GERC Reviews Petitions From Four Solar Developers Seeking Extensions For Over 7.5 MW Projects In Gujarat

Representational image. Credit: Canva

The Gujarat Electricity Regulatory Commission (GERC) is currently reviewing four separate petitions from solar project developers who are requesting extensions for the commissioning of evacuation lines and metering systems for their respective ground-mounted solar power plants. All the petitioners claim that the delays they have experienced were due to circumstances beyond their control, and they are seeking relief from the Commission. The projects, with capacities ranging from 0.9 MW AC to 2.48 MW AC, are all located in Gujarat and are part of the state’s broader push towards solar power adoption.

In the first case, Pratistha Prints, the petitioner behind a 0.9 MW AC capacity solar project, approached the Commission seeking a time extension. The petitioner stated that the project has been delayed due to right-of-way issues, unexpected heavy rainfall, and flooding. In addition, the petitioner pointed to regulatory changes in banking rules and a hike in solar module prices as key contributing factors to the delay. According to Pratistha Prints, these challenges were outside of their control, and they are requesting that the Commission consider these factors when assessing their request. The Commission has directed the petitioner to provide supporting documents detailing the causes of the delay. Gujarat Energy Transmission Corporation Ltd. (GETCO) and Dakshin Gujarat Vij Company Limited (DGVCL) have been named as respondents in the case. The next hearing has been scheduled for May 2, 2025.

In a similar petition, Pragati Fashions has requested an extension for their 1.80 MW AC solar power plant project. Like the previous petitioner, Pragati Fashions cited multiple reasons for the delay. These included right-of-way clearance issues, severe weather conditions such as heavy rain and flooding, complications related to Guaranteed Technical Particulars (GTP) approval, changes in banking policies, and a sharp increase in the cost of solar modules. The petitioner argued that these conditions severely hindered project implementation. The GERC has asked Pragati Fashions to submit evidence supporting their claims. GETCO and DGVCL are again the named respondents, and the next hearing for this matter is also scheduled for May 2, 2025.

The third petition was filed by ARMO Synthetics Pvt. Ltd. for their 2.41 MW AC ground-mounted solar project. The company is seeking an extension of the deadline for the transmission line and metering system, citing delays similar to those faced by the other petitioners. These include problems in obtaining right-of-way clearance, extreme weather events such as heavy rainfall and flooding, new banking regulations, and issues with GTP approvals. Additionally, ARMO Synthetics has requested the Commission to put a hold on the encashment of their bank guarantee, arguing that the delays were not due to negligence or inaction on their part. The Commission has instructed ARMO Synthetics to submit all relevant documents that explain the reasons for the delay. GETCO, GEDA (Gujarat Energy Development Agency), GUVNL (Gujarat Urja Vikas Nigam Limited), and DGVCL are listed as respondents. The next hearing is scheduled for May 2, 2025.

The fourth petition involves Ruchi Twisters Private Limited, which is developing a 2.48 MW AC solar project. This petitioner has also requested additional time to complete the commissioning of the evacuation line and metering system. Ruchi Twisters has attributed the delay to several factors including right-of-way clearance problems, intense rainfall and flooding, banking policy changes, and delays in securing GTP approvals. Like ARMO Synthetics, Ruchi Twisters has also asked the Commission to prevent the encashment of their bank guarantee. The Commission has asked them to provide detailed documents explaining the situation. GETCO, GEDA, GUVNL, and DGVCL are listed as parties in the case. The next hearing is set for May 1, 2025.

All four cases indicate common challenges faced by solar project developers in Gujarat, especially regarding weather conditions, regulatory changes, and administrative approvals. The outcomes of these cases could influence how future delays are treated in the renewable energy sector.

 

  • Related Posts

    Driving the Vision of Atmanirbhar Bharat: Durasol Energi at Maha Urja Expo 2026

    Born in India. Made for the World. Guided by its vision of “Let’s Improve the Quality of Life,” Durasol Energi, a global brand of Intelenergi Global Pvt. Ltd., is committed…

    First Solar Conducts EPC-Installer Training for PM KUSUM Programme in India

    First Solar conducted an EPC Training Meet in India on 30 and 31 July 2026 in Karnataka. The event brought together founders, project managers, design engineers, and installation professionals from…

    Have You Seen?

    Repairing Qatar LNG ‘to cost $5.8bn and take up to a year’

    • September 17, 2026
    Repairing Qatar LNG ‘to cost $5.8bn and take up to a year’

    Oil Prices Slide as Saudi Arabia Reroutes Crude via Oman

    • September 17, 2026
    Oil Prices Slide as Saudi Arabia Reroutes Crude via Oman

    Soaring LNG Prices Push Asian Demand Toward Second Annual Decline

    • September 17, 2026
    Soaring LNG Prices Push Asian Demand Toward Second Annual Decline

    India Pushes Back on U.S. Tariff Threat Over Russian Oil

    • September 17, 2026
    India Pushes Back on U.S. Tariff Threat Over Russian Oil

    Winter is Coming for Diesel

    • September 17, 2026
    Winter is Coming for Diesel

    Rift Helium reports $1.78m loss ahead of Tanzania helium drilling programme

    • September 17, 2026
    Rift Helium reports $1.78m loss ahead of Tanzania helium drilling programme

    South Korea’s YPP eyes green hydrogen project in Kazakhstan

    • September 17, 2026
    South Korea’s YPP eyes green hydrogen project in Kazakhstan

    Air Products to build $250m plant to supply Arizona semiconductor expansion

    • September 17, 2026
    Air Products to build $250m plant to supply Arizona semiconductor expansion

    UK offshore gas hub weighs second turquoise hydrogen tech provider

    • September 17, 2026
    UK offshore gas hub weighs second turquoise hydrogen tech provider

    India semiconductor sector boosted by new plants and investment

    • September 17, 2026
    India semiconductor sector boosted by new plants and investment