Manufacture of ITER superconducting magnet system completed

Wednesday, 7 May 2025

Manufacture of ITER superconducting magnet system completed
The central solenoid module (Image: General Atomics)

Each 4-metre-tall, 110-tonne cylindrical module is wound from about 6 kilometres of niobium-tin superconducting cable and requires more than two years of precision fabrication and verification. The final phase, in-factory testing, verifies performance by simulating conditions that the module will experience during operation at ITER.

US ITER and supplier General Atomics have announced the completion of testing of the sixth module at the General Atomics Magnet Technologies Center in Poway, California. 

The sixth production module, which is the last module required to complete the central solenoid stack, was subjected to a series of demanding tests including helium leak testing, high voltage insulation testing, cooldown to 4.5 K and charging to 48.5 kA followed by a series of tests designed to measure as-built performance of the superconductor.

Four central solenoid modules have already been delivered by US ITER and stacked on a dedicated assembly platform at the construction site in Cadarache, France. The fifth module is en route and the sixth will be shipped in the coming months.

Fabrication of a seventh module, which is to be used as a spare, remains to be finalised.

US ITER has also delivered the ‘exoskeleton’ support structure that will enable the central solenoid to withstand the extreme forces it will generate. The exoskeleton is comprised of more than 9000 individual parts, manufactured by eight US suppliers.

ITER’s magnetic system consists of toroidal and poloidal magnetic field coils, correction coils, and the central solenoid. This is the largest superconducting system ever created. The fully assembled pulsed magnetic system will weigh almost 3000 tonnes.

Thirty-three nations are collaborating to build ITER – the European Union is contributing almost half of the cost of its construction, while the other six members (China, India, Japan, South Korea, Russia and the USA) are contributing equally to the rest. Construction began in 2010 and the original 2018 first plasma target date was put back to 2025 by the ITER council in 2016. However, in June last year, a revamped project plan was announced which aims for “a scientifically and technically robust initial phase of operations, including deuterium-deuterium fusion operation in 2035 followed by full magnetic energy and plasma current operation”.

In addition to supplying the superconductor, Russia has manufactured and sent one of the six poloidal magnetic field coils – the PF1 coil – to the construction site.


The PF1 coil (Image: Rosatom)

“The magnetic system, the most complex and powerful ever created, is the basis, the foundation of the entire future installation – without it, the operation of ITER is basically impossible,” said Anatoly Krasilnikov, Director of the ITER Project Center (a Rosatom institution).

“Through joint efforts with international partners, we have successfully completed this stage, and this is our common, collective merit. Russia, our enterprises, took direct part in this process. We produced 120 tonnes of niobium-titanium superconductor (by the way, in close cooperation with Europe), as well as more than 17 km of niobium-tin superconductor.”

   

  • Related Posts

    AEP, Amazon and X-energy planning 12-SMR plant

    Tech giant Amazon is to support the project’s development through a funding agreement and through a long-term power purchase agreement “covering the costs of the facility and its operations for…

    Rosatom signs floating nuclear power deal for Indonesia

    Russia’s state nuclear corporation Rosatom said it signed the agreement during Russian Energy Week in Moscow to supply the power to the northern part of Halmahera Island in North Maluku.…

    Have You Seen?

    Podcast | Dry ice: demand, quality and customer trust

    • October 20, 2026
    Podcast | Dry ice: demand, quality and customer trust

    Seaweed offers alternative feedstock for 420GWh UK biomethane project

    • October 20, 2026
    Seaweed offers alternative feedstock for 420GWh UK biomethane project

    Pakistan’s Growth Slows as Hormuz Crisis Hits Industry

    • October 20, 2026
    Pakistan’s Growth Slows as Hormuz Crisis Hits Industry

    Qatar Offers Lebanon 2 Gas Plants and 20 Years of LNG Piped Through Syria

    • October 20, 2026
    Qatar Offers Lebanon 2 Gas Plants and 20 Years of LNG Piped Through Syria

    Brent Tops $110 as Tanker Attacks Threaten Persian Gulf Supply

    • October 20, 2026
    Brent Tops $110 as Tanker Attacks Threaten Persian Gulf Supply

    US lawmakers seek to boost bio-LNG demand in maritime sector

    • October 20, 2026
    US lawmakers seek to boost bio-LNG demand in maritime sector

    EU Policy Draft Softens Language on Arctic Drilling

    • October 20, 2026
    EU Policy Draft Softens Language on Arctic Drilling

    Canada’s Inflation Rises to 3.1% as Fuel Oil Prices Jump 58%

    • October 20, 2026
    Canada’s Inflation Rises to 3.1% as Fuel Oil Prices Jump 58%

    Podcast | Helium Super Summit preview: shortages, supply and new producers

    • October 19, 2026
    Podcast | Helium Super Summit preview: shortages, supply and new producers

    China’s Solar Exports Keep Falling as Beijing Mulls Export Controls

    • October 19, 2026
    China’s Solar Exports Keep Falling as Beijing Mulls Export Controls