UK parliament committee calls for speedier Sellafield clean-up

Thursday, 5 June 2025

UK parliament committee calls for speedier Sellafield clean-up
The Sellafield site (Image: ONR)

The Sellafield site – which houses more than 1000 buildings – is the largest nuclear complex in Western Europe. Sellafield’s nuclear facilities include those connected with the Magnox reprocessing programme, the Sellafield mixed-oxide fuel plant, the Thermal Oxide Reprocessing Plant, and nuclear waste treatment plants. It is also home to redundant facilities from defence work in the 1950s, which included making plutonium for nuclear weapons.

The Nuclear Decommissioning Authority (NDA) expects full site remediation at Sellafield will take until 2125, while the forecast cost of decommissioning the site has risen to GBP136 billion (USD176 billion). The NDA spent GBP2.7 billion at Sellafield in 2023-24, while the site earned GBP0.8 billion in income in the same year.

The Public Accounts Committee’s  finds that Sellafield Ltd has missed most of its annual targets for retrieving waste from several buildings on the site, including the Magnox Swarf Storage Silo (MSSS). The committee’s inquiry heard that the MSSS is the most hazardous building in the UK, and “as a result of Sellafield Ltd’s underperformance will likely remain extremely hazardous for longer”. The report seeks answers from government on how it will hold the NDA and Sellafield Ltd to account in mitigating the site’s greatest hazards.

“Sellafield Ltd’s performance in delivering major projects (such as new buildings to store waste or make it safe) has historically been very poor, with large cost increases and delays occurring all too frequently,” the report says. “There are signs of improvement – however given Sellafield’s track record, we are yet to be fully convinced that this is not another false dawn.”

The Public Accounts Committee warns of the impact that delays in the programme have on costs. In the long-term, waste will need to be stored in an underground Geological Disposal Facility (GDF). The committee finds that the date for the GDF has slipped from 2040 to the late 2050s, with every decade of delay meaning Sellafield could need to construct another storage building, each costing GBP500-760 million.

The Public Accounts Committee says the Department for Energy Security and Net Zero (DESNZ) “needs to do more to ensure that the site is decommissioned in a way that represents value for money for the taxpayer”. It says the estimated cost of decommissioning the site will rise “if work is deferred for short term affordability reasons, or if the GDF is delayed. Conversely, there may be opportunities to reduce the cost of decommissioning Sellafield and the other NDA sites”. The committee said DESNZ also “needs to make sure that Sellafield Ltd and the NDA are implementing a corporate culture in which all staff feel safe and confident to speak up, particularly given the safety critical nature of the industry”.

“As with the fight against climate change, the sheer scale of the hundred-year timeframe of the decommissioning project makes it hard to grasp the immediacy of safety hazards and cost overruns that delays can have,” said Sir Geoffrey Clifton-Brown, Chair of the committee. “Every day at Sellafield is a race against time to complete works before buildings reach the end of their life. Our report contains too many signs that this is a race that Sellafield risks losing.

“It is of vital importance that the government grasp the daily urgency of the work taking place at Sellafield, and shed any sense of a far-off date of completion for which no-one currently living is responsible. Sellafield’s risks and challenges are those of the present day. There are some early indications of some improvement in Sellafield’s delivery which our report notes. Government must do far more to hold all involved immediately accountable to ensure these do not represent a false dawn, and to better safeguard both the public purse and the public itself.”

The Public Accounts Committee examines the value for money of government projects, programmes and service delivery. Drawing on the work of the National Audit Office, the committee holds government officials to account for the economy, efficiency and effectiveness of public spending.

   

  • Related Posts

    Nuclear central in France’s latest energy strategy

    The Multiannual Energy Programme (PPE) is not a piece of legislation, but presents the trajectory to be followed over the next decade in terms of energy policy. It has two…

    Final Investment Decision taken for Romanian SMR project

    Romania’s small modular reactor (SMR) project is aiming for 462 MWe installed capacity, using NuScale technology with six modules at the former coal plant site at Doicești – about 90…

    Have You Seen?

    Exxon Mobil Can Sue California Attorney General for Defamation Over Recycling, Judge Rules

    • February 14, 2026
    Exxon Mobil Can Sue California Attorney General for Defamation Over Recycling, Judge Rules

    Enfinity Expands $183M Bond Facility with Eiffel to Scale Solar and BESS in U.S. and Europe

    • February 14, 2026
    Enfinity Expands $183M Bond Facility with Eiffel to Scale Solar and BESS in U.S. and Europe

    Saatvik Green Energy to Acquire 49% Stake in Intelligent Hydel Solutions, Enters IPP Segment

    • February 14, 2026
    Saatvik Green Energy to Acquire 49% Stake in Intelligent Hydel Solutions, Enters IPP Segment

    US Drillers Cut Three Oil Rigs, Add Three Gas Rigs, Leaving Weekly Count Unchanged, Says Baker Hughes

    • February 13, 2026
    US Drillers Cut Three Oil Rigs, Add Three Gas Rigs, Leaving Weekly Count Unchanged, Says Baker Hughes

    Caturus Signs LNG Supply Deal with Saudi Aramco

    • February 13, 2026
    Caturus Signs LNG Supply Deal with Saudi Aramco

    India Explores Gas Power Boost to Stabilize Grid During Peak Hours

    • February 13, 2026
    India Explores Gas Power Boost to Stabilize Grid During Peak Hours

    Enbridge Reports Record 2025 Financial Results, Reaffirms 2026 Financial Guidance, and Grows Secured Backlog to $39 Billion

    • February 13, 2026
    Enbridge Reports Record 2025 Financial Results, Reaffirms 2026 Financial Guidance, and Grows Secured Backlog to $39 Billion

    Pentagon to Move Carrier to Middle East From Caribbean, Officials Say

    • February 13, 2026
    Pentagon to Move Carrier to Middle East From Caribbean, Officials Say

    India’s Reliance Wins US Licence for Venezuelan Oil, Sources Say

    • February 13, 2026
    India’s Reliance Wins US Licence for Venezuelan Oil, Sources Say

    US Allows Oil Majors to Broadly Operate in Venezuela, New Energy Investments

    • February 13, 2026
    US Allows Oil Majors to Broadly Operate in Venezuela, New Energy Investments