and moving forward with what is advancing offshore wind in California, and right now most of that is occurring at the state level.” That includes approved spending of roughly $475 million to upgrade ports and $4.6 billion to upgrade power transmission lines to prepare for future offshore wind projects.

In 2023 and 2024, several offshore wind companies, including Orsted, took billions in write-offs, impairments and other cancellation fees after they determined they could no longer complete projects profitably due to rocketing construction costs, higher interest rates and supply chain snags.

In New Jersey, which has seen its share of offshore wind project delays, Governor Phil Murphy, a Democrat, told Reuters in an email that he remains committed to clean energy.

“New Jersey will explore all available options to protect the health of our environment and residents while bolstering energy independence, creating good-paying American jobs, lowering energy bills, and growing New Jersey’s innovation economy,” Governor Murphy said.

There are currently four offshore wind projects operating in the U.S., but one – Vineyard Wind 1 – was shut for part of 2024 after a blade fractured and fell into the ocean in July.

There are also four offshore wind projects under construction and several more in development.

The following factbox lists the projects in service and those under construction and in advanced development that were expected to continue despite Trump’s review:

In Service
State(s)
Company
Start Construction
First Power
Size (MW)
Project
Block Island
Orsted
Coastal Virginia Offshore Wind Pilot
Dominion
South Fork
RI, MA
Orsted (50%) and Global Infrastructure Partners (GIP) Skyborn Renewables unit (50%)
Feb 2022
Dec 2023
Vineyard Wind 1
Iberdrola/Copenhagen Infrastructure Partners
Nov 2021
Jan 2024
Under Construction
State(s)
Company
Start Construction (Estimated)
First Power (Estimated)
Size (MW) Estimated
Revolution Wind
RI, MA
Orsted (50%) and Global Infrastructure Partners (GIP) Skyborn Renewables unit (50%)
Coastal Virginia Offshore Wind (Commercial)
Dominion (50%)/Stonepeak (50%)
Nov 2023
Empire Wind 1
Equinor
May 2024
***2027
Sunrise Wind
RI, MA
Orsted
Jul 2024
Under Development
State(s)
Company
Start Construction (Estimated)
First Power (Estimated)
Size (MW) Estimated
New England Wind 1
Iberdrola
SouthCoast Wind 1
Ocean Winds (EDP/Engie)
late 2025
Community Offshore Wind 1
NY, NJ
RWE/National Grid
MarWin
US Wind owned by Toto Holding’s Renexia
Atlantic Shores South 1
EDF/Shell
Momentum Wind
US Wind owned by Toto Holding’s Renexia
Excelsior Wind
NY, NJ
Copenhagen Infrastructure Partners’ Vineyard Offshore
Leading Light
NY, NJ
Invenergy/energyRE
Vineyard Wind 2
Copenhagen Infrastructure Partners’ Vineyard Offshore
Community Offshore Wind 2
NY, NJ
RWE/National Grid
New England Wind 2
Iberdrola
*** Empire Wind 1 – 2027 is estimated time of commercial power instead of first power

Share This:


More News Articles

 

  • Related Posts

    Goldman Sachs Raises Q2 Brent Oil Price Forecast by $10 to $76 a Barrel

    March 4 (Reuters) – Goldman Sachs  raised on Wednesday its second-quarter 2026 average price forecast for Brent crude ​oil by $10 to $76 per barrel and for WTI by $9…

    There is Little US LNG Producers Can do to Immediately Replace Lost Qatari Cargoes

    Summary US LNG plants running near full capacity, limiting the potential for output increase amid Qatar disruptions Venture Global has the most flexibility, with higher percentage of spot market sales…

    Have You Seen?

    Trump to Meet Tech Giants on Energy Pledge Ahead of Midterms

    • March 4, 2026
    Trump to Meet Tech Giants on Energy Pledge Ahead of Midterms

    There is Little US LNG Producers Can do to Immediately Replace Lost Qatari Cargoes

    • March 4, 2026
    There is Little US LNG Producers Can do to Immediately Replace Lost Qatari Cargoes

    Goldman Sachs Raises Q2 Brent Oil Price Forecast by $10 to $76 a Barrel

    • March 4, 2026
    Goldman Sachs Raises Q2 Brent Oil Price Forecast by $10 to $76 a Barrel

    Hormuz Shutdown Worsens After US Hits Iranian Warship; Tankers Stranded for Fifth Day

    • March 4, 2026
    Hormuz Shutdown Worsens After US Hits Iranian Warship; Tankers Stranded for Fifth Day

    Asian LNG Prices Soar to Three-Year High

    • March 4, 2026
    Asian LNG Prices Soar to Three-Year High

    Goldman Sachs Hikes Q2 Brent Oil Price Forecast by $10

    • March 4, 2026
    Goldman Sachs Hikes Q2 Brent Oil Price Forecast by $10

    Barclays Warns Grid Constraints Could Strand Renewables Assets

    • March 4, 2026
    Barclays Warns Grid Constraints Could Strand Renewables Assets

    Alfa Laval to supply cryogenic tech for South Korea’s first liquid air energy storage plant

    • March 4, 2026
    Alfa Laval to supply cryogenic tech for South Korea’s first liquid air energy storage plant

    Japan studies bio-based CO2 liquefaction from waste incineration

    • March 4, 2026
    Japan studies bio-based CO2 liquefaction from waste incineration

    Solar chemistry moves NASA closer to lunar oxygen production

    • March 4, 2026
    Solar chemistry moves NASA closer to lunar oxygen production