GERC Reviews Plea For Solar Project Commissioning Extension Amid Grid Connectivity Delays In Gujarat

Representational image. Credit: Canva

Anu Santosh Prints Pvt. Ltd., a company based in Surat, Gujarat, filed a petition before the Gujarat Electricity Regulatory Commission (GERC) seeking an extension of time for commissioning a 1.475 MW AC capacity ground-mounted solar power project. The petition was filed under Section 86 of the Electricity Act, 2003, in conjunction with the Gujarat Renewable Energy Policy, 2023, relevant GERC regulations, and a tariff order dated August 31, 2024. The company also submitted an interlocutory application seeking interim relief to prevent the encashment of the bank guarantee submitted to Dakshin Gujarat Vij Company Limited (DGVCL), the third respondent in the matter.

The petition was taken up for hearing on May 27, 2025. During the hearing, the counsel representing Gujarat Energy Transmission Corporation Limited (GETCO), the first respondent, requested three weeks’ time to file a consolidated reply to the main petition and the interlocutory application. The request was not objected to by the petitioner’s counsel. As a result, the Commission granted GETCO three weeks to submit its reply and directed that a copy be provided to the petitioner. Following the reply, Anu Santosh Prints Pvt. Ltd. was given one week to file a rejoinder, if required.

The legal representative for the petitioner stated that the delay in commissioning the solar power project was primarily due to pending work on the evacuation line, bay structures, and metering system that needed to be completed by GETCO. These components are essential for connecting the solar power project to the transmission grid.

The Commission noted the parties’ submissions and allowed the timelines as requested. Since the petition was already listed for hearing, the application seeking urgent listing (IA No. 36 of 2025) was considered satisfied and accordingly disposed of.

The next hearing for the matter is scheduled for June 26, 2025, at 11:30 a.m. The Commission directed all parties to complete their pleadings before the said date.

This matter is critical because it reflects the procedural and coordination challenges that small-scale solar power developers face when trying to commission projects under state-level renewable energy policies and grid regulations.

 

  • Related Posts

    GameChange Energy Technologies Acquires eBOS Division From Terrasmart, Expanding Fully Integrated Module-To-Grid Solar Solutions

    GameChange Energy Technologies, a global infrastructure firm delivering module-to-grid energy solutions, has announced the acquisition of the Electrical Balance of Systems (eBOS) division from Terrasmart, a unit of Gibraltar Industries.…

    Recurrent Energy Completes Sale Of 200 MWh Fort Duncan Battery Storage Facility To Hunt Energy Network, With Revenue Recognized By Canadian Solar In Q1 2026

    Representational image. Credit: Canva Recurrent Energy, a subsidiary of Canadian Solar Inc. and a leading global developer, owner, and operator of solar and energy storage assets, has announced the successful…

    Have You Seen?

    Eni Set to Approve Two Gas Projects Offshore Indonesia

    • February 24, 2026
    Eni Set to Approve Two Gas Projects Offshore Indonesia

    Russia’s Dark Oil Web Exposed in Major UK Sanctions Escalation

    • February 24, 2026
    Russia’s Dark Oil Web Exposed in Major UK Sanctions Escalation

    Oil Tanker Rates Surge to Six-Year High

    • February 24, 2026
    Oil Tanker Rates Surge to Six-Year High

    US Natgas Prices at Waha Hub in Texas in Negative Territory for Record 12th Day

    • February 24, 2026
    US Natgas Prices at Waha Hub in Texas in Negative Territory for Record 12th Day

    Messer launches ASU at copper recycling site in Germany

    • February 24, 2026
    Messer launches ASU at copper recycling site in Germany

    India’s Oil Import Dependence Climbs to Nearly 89% as Domestic Output Lags

    • February 24, 2026
    India’s Oil Import Dependence Climbs to Nearly 89% as Domestic Output Lags

    Woodside Warns LNG Glut Fears May Be Overstated

    • February 24, 2026
    Woodside Warns LNG Glut Fears May Be Overstated

    Andion CH4 Renewables €67m credit line will spur Italy and Sweden growth

    • February 24, 2026
    Andion CH4 Renewables €67m credit line will spur Italy and Sweden growth

    Portugal probes proposed Linde acquisition of Acaíl

    • February 24, 2026
    Portugal probes proposed Linde acquisition of Acaíl

    Oil Prices Hover Near Seven-Month Highs on US-Iran Tensions

    • February 24, 2026
    Oil Prices Hover Near Seven-Month Highs on US-Iran Tensions