APTEL Reviews KERC Order On 50 MW Solar Project Delay And Liquidated Damages

Representational image. Credit: Canva

Hero Future Energies filed an appeal challenging the Karnataka Electricity Regulatory Commission’s (KERC) order that denied the company an extension of 180 days for commissioning its solar project. The company argued that the delay was not entirely their fault and was caused by procedural and administrative delays beyond their control. The main dispute began after the original Power Purchase Agreement (PPA) was signed on 19 February 2014. Although the PPA was approved by KERC on 13 March 2014, the approval took 22 days and this delay was not immediately factored into the project timeline.

Hero Future Energies contended that the effective date of the PPA should be considered from the date of KERC’s approval, not the date of signing. They also highlighted that the signed copy of the PPA was only received on 13 August 2014, causing further delays in initiating project financing and land acquisition. Despite this, the company completed the commissioning of the solar plant on 14 August 2015.

To accommodate the delay, the second respondent, Hubli Electricity Supply Company (HESCOM), granted an extension of 5 months and 8 days through a letter dated 17 October 2014. This extension was later formalized through a Supplementary PPA signed on 20 October 2015. However, when this Supplementary PPA was submitted to KERC for approval, KERC pointed out deficiencies and insisted on reducing the tariff from ₹7.47 per kWh to ₹6.50 per kWh, the latter being applicable on the date of commissioning.

When Hero Future Energies took the matter to the High Court, the court directed them to approach KERC. The company filed a petition with KERC, seeking approval of the Supplementary PPA and the originally agreed tariff. While KERC upheld the original tariff of ₹7.47 per kWh, it rejected the extension of 180 days, citing that the delay could not be justified under force majeure clauses or the terms of the PPA.

Following this decision, HESCOM issued a letter demanding ₹12.05 crore in liquidated damages from Hero Future Energies for the delay in commissioning. This amount was partially recovered through deductions from energy bills, prompting the company to approach the Appellate Tribunal for Electricity (APTEL) for relief.

Hero Future Energies argued that similar delays had been treated differently in other cases, and the extension granted by HESCOM should be considered valid. They emphasized that the delay occurred due to KERC’s approval process and procedural issues, and not due to any default on their part. They sought restitution and cancellation of the liquidated damages.

The tribunal acknowledged that delays in approval by the regulator could justify time extensions and that natural justice requires giving the developer a proper opportunity to explain the delays. The tribunal found merit in Hero’s claim for part of the extension and noted that denying the full 180-day extension without a hearing was unjust.

 

  • Related Posts

    Solex Energy Subsidiary Approves INR 150 Crore Convertible Debenture Issue

    Solex Energy Limited has announced that its wholly owned subsidiary, Solex New Energy Private Limited, has approved a fundraising proposal worth ₹150 crore through the issuance of compulsorily convertible debentures…

    NTPC Appoints Diwakar Nath Misra As Government Nominee Director To Its Board

    NTPC Limited has announced the appointment of Shri Diwakar Nath Misra as a Government Nominee Director on its Board, following an official order issued by the Ministry of Power on…

    Have You Seen?

    Credibility and capital key to scaling-up new helium production

    • October 21, 2026
    Credibility and capital key to scaling-up new helium production

    Russia to Send First Diesel Tanker to U.S. on Thursday

    • October 21, 2026
    Russia to Send First Diesel Tanker to U.S. on Thursday

    Higher Oil Availability Pressures Middle East Crude Benchmarks

    • October 21, 2026
    Higher Oil Availability Pressures Middle East Crude Benchmarks

    Agency Says India Coal-Fired Units Running Critically Low on Fuel as Power Demand Soars

    • October 21, 2026
    Agency Says India Coal-Fired Units Running Critically Low on Fuel as Power Demand Soars

    Set it and forget it: Automated electrolyte management in trace oxygen analysis

    • October 21, 2026
    Set it and forget it: Automated electrolyte management in trace oxygen analysis

    Semiconductor helium demand to reach 2.2 Bcf by 2028

    • October 21, 2026
    Semiconductor helium demand to reach 2.2 Bcf by 2028

    UK Approves Jackdaw Gas Field as Energy Crisis Deepens

    • October 21, 2026
    UK Approves Jackdaw Gas Field as Energy Crisis Deepens

    Morgan Stanley: Global Fuel Market Will Stay Tight Through Mid-2027

    • October 21, 2026
    Morgan Stanley: Global Fuel Market Will Stay Tight Through Mid-2027

    Japan’s Trade Deficit Doubles as Hormuz Crisis Hikes Energy Import Costs

    • October 21, 2026
    Japan’s Trade Deficit Doubles as Hormuz Crisis Hikes Energy Import Costs

    Conversion costs outweigh hydrogen shipping costs: Wood

    • October 21, 2026
    Conversion costs outweigh hydrogen shipping costs: Wood