GERC Reviews 25 MW Hybrid Project’s Plea For Extension And Temporary Use Of 220 kV Bay

Representational image. Credit: Canva

M/s OPWIND Energy Pvt. Ltd. filed a petition before the Gujarat Electricity Regulatory Commission (GERC) seeking an extension of time for the construction of power evacuation infrastructure and the temporary use of a spare 220 kV bay at the Kalavad sub-station. The company is setting up a 25 MW wind-solar hybrid power project and wants to use the spare bay until December 31, 2025. The company argued that the delay in infrastructure work requires more time and that permission to use the existing infrastructure temporarily would help them proceed with commissioning.

The petition was filed under Section 86 (1)(c), (e), and (f) of the Electricity Act, 2003, along with relevant regulations under the GERC (Conduct of Business) Regulations, 2004. OPWIND also filed an Interlocutory Application under Section 94(2) of the Electricity Act, seeking an interim stay and injunction against a letter issued by the Gujarat Energy Transmission Corporation Limited (GETCO) on February 18, 2025, which may have restricted their access to infrastructure at the Kalavad sub-station.

The petitioner referred to an earlier order by the Commission in a similar case involving M/s Morjar Renewables Pvt. Ltd., where temporary use of infrastructure was allowed. Based on this, OPWIND requested the Commission to provide similar relief and also sought one week to file a rejoinder to GETCO’s reply.

GETCO, represented by its legal counsel, stated that it had already filed its reply and objected to the petitioner’s request for temporary use of the 220 kV bay. GETCO argued that OPWIND Energy has no vested rights to use the infrastructure and hence the bay cannot be granted for use without formal allocation or completion of necessary construction. However, GETCO did not object to the admission of the petition itself and agreed that the matter could be scheduled for the last week of June 2025.

After hearing both sides, the Commission noted that GETCO’s reply had been submitted and the petitioner was given time to submit its rejoinder within a week. The Commission directed both parties to complete all pleadings before the next hearing date. The matter has now been scheduled for further hearing on June 26, 2025, at 11:30 a.m. Both parties agreed on the hearing date.

The Commission has not passed any interim relief or final decision in this hearing but ensured that procedural fairness is maintained. The case will now move forward after the parties complete their respective submissions, and a decision will be made based on the arguments presented in the next hearing.

 

  • Related Posts

    Waaree Renewable Technologies Secures LOA for 291 MWp Solar PV and 280 MWh BESS Project

    Waaree Renewable Technologies Limited (WRTL), a subsidiary of Waaree Energies Limited, has received a Letter of Award (LOA) from one of India’s thermal power generating companies for the development of…

    Latin America’s Energy Storage Capacity Set to Reach 34 GW by 2035: Wood Mackenzie

    Latin America’s energy storage market is entering a period of rapid expansion, with cumulative energy storage capacity projected to increase from 2.5 GW in 2025 to 34 GW by 2035,…

    Have You Seen?

    OMV Petrom receives additional 35MW of electrolysers at clean fuel facility

    • August 28, 2026
    OMV Petrom receives additional 35MW of electrolysers at clean fuel facility

    Bangladesh LNG expansion could drive $8.5bn annual import bill, IEEFA warns

    • August 28, 2026
    Bangladesh LNG expansion could drive $8.5bn annual import bill, IEEFA warns

    Waaree Renewable Technologies Secures LOA for 291 MWp Solar PV and 280 MWh BESS Project

    • August 28, 2026
    Waaree Renewable Technologies Secures LOA for 291 MWp Solar PV and 280 MWh BESS Project

    Latin America’s Energy Storage Capacity Set to Reach 34 GW by 2035: Wood Mackenzie

    • August 28, 2026
    Latin America’s Energy Storage Capacity Set to Reach 34 GW by 2035: Wood Mackenzie

    Meritus strengthens Southern California team

    • August 28, 2026
    Meritus strengthens Southern California team

    Jan De Nul enters North Sea CCS market

    • August 28, 2026
    Jan De Nul enters North Sea CCS market

    Søby Solar Park to Supply Renewable Power to Four Companies Under Fixed-Price PPAs

    • August 28, 2026
    Søby Solar Park to Supply Renewable Power to Four Companies Under Fixed-Price PPAs

    IEEFA Finds Renewables Cheaper Than Coal in Indonesia, Urges Least-Cost Power Planning and 100 GW Solar Integration

    • August 28, 2026
    IEEFA Finds Renewables Cheaper Than Coal in Indonesia, Urges Least-Cost Power Planning and 100 GW Solar Integration

    Siemens Energy to spin off Transformation of Industry with view to sale

    • August 28, 2026
    Siemens Energy to spin off Transformation of Industry with view to sale

    Suzlon Breaks Ground on 1,325 MW Wind Projects in Andhra Pradesh, Targets INR 10,500 Crore Investment

    • August 28, 2026
    Suzlon Breaks Ground on 1,325 MW Wind Projects in Andhra Pradesh, Targets INR 10,500 Crore Investment