US Utilities Commit to 116 GW Of Large-Load Capacity Growth, Equal To 15.5% of Current National Peak Demand

Representational image. Credit: Canva

A new Wood Mackenzie study reveals that U.S. utilities are preparing for substantial growth in large load capacity, with 116 gigawatts (GW) already committed or under construction—equivalent to 15.5% of the nation’s current peak electricity demand. When projects under advanced discussion or short-term forecasts are included, the total rises to 147 GW, or 20% of peak demand. The report, “No Turning Back: An Analysis of Utility Large Load Pipelines,” highlights that much of this capacity is expected to come online within this decade. By 2030, about 60 GW—representing 8% of today’s peak demand—is projected to be added.

Utilities anticipate 93 GW will be operational by 2035, although little information has been disclosed about projects beyond that year. Ben Hertz-Shargel, Wood Mackenzie’s global head of Grid Edge, noted that utilities are rapidly committing to new loads this decade, but warned that the market may struggle to meet this demand on the planned timeline, potentially delaying projects. The study also points to a shift in where large load projects are being developed. Currently, 91% of the 17 GW under construction is located in regulated markets.

However, 54% of committed capacity not yet under construction and 65% of advanced-discussion capacity are planned for deregulated markets. Nearly three-quarters of these high-confidence loads are concentrated in the ERCOT and PJM regions. According to Hertz-Shargel, the growing presence of projects in deregulated markets—especially in ERCOT—carries risks such as supply shortfalls and price increases for smaller customers. These challenges have already prompted market interventions in Texas and PJM, with further regulatory actions expected.

The report warns that pipeline certainty is declining, as new requests outpace the advancement or withdrawal of existing projects. While some utilities have slightly increased their high-confidence capacity, its overall share of the pipeline has decreased in recent quarters. Data centers are a major factor adding to this uncertainty. For projects exceeding 300 MW, the ramp-up to full contract capacity can take much longer than four years, making it difficult to predict when the grid will actually experience the new load. Hertz-Shargel emphasized that the timing of demand ultimately depends on data center developers, not just utilities.


Subscribe to get the latest posts sent to your email.

 

  • Related Posts

    Toyota Supplier JTEKT Installs Large Solar Carport In Japan Under 20-Year PPA To Boost Clean Energy Transition

    Electric cars charging at stations beneath solar panels in a parking lot JTEKT Corporation, a key supplier to the Toyota Group, has taken an important step toward cleaner energy by…

    South Africa’s Renewable Energy Sector Expands Strongly In 2025 With Rising Capacity And Socio-Economic Impact

    A large renewable energy farm with solar panels and wind turbines near mountains South Africa’s renewable energy sector showed strong growth and positive impact in 2025, according to the latest…

    Have You Seen?

    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    • April 11, 2026
    US Loans 8.5 Million Barrels of SPR Oil in Second Batch Since Iran War

    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    • April 10, 2026
    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    Vance Warns Iran Not to “Play Us” as He Leaves for Talks

    • April 10, 2026
    Vance Warns Iran Not to “Play Us” as He Leaves for Talks

    Occidental Reports Lower Realized Oil Prices Even as Iran Conflict Drives Up Crude Rates

    • April 10, 2026
    Occidental Reports Lower Realized Oil Prices Even as Iran Conflict Drives Up Crude Rates

    US Drillers Cut Oil and Gas Rigs for Third Time in Four Weeks, Baker Hughes Says

    • April 10, 2026
    US Drillers Cut Oil and Gas Rigs for Third Time in Four Weeks, Baker Hughes Says

    What the Trump Tax Breaks Giveth, the Gasoline Pump Taketh Away

    • April 10, 2026
    What the Trump Tax Breaks Giveth, the Gasoline Pump Taketh Away

    US Likely to Extend Russian Oil Waiver to Temper Iran War Shock, Sources Say

    • April 10, 2026
    US Likely to Extend Russian Oil Waiver to Temper Iran War Shock, Sources Say

    FERC Approves NextDecade’s Request for More Workers and Longer Hours at Texas Site

    • April 10, 2026
    FERC Approves NextDecade’s Request for More Workers and Longer Hours at Texas Site

    Ranked: The Countries Building the Most Nuclear Power – Visual Capitalist

    • April 10, 2026
    Ranked: The Countries Building the Most Nuclear Power – Visual Capitalist

    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022

    • April 10, 2026
    Oil Ends Lower Ahead of U.S.-Iran Ceasefire Talks, Posts Steepest Weekly Loss Since 2022